Documents Completion of Fuel Load Related Activities Discussed W/Region Iii.Drawings in Control Room up-to-date. All nuclear,safety-related Concerns Documented by Safeteam Investigated & Considered Resolved
ML20112H280
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 03/19/1985
From: Jens W
DETROIT EDISON CO.
To: Norelius C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
NE-85-0465, NE-85-465, NUDOCS 8504020201
Download: ML20112H280 (1)


Text

[FRICRITYROUTING I

Qt Iyyg II7EYT W:yneP.Jens a

anons

~

Fermi 2

^-

6400 North r}ue H@way fIl N

{'gan 48?66 J

Nuclear operations March 19, 1985 NE-85-0465 Mr. Charles E. Norelius Director, Division of Reactor Projects Region III U. S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, Illinois 60137

Dear Mr. Norelius:

Reference:

Fermi 2 NRC Docket No. 50-341

Subject:

Completion of Select Fuel Load Related Activities The purpose of this letter is to document the completion of the following fuel-load related activities recently dis-cussed with the NRC Region III:

o The drawings in the Control Room are up-to-date.

No outstanding nonconformance reports (NCRs/DERs) are posted against these drawings.

o All nuclear, safety-related concerns documented by the SAFETEAM have been investigated and are considered to be resolved.

Responses have been sent to the origina-tors of these concerns.

If you have questions concerning this matter, please con-tact Mr. Lewis Bregni, (313) 586-5083.

Sincerely, cc:

Mr. P. M. Byron

-.k Mr. R. C. Knop j

Mr. J. M. Taylor 9

i USNRC Document Control Desk Washington, D.C.

20555 8504020201 850319

~

PDR ADOCK 05000341 P

PDR MAR 251985 166/ e ey