FOIA Request for Documents Re Meetings Between Members of Nrr,J Kane,H Singh,F Rinaldi & Others Re Resolution of Diesel Generator Bldg & Implementation of Recommendations or Conclusions from Brookhaven 831021 Rept
ML20112E468
Person / Time
Site: Midland
Issue date: 05/22/1984
From: Garde B
GOVERNMENT ACCOUNTABILITY PROJECT
To:
NRC OFFICE OF ADMINISTRATION (ADM)
References
FOIA-84-425 NUDOCS 8501150155
Download: ML20112E468 (2)


Text

( .

GOVER'NMENT ACCOUNTADILITY PROJECT Institute for Policy Studies 1901 Que Street. N.W., Woshington. D.C. 20009 (202)234 9382 1

Freedorr of Information Act Request 1

W BNFORMATION Director - ACT REQl>EST Office of Administration [OM W gf Nuclear Regulatory Commission Washington, D.C. 20555 May 22, 1984 h k 8 U [

To Whom It May Concern:

Pursuant to the Freedom of Information Act (FOI A), 5 U.S.C. 5552, the Government Accountability Project (GAP) of the Institute for Policy Studies requests copies of any and all agency records and information, including but not limited to notes, letters, memoranda, drafts, minutes, diaries, logs, calendars, tapes, transcripts, summaries, interview reports, procedures, instructions, engineering analyses, drawings, files, graphs, charts, maps, photographs, agreements, handwritten notes, studies, data sheets, notebooks, books, telephone messages, computations, voice recordings, computer run-offs, any other data compilations, interim and/or final reports, status reports, and any and all other records relevant to and/or generated ~

in connection with meetings between the members of NRR, J. Kane, Harry Singh, Frank Rinaldi, and others regarding the resolution of the problems of the D.G.B. building and the implementation of recommendations / conclusions from the Brookhaven Report, October 21, 1983.

i This request includes all agency records as defined in 10 C.F.R. 59.3a(b) and the NRC Manual, Appendix 0211, Parts 1.A.2 and A.3 (approved October 8,1980) whether they currently exist in the NRC official, " working," investigative or other files, ,

or at any other location, including private residences.

If any records as defined in 10 C.F.R. $9.3a(b) and the NRC Manual, supra, and covered by this request have been destroyed and/or removed after this request, please provide all surrounding records, including but not limited to a list of all records which have been or are destroyed and/or removed, a description of the action (s) taken relevent to, generated in connection with, and/or issued in order to implement the action (s).

GAP requests that fees be waived, because " finding the information can be considered as primarily benefitting the general public." 5 U.S.C. 3552(a)(4)(a). GAP is a non-profit, nonpartisan public interest organization concerned with honest and open government. Through public outreach, the Project promotes whistleblowers as agents 8501150155 840522 PDR FOIA GARDEB4-425 PDR

_ . . _ _ _ _ _ _ _ _ _ _ _ _ _ J

,e ,

Director :

Office' of Administration of government accountability. Through its Citizens Clinic, GAP offers assistance to local public interest and citizens groups seeking to ensure +.he health and safety of their communities. The Citizens Clinic is currently assisting several citizens groups, local governments and intervenors in the mid-Michigan area concerning the construction of the Midland plant.

We are requesting the above information as part of an ongoing monitoring project on the adequacy of the NRC's efforts to protect public safety and health at nuclear power plants.

For any documents or portions that you deny due to a specific F0IA exemption, please provide an index itemizing and describing the documents or portions of documents withheld. The index should provide a detailed justification of your grounds for claiming each exemption, explaining why each exemption is relevant to the document or portion of the document withheld. This index is required under Vaughn v. Rosen (I),

484 F.2d 820 (D.C.Cir.1973), cert, denied, 415 U.S. 977 (1974).

We look forward to your response to this request within ten days.

i i

l l Billie Pirner Garde Citizens Clinic Director l

l i

!