HAWKEYE VALVE & FITTING CO.
en 1260 West 11th Street P. O. Box 319 Milan, Illinois 61264 PHONE: (309) 787-6800 I
FAX: (309) 787-8198 SWAGELOK-companes September 30, 1992 N
TCT%tDn C *3 Harry Johnson J.51 Tima A Iowa Electric DAEC 3277 DAEC RD Palo, IA 52324
Dear Harry:
Per our phone conversation this afternoon concerning 10CFR part 21 on your safety related order # S69616.
As disc-ssed your part
- P115263 our SS-400-3 heat code #EBY has a posalble defect in the raw material.
Per your checking of your stock the 41 pes.
left in your stock did not have this the heat code.
As you stated you will check where the other 9 Pcs. went, and verify that heat code #EBY is not stamped on them.
Thank yr u f or your help s
on this matter.
Best regards.
Sincerely, T dd White l
9210140030 92o930 l
PDR ADOCK 05000331 S
i HAWKEYE VALVE & FITTING CO.
M 1260 West 11th Street P. O. Box 319 Milan, Illinois 61264 gw..
j PHONE: (309) 787-6800 SWAGELOK FAX: (309) 787-8198 companes Hawkeye Valve & Fitting Procedure for 10 C1R Part 21 defects and noncompliances.
If a part non conforms or is doffective for any reason it will be brought to the attention of the QA manager.
The QA manager will determine what order or ordera are affected by the the non conformance by entering the specific part # into the computer to determine which customers would be effected.
If the customer is a Nuclear power plant the following will be dones
&soJ cc,ard P h. Contact the Utility in question and let them know the fposa ility of a prcblem exists.
. #pp 2.
The NRC Chicago Region will be contacted at 1-708-790-5500 situation.
g,andinformedofthe p,
3.
A letter will follow to the NRC addressed to: Director, Office of Nuclear Reactor Regulation, U.S.
Nuclear Regulatory l pf' !b Commission, Washington, DC 20555.
c7 I
U A copy a 11 correspondence will be attached to the permanent order and copy of all correspondence will be faxed to said utility.
10 CFR Part 21 applies to all orders from Nuclear Utilities that are safety related which are processed by Hawkeye Valve &
Fitting.
It is permissible for the NRC or said Utility to come to our facility to inspect our records and docusarments concering any order where 10CFR applies.
By signing this sheet Hawkeye employees have been briefed and understand the actions & proceedures required to report a defect or non conformance for safety related orders where 10CFR Part 21 3
applies.
i i
i NAME DATE k
WWph/bir N/9k' /
A. x M...
"Hi C3sm C Ab
/U < k >
1 co w [w&1A-n ie m I W m e=-
7Vsy>p.
I 4
%QQQ,,
9 Cit AWFoltD FIYrING COMi%NY
>dit A DN. OltlO 44 tilla FRLJ A LENNON.
PHONE (2161248-4600 September 17, 1992 FAX (216) 349-5070 -
1 c=
Subject:
SS-400-3 Heat Code EBY
Dear Valued Customer:
We are writing in regards to the twagelok Union Tee, part number SS-400-3.
Our records show that yoe may-have purchaced some of thesc parts with the Heat Code #EBY.
A defect in the raw material that was undetectable has been discovered when the fitting was assembled for service. -The defect causes the fitting body to fail immediately upon pulling up the nut 1-1/4 turne The 20* flare of the fitting body splits longitudinally and will leak during system pressurization tests.
When the nut is removed, the crack is very visible.
i Unfortunately some of these parts were shipped to.our customers before the defect was discovered.
Fe have recalled i
all of'our world wide inventories of this heat and out inspection indicates a_ defect rate of less than 0.1%.
Our experience indicates that the defect is found upon installation and/or testing of the system.
j If you have any unused inventory of the part number SS-400-3 Heat Code EBY, we would like to replace it.
Crawford Fitting Company e