Provides Addl Details on long-term Program for Corrective Action Re Cable Tray Support Verification Program.Schedule for Walkdowns Encl
ML20113F729
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 01/16/1985
From: Gucwa L
GEORGIA POWER CO.
To: Stolz J
Office of Nuclear Reactor Regulation
References
NED-85-032, NED-85-32, NUDOCS 8501240117
Download: ML20113F729 (3)


Text

.. -;

~ Georgia Power Corrpany 333 Piedmont Avenue 4.

Atfanta. Georgia 30308.

Telephone 404 5264526 Mading Address:

Post Off.ce Box 4545 Attanta Georgia 30302 Georgia Power L T. Gacwa -

tre southem eiectic system uanager nuciear Engineenng NED-85-032 and Chief Nucleat Eng:neer January 16, 1985 Director of Nuclear Reactor Regulation Attention:

Mr. John F. Stolz, Chief Operating Reactors Branch No. 4 Division of Licensing U. S. Nuclear Regulatory Comission Washington, D.C.

20555 NRC DOCKETS 50-321, 50-366 OPERATING LICENSES DPR-57, NPF-5 EDWIN I. HATCH NUCLEAR PLANT - UNITS 1 AND 2 VERIFICATION OF 0PERABILITY OF-CABLE TRAY SUPPORTS Gentlemen:

Georgia Power Company's (GPC) letter NED 84-641 dated December 28, 1984, provided a status of our. cable tray support verification program.

Additional details on the long term program for corrective action are provided herein.

The objective of the program is to verify that the seismic qualification of safety-related' cable-tray supports meets the requirements contained in the appropriate _ Plant Hatch Final Safety Analysis Report (FSAR).

If a support can not be shown to meet these requirements, the support will be evaluated against the operability criteria included previously as an attachment to our letter NED 84-641 to determine reportability.

In addition, the support will be modified to meet FSAR criteria.

As indicated in letter NED 84-641, we have determined that a number of - supports do not presently meet FSAR requirements.. A modification schedule to bring these supports 'into ' compliance with the FSAR will be sent to you'by April 30, 1985.

8501240117 850116 PDR ADOCK 05000321 P

pcn 0

'le

r=

O^

^0 GeorgiaPower A Director cf Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Washington, D.C.

20555 January 16, 1985 Page 2 To ensure that the remainder of the cable tray supports meet FSAR requirements, a program consisting of the following activities will be conducted:

1.

Walkdown -

A plant walkdown will be conducted by experienced engineers to identify cable tray supports most susceptible to load control issues. The identified cable tray supports will be analyzed and a modification schedule prepared for supports which do not meet FSAR criteria.

The identified supports which do not meet FSAR criteria will be evaluated against the operability criteria to determine reportability.

2.

Follow-On Walkdowns -

The results of the initial walkdown will be evaluated to identify other cable tray supports which may require investigation and to determine.the scope of following walkdowns.

Follow-on walkdowns will be conducted based on the results of the initial walkdown.

The identified cable tray supports from each walkdown will be analyzed and a modification schedule prepared after each walkdann to bring identified supports into compliance with the FSAR.

The results of each

- follow-on walkdown will be evaluated to determine the need for additional walkdowns.

A schedule for these activities is attached for your information. As each follow-on walkdown is completed, a modification schedule will be sent to you.

GPC affirms that all cable tray supports evaluated to date meet the operability criteria attached to letter NED 84-641.

We further believe the program to examine supports and the load tracking program presently in place will ensure that -all supports will be brought into compliance with the FSAR.

Yours very truly, W f f:=

L. T. Gucwa KW/clh Attachment-cc:

J. T. Beckham, Jr.

H. C. Nix, Jr.

J. P.-0'Reilly (NRC-Region II)

Senior Resident Inspector room

e-GeorgiaPower b Director _of Nuclear Reactor Regulation U.-S.-Nuclear Regulatory Commission Washington, D.C.

20555 January 16, 1985 AlTACHMENT 1 VERIFICATION PROGRAM SCHEDULE Unit 1 Unit 2 1.

EVALUATION 0F SUPPORTS PREVIOUSLY IDENTIFIED

. Analysis Complete' March 31, 1985 March 31, 1985 Modification Plan Developed March 31, 1985 March 31, 1985 2.

INITIAL-WALKDOWN Walkdown Complete Completed March 31, 1985*

Walkdown Evaluation April 15,1985 N/A

.Walkdown Evaluation Schedule.

N/A April 15, 1985*

Modification Plan Developed

. April 30,1985 To Be Determined 3.

FOLLOW-0N WALKDOWN(S)

To Be Determined To Be Determines

  • Inaccessible area walkdown will be conducted during the 1985 outage-runs