Text
,
'"h Northeast i maen s -t, an% Cm037 Utilities System wrtheut utstie. ser+. comp.or P.O. Box 270 llartford, CT 06141-0270 (203) 665-5000 fN O p looq Docket No. 50-336 B15772 Re:
10CFR50.71(e) i 10CFR50.59 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555 I
Millstone Nuclear Power Station, Unit No. 2 j
Revision 14 to the Updated Final Safety Analysis Report j
And Addendum to Annual Report
?
j Northeast Nuclear Energy Company (NNECO) hereby submits, as Attachment 2, Revision
[T '
14 to the updated FSAR in the form of replacement pages as required. Pursuant to s
P 10CFR50.71(e)(2)(i), I certify that this revision accurately presents changes completed since our previous submittal that are necessary to reflect information and analyses submitted to the Commission or prepared pursuant to Commission requirements, as of December 31,1995. NNECO is currently performing an extensive review of the Millstone Unit No. 2 design and licensing bases which may result in significant changes to the FSAR.
In addition, as noted in the enclosed FSAR Update, Section 9.9.14, the information on Balance of Unit is currently under extensive design evaluation and is subject to change.
Changes from these efforts will be provided in a future submittal.
Pursuant to 10CFR50.71(e) and 10CFR50.4(b)(6), this transmittal consists of one original and ten copies. As stipulated in 10CFR50.71(e)(2)(ii): 'This submittal shall include an identification of changes made under the provisions of Section 50.59 but not previously submitted to the Commission." Pursuant to Section 50.59(b) and Technical Specification Section 6.9.1.4, with the exception noted in the following paragraph, such information is routinely submitted to the NRC as part of our annual reports, and is not included in this submittal. The most recent annual report was submitted on February 28,1996,W for the period January 1,1995, through December 31,1995.
(1) -
F. R. Dacimo letter to U.S. Nuclear Regulatory Commission, 'Wiillstone Nuclear Power Station, Unit Nos.1,2, and 3, Annual Report," dated February 28,1996.
9607170051 960628 l
k PDR ADOCK 05000336 I
l K
PDR 3
0634 2 REY. the
r-i U.S. Nuclear Regulatory Commission B15772/Page 2 Through an administrative oversight, a description of a change entitled " Containment isolation Valves / Penetrations" was omitted from the annual report submitted on February 28,1996." That description is provided herein as Attachment 1.
We trust that this information satisfies the requirements of 10CFR50.71(e).
If you have any questions, please contact Mr. J. S. Duddy at (203) 440-2082.
Very truly yours NORTHEAST NUCLEAR ENERGY COMPANY T. C. Feige6baum Executive Vice President and Chief Nuclear Officer i
cc-T. T. Martin, Region l Administrator D. G. Mcdonald, NRC Project Manager, Millstone Unit No. 2 i
P. D. Swetland, Senior Resident inspector, Millstone Unit No. 2 i