U A16 Docket No. 50-346- TOLEDO License No. NPF-3

!!()l!$()lY Roano P. C AMEE Serial No. 1-495

?l"m?'

uisi 259 5221 January 31, 1985 Mr. James C. Keppler, Regional Administrator Region III United States Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, Illinois 60137

Dear Mr. Keppler:

Your letter of October 1, 1984 (Log No. 1-1037), regarding the Performance Appraisal Inspection 50-346/84-19, identified specific weaknesses with the General Employee Training (GET) Program, at the Davis-Besse Nuclear Power Station, Unit No. 1.

Specifically, the Nuclear Quality Assurance Manual and AD 1807.00, Control of Conditions Adverse to Quality, place a high reliance on the ability of all employees to recognize and identify conditions adverse to quality, and this topic was not covered in the GET Program.

In Toledo Edison's letter of December 14, 1984 (Serial No. 1-488), a commit-ment was made to revise the GET Quality Assurance Module by February 1, 1985.

Included in the revision to the module is a discussion on the philosophy of quality assurance, including an individual's responsibility to the Quality Assurance Program.

This portion was scheduled to be presented by the President and Chief Operating Officer of the Toledo Edison Company. After the module script was written and approved by the President of the Company, he became unavail-able for photography and recording due to medical reasons. This has resulted in the inability to complete the revision to the module by the scheduled date.

The revised GET Quality Assurance module will be completed by February 28, 1985.