SUMMARY

Tha following report highlights the operating experience of Wolf Creek Generating Station for the month of April, 1996. This report is being provided pursuant to Technical Specification 6.9.1.8.

I.

SUMMARY

OF OPERATING EXPERIENCE The unit began the month of April, 1996, in Mode 4. The unit was in process of start-up procedures from Refuel VIII. The unit entered Mode 3 at 2312, April 2, 1996; Mode 2 at 2315 on April 5, 1996, and Mode 1 at 0550 April 7, 1996. The generator was synchronized to the grid at 1113, April 7, 1996. The plant reached Mode 1, 100% power at 0430, April 11, 1996. The unit operated at approximately 100% power until commencing turbine / generator load decrease at 2106, April 19, 1996. At 0536, April 20, 1996, the gtnerator output breakers were opened, and at 0950, April 20, 1996, the unit was in Mode 2, approximately 5% power, to balance the turbine. Upon completion of turbine balancing work, the unit commenced increasing power. The unit reentered Mode 1 at 1458, and the generator was synchronized to the grid at 2145, April 20, 1996. The unit reached Mode 1, 100% power, at 0000, April 22, 1996, and remained at that level t.hrough the end of April, 1996.

II. MAJOR SAFETY RELATED MAINTENANCE ACTIVITIES NONE l

l l

Wolf Creek Generating Station Monthly Operating Report April, 1996 9607170100 960712 Page 2 of 6 PDR ADOCK 05000482 R PDR l I

. kttachmint 2 to CO 96-0058

. OPERATING DATA "iPORT

~'

  • DOCKET NO. 50-412 WOLF CREEK GENERATING STATION WOLF CREEK NUCLEAR OPERATING CORPORATION DATE 5-9-96 TELEPHONE 316-364-8831 OPERATING STATUS
1. Reporting Period: April, 1996 Gross Hours in Reporting Period: 719
2. Currently Authorized Power Level (MWt) : 3565 Max. Depend. Capacity (MWe- 1167 Net) :

Design Electrical Rating (MWe-Net) : 1170

3. Power Level to Which Restricted - (If Any) (MWe-Net) : N/A

.4. Reasons for Restriction (If Any) : N/A l

This Month Yr. to Date Cumulative

5. Number of Hours Reactor was Critical 593.9 1,293.5 75,910.2 l

l

6. Reactor Reserve Shutdown Hours 0.0 0.0 339.8 l
7. Hours Generator on Line 548.7 1,248.3 75,028.0
8. Unit' Reserve Shutdown Hours 0.0 .0.0 0.0
9. Gross Thermal Energy Generated (MWh) 1,784,195 4,265,894 249,607,565
10. Gross Electrical Energy Generated (MWh) 615,248.0 1,478,444 86,737,364
11. Net Electrical Energy Generated (MWh) 581,521.0 1,380,875 82,817,726
12. Reactor Service Factor 82.6% 44.6%- 81.2% l
13. Reactor Availability Factor 82.6% 44.6% 81.6%

l

14. . Unit Service Factor 76.3% 43.0% 80.3%
15. Unit Availability Factor 76.3% 43.0% 80.3% l l
16. Unit Capacity Factor (Using MDC) 69.3% 40.8% 77.9%
17. Unit Capacity Factor (Using Design MWe) 69.1% 40.7%. 75.8%
18. Unit Forced Outage Rate 0.0% 8.1% 4.8%
19. Shutdowns Scheduled over Next 6 Months (Type, Date, and Duration of each) :

None

20. If Shut Down at End of Report Period, Estimate Date of Startup: N/A Wolf Creek Generating Station Monthly Operating Report April, 1996 Page 3 of 6

. - .. ,_.. . .- . .. ~ ~ - - _

, Attachment 2 to CO 96-0058 ,

UNIT SHUTDOWN AND POWER REDUCTIONS DOCKET NO.,50-48%

WOLF CREEK GENERATING STATION WOLF CREEK NUCLEAR OPERATING CORPORATION DATE*5-8-96 TELEPHONE 316-364-8831 Type METHOD OF SHUTTING F: FORCED DURATION REASON DOWN THE REACTOR CORRECTIVE ACTIONS / COMMENTS No Date S: SCHEDULED (Hours) (1) OR REDUCING POWER (2) 1 4/1/96 S 154.2 C 4 The unit remained in outage conditions for l Refuel VIII, and resumed operation on April 7, 1996 2 4/19/96 S 16.1 B 5 Power was reduced to 5%, Mode 2, 4/19/96, l

for turbine balancing.

SUtetARY: The unit began the month of April, 1996, in Mode 4. The unit was in process of start-up procedures from Refuel VIII. The unit entered Mode 3 at 2312, April 2, 1996; Mode 2 at 2315 on April 5, 1996, and Mode 1 at 0550 April 7, 199E. The generator was synchronized to the grid at 1113, April 7, 1996. The plant reached Mode 1, 100% power at 0430, April 11, 1996. The unit operated at approximately 100% power until commencing i turbine / generator load decrease at 2106, April 19, 1996. At 0536, April 20, 1996, the Main Generator output breakers were opened, and at 0950, April 20, 1996, the unit was in Mode 2, approximately 5% power, to balance the turbine. Upon completion of turbine balancing work, the unit commenced increasing power. The unit reentered Mode 1 at 1458, and the generator was synchronized to the grid at 2145, April 20, 1996. The unit reached Mode 1, 100% power, at 0000, April 22, 1996, and remained at that level through the end of April, 1996.

1) REASON: A: EQUIPMENT FAILURE (EXPLAIN) E: OPERATOR TRAINING AND LICENSE EXAMINATION (2) METHOD: 1. MANUAL B: MAINTENANCE OR TEST F: ADMINISTRATIVE 2. MANUAL SCRAM C: REFUELING G: OPERATIONAL ERROR (EXPLAIN) 3. AUTOMATIC SCRAM D: REGULATORY RESTRICTION H: OTHER (EXPLAIN) 4. CONTINUED
5. REDUCED LOAD l
9. OTHER Wolf Creek Generating Station Monthly Operating Report April, 1996 Page 5 of 6