ML20112D499
| ML20112D499 | |
| Person / Time | |
|---|---|
| Site: | Crane |
| Issue date: | 05/15/1984 |
| From: | Weiss E HARMON & WEISS, UNION OF CONCERNED SCIENTISTS |
| To: | Felton J NRC OFFICE OF ADMINISTRATION (ADM) |
| References | |
| FOIA-84-377 NUDOCS 8501140323 | |
| Download: ML20112D499 (1) | |
Text
HARMON, WEISS & JORDAN 2001 $ ST REET, N.W.
SUITE 430
%SHINoTON, D.G. cooos GAIL McGREEVY H ARMON TELEPHONE ELLYN R. WEISS (202)326 3500 WILLIAM S. JORDAN. til DIANE CURRAN DEAN R. TOUSLEY May 15, 1984 FREEDOM OF INFORMATION ACT REQUESI Joseph Felton, Director f
[ -f
~
}
Division of Rules and Records T
United States Nuclear Regulatory Commission Id [-/7-g gf Washington, D.C.
20555 Re:
Freedom of Information Act Request
Dear Mr. Felton:
On May 4,1984, the Commission issued CLI-84-4 a copy of which is enclosed.
On page 3 of that Order, the Commission states that it had conducted a "sua sponte" review "of the circumstances surrounding the implementation schedule for the seven long-term items" which GPU will not have completed prior to its scheduled restart of Three Mile Island Unit 1.
The Commission states further that it
" determined from its review of each of these items that the current schedule for completion is reasonable in view of the technical issues involved and.
because completion of required items at TMI-l at restart will be comparable to the schedule of completion at other B&W reactors."
Pursuant to the federal Freedom of Information Act, I hereby request copies of all documents considered by the Commission in its sua sponte review of these issues.
Very truly yours, bh
~.i Ellyn R. Weiss General Counsel Union of Concerned Scientists ERW:cpk 0501140323 840515 PDR FOIA WEISS84-377 PDR n