ML20112E905

From kanterella
Jump to navigation Jump to search
Confirms 850108 Telcon Re Util Commitment to Implement Mods, Per Generic Ltr 84-23, Prior to Restarting After Second Refueling Outage for Unit 1 & First Refueling Outage for Unit 2
ML20112E905
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 01/09/1985
From: George Alexander
COMMONWEALTH EDISON CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
References
9609N, GL-84-23, NUDOCS 8501150305
Download: ML20112E905 (1)


Text

Commonwealth Edison A

One First National Plaza. Chicago, Illinois C/

Address Reply to: Post Office Box 767 Chicago. Illinois 60690 January 9, 1985 Mr.. Harold R. Denton, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, DC' 20555

Subject:

LaSalle County Station Units 1 and 2 Supplementary Response to Generic Letter 84-23 NRC-Docket No. 50-373/374 References (a):

Generic Letter 84 D. G. Eisenhut letter to All BWR OLs dated October 26, 1984

-(b):

G. L. Alexander letter to H. R. Denton dated 12-04-84

Dear Mr. Denton:

On January 8, 1985, Jim Marshall of CECO. discussed our response, reference b, to Generic Letter 84-23 with Mr. A. Bournia.

As a result of that conversation, CECO. is committing to the following schedule:-

1.

The modifications for LaSalle Unit 1 shall be

~ implemented prior to restarting after the second refueling outage.

2. -The modifications for LaSalle Unit 2 shall be simplemented prior to restarting after the first refueling outage.-

Please= address any questions that you or your staff may have concerning our response to this office.. One signed original with fifteen copies are being-provided for your use.

Sincerely, h

I Greg Alexander Nuclear Licensing Administrator i

Attachment I-

'cc:.RIII Inspectors - LSC jg5 9609N PDR L

f,

<