Informs That No Further Action Planned for Open Issues Other than Entry Into Commitment Tracking Sys.Project Shutdown Rendered Technical Resources Unavailable.Related Correspondence
ML20116A122
Person / Time
Site: Midland
Issue date: 04/19/1985
From: Jackie Cook
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
CON-#285-664 OL, OM, NUDOCS 8504240363
Download: ML20116A122 (2)


Text

(, M -

Ed 4 4R

.ocar====

PR00. & U% FA* _

[A cp fr C.

P OV'"*

Con Jernet W Cook

, I.

C0hh,y,D s;,

Ykr Msdent - %g *

'ng and Construction g

n ceneral offices: 1945 West Pernell Road, Jackson, MI 49201 + (517) 788 0453 I 8W 2341:30 April 19, 1985 g

VICf.

Mr J G Keppler, Regional Administrator U S Nuclear Regulatory Commission Region III 799 Roosevelt Road Glen Ellyn, IL 60137 MIDLAND ENERGY CENTER GWO 7020 BROOKHAVEN NATIONAL LABORATORY REPORT CONCERNING WELDING PROGRAM ALLEGATIONS FILE 0505.2/0.4.2/UFI SERIAL 32225

REFERENCE:

(1) Charles Norelius letter to J W Cook, dated March 22, 1985 transmitting BNL Report on Welding Allegations, dated January 1985 Thank you for the BNL report on welding allegations attached to the referenced letter.

We are pleased to get a portion of the issues identified in the report closed.

We had been conducting detailed discussions prior to the project shutdown to support resolution of the issues. Technical resources are no longer available to further the investigation. For this reason we believe it impracticable to bring the remaining open issues to conclusion at this time. However, in the event of a Project restart we would pursue reinstituting a full technical investigation of all the issues still pending, as identified in your letter, I

and determine the most practical way to resolve them.

Therefore, we are taking no further action at this time on the open issues other than entering them into our commitment tracking system. At the time of l,

Project restart we will bring specific suggestions to the NRC Staff for resolution of each item, such as utilizing the CCP or IDVP or other alternate solutions.

JWC/WRB/lr CC RFWarnick, NRC Region III JJHarrison, NRC Region III RBlandsman, NRC Region III 8504240363 850419

'7)

PDR ADOCK 05000329 G

PDR

(

3 OC0485-07204A-MP01

2 0M/0L SERVICE LIST Mr Frank J Kelley Atomic Safety & Licensing Attorney General of the Appeal Board State of Michigan U S Nuclear Regulatory Commission Ms Carole Steinberg Washington, DC 20555 Assistant Attorney General Environmental Protection Division Mr C R Stephens (3) 720 Law Building Chief, Docketing & Services Lansing, MI 48913 U S Nuclear Regulatory Commission Office of the Secretary Washington, DC 20555 Mr Myron M Cherry, Esq Suite 3700 Ms Mary Sinclair Three First National Plaza 5711 Summerset Street Chicago, IL 60602 Midland, MI 48640 Mr Wendell H Marshall Mr William D Paton, Esq RFD 10 Counsel for the NRC Staff Midland, MI 48640 U S Nuclear Regulatory Commission Washington, DC 20555 Mr Charles Bechhoefer, Esq Atomic Safety & Licensing Atomic Safety & Licensing Board Panel Board Panel U S Nuclear Regulatory Commission U S Nuclear Regulatory Commission East-West Towers, Room E-413 Washington, DC 20555 Bethesda, MD 20014 Ms Barbara Stamaris Dr Frederick P Cowan 5795 North River Road 6152 N Verde Trail Rt 3 Apt B-125 Freeland, MI 48623 Boca Raton, FL 33433 Dr Jerry Harbour Mr Fred C Williams Atomic Safety & Licensing Isham, Lincoln & Beale Board Panel 1120 Connecticut Ave NW, Suite 840 U S Nuclear Regulatory Commission Washington, DC 20036 East-West Towers, Room E-454 Bethesda, ND 20014 Mr James E Brunner, Esq Consumers Power Company Mr M I Miller, Esq 212 West Michigan Avenue Ishan, Lincoln & Beale Jackson, MI 49201 Three First National Plaza 52nd Floor Chicago, IL 60602 Mr Steve Gadler, Esq Mr John Demeester, Esq 2120 Carter Avenue Dow Chemical Building St Paul, NN 55108 Michigan Division Midland MI 48640 Mr P Robert Brown Clark, Klein & Beaumont Ms Lynne Bernabei 1600 First Federal Bldg Government Accountability Project Woodward Ave 1901 Q Street, NW Detroit, MI 48226 Washington, DC 20009 CC0485-07204A-MP01