Special Rept SR-92-001-00:on 921010,inservice Eddy Current Exam of SG Tubing Completed,Per 10CFR50.36(c)(2).Total Number of Tubes Have Been Plugged in SG Shown as Listed
ML20116B212
Person / Time
Site: Waterford Entergy icon.png
Issue date: 10/23/1992
From: Packer D
ENTERGY OPERATIONS, INC.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
SR-92-001-00, SR-92-1, W3F1-92-0432, W3F1-92-432, NUDOCS 9211020105
Download: ML20116B212 (2)


Text

'

1 g ENkOIhy Operations

' gyyradons. im, fn m

,i.,

D.F. Packer W3f1-92-0432 A4.05 OA October 23, 1992 U.S. Nucicar Regulatory Commission Attn:

Document Control Desk Wo bioyion, D.C.

20555

Subject:

Waterford 3 SES Docket No. 50-382 License No. NPf-38 Reporting of Special Report Gentlemen:

Attached is Special Report Number SR-92-001-00 for Waterford Steam Electric Station Unit 3.

This Special Report is submitted per 10CfR50.36(c)(2) and Technical Specifications 4.4.4.5.a and 6.9.2.

Very truly yours,

)

/

({ p n,d -N gu 9 WVI D.F. Packer General Manager - Plant Operations DFP/BRL/ssf Attachment cc:

J.L. Milhoan, NRC Region IV G.L. Florreich J.T. Wheelock - INP0 Records Center R.B. McGehee N.S. Reynolds NRC Resident inspectors Office Administrator - LRPD i

i I

L

' '\\t w

v-g

- - v

1

)

4 SPECIAL REPORT

(

/

oR-92-001-00 1

i Steam Generator Eddy Current Examination

{

(5thRefueling) i l-Inservice Eddy Current examination of the Steam Generator (5/G) tubing was j

completed at Waterford Steam Electric Station Unit 3 on October 10, 1992, l

This report is submitted in accordance with Technical Specification (IS)

J 4 4.4.5.a. which requires reporting the number of tubes pluaged in each i

j S/G within 15 days of completing inservice inspection (ISI) of 5/G tubes f

pursuant to TS 6.9.2.

A follow-up report will be submitted in 6ccordance i

with iS 4.4.4.5.b by October 10, 1993.

I The total number of tubes which have been plugged in each S/G are shown i

below:-

l S/Gfl S/G #2 i

l Manufacturing /Preservice 6

20 i

Batwing (Preventive Plugging) 149 149 i

l First Refueling 0

1 l

Second Refueling 3

0 i

Third Refueling 10 9

l fourth Refueling

[

- Preventive Plugging 4

5 l

As a Result of ECT

- Batwing Preventive Plugging 156 156 2

Fifth Refueling 4

5 i

Total:

332 345.

l PLANT CONTACT l

J.E. Howard, Procurement / Programs Engineering Manager (504) 739-6327 4