g la VIRGINIA ELECTRIC AND POWER COMPANY SURRY POWER STATION MONTHLY OPERATING REPORT REPORT NO. 84-10 1

APPROVED BY;M M f.fd

' STATION MANAGER i

1 4

l 1

8411150338 840930 fki DR ADOCK 05000280 gh PDR

I s

a Section

- P_ age

.=

d Operating Data Report - Unit #1 1

Operating Data Report - Unit #2 2

Unit Shutdowns and power Reductions - Unit #1 3

Unit Shutdowns and Power Reductions - Unit #2 4

Load Reductions Due to Environmental Restrictions - Unit #1 5

Load Reductions Due to Environmental Restrictions - Unit #2 6

7 Average Daily Unit Power Level-Unit #1 7

Average Daily Unit Power Level-Unit #2 8-9 Summary of Operating Experience Amendments to Facility' License or Technical Specifications 10 Facility Changes Requiring NRC Approval 11 Facility Changes That Did Not Require NRC Approval 12 Tests and Experiments Requiring NRC Approval 13 Tests and Experiments hat Did Not Require NRC Approval 13 Other Changes, Tests and Experiments 14 Chemistry Report 15 Description of AH Instances Where hermal Discharge Limits Were Exceeded 16 17-18 Fuel Handling Procedure Revisions hat Changed the Operating Mode Described in the FSAR 19 Description of Periodic Tests Which Were Not Completed Within the Time Limits Specified in Technical Specifications 20 e

w

.ya e

_,..-,ci

,.---,-,.m,,,,

-,%,.--_,e,-

11 s

4 i

Prge Section Maintenance of Safety Related Systems During Outage or

~~

22 Reduced Power Periods - Unit #1-Mechanical Maintenance' -

Maintenance of Safety Related Systems During Outage or 24 Reduced Power Periods - Unit #2 - Mechanical Maintenance Maintenance of Safety Related Systems During Outage or 26 Reduced Power Periods - Unit i1 - Dectrical Maintenance Maintenance of Safety Related Systems During Outage or

'28 Reduced Power Periods - Unit i2 - Dectrical Maintenance Maintenance of Safety Related Systems During Outage or 30 Reduced Power Periods - Unit #1-Instrument Maintenance.

Maintenance of Safety Related Systems During Outage or

'32 Reduced Power Periods - Unit #2 -Instrument Maintenance i

O t

a-e-.--.

-. =, m eye.,,ey.oe. _._

em,-

m

.r

.y

5 O

4!

I, i

WEPCO UPERAllNG DATA REPORT PR0 BRAN N0512662 10/08/84 11 25.21

~

DOCK (T NO.. 50-280 DATE SEPT. le 1984

(

COMPLFTED Bf

v. JDNE S

)

TELEPHONE 804-357-3184 OPERailNG STATUS

,):

i (.

1. dNil NAME SURRf UNli I

(

2. REPORilNG PERIDD SEPTEMBER 1984

)

3. LICENSED THERMAL *DWER -MWi-2441 4 N AME PL AIE R Af lMG -GRUSS MWE-847.5

(

5. DE 51'G4 ELE C Talc AL RA TING -NE T MWE-788

-)'

6.

M ARIMUM DEPEMoanLE C AP ACIT Y -GROSS MwE-818

7. MARIMJM DEPENDABLE CAPACITY -NET MW E -

775

-)

R.

IF CHANGE 5 00004 IN CAPACITV R Af l NGS

'(

-IIEMS 3 fpROJGH 7-SINCE L AST REPJRio GIVE REASDMS

):

l

('

i 9.

POWER LEVEL TO WHICH RE51RICTED, IF ANY

-NET MwE-l

(

10. RE ASONS F OR ME 5f R IC T IONS, IF ANY IHIS MONIH fR-10-DATE CUMMUL A T I VE Ff - ):

!(

IN 1EPORTING PERIDD 720 3 6575.0 103223.0

11. H0045
12. NUMBER 3F HOURS REACTOR WAS CRiflCAL 622. 5 5163.'3 64296.2 l

(

13. REACTOR RESERVE SHuiDOWN HOURS 0.0 93 3774.5 '

')

i

14. HOURS GENERATOR UN-LINE 622. 5 5100. 3 62967. 5

')-

(-

i

15. UNli RESERVE SHJiD0dN HDJR5 0.0 00 3736.2.

e i (

IS. 64055 THERMAL ENERGY GENERATED -NWH-1204039.3

' 11041699.9 1459FM64.2

):

17. GROSS ELECTRIC AL ENERGY GENER ATED -MWH-379720.0 2523505.0 46843348.0
19. NET EL Et tRIC AL ENERGf GENER A TED -MWH-355815.0 312:M10.0 44404'bE.0

').

(

19. UNIT SElvlCE FACfDR mi.St 77.6%

61.tM

20. UNif AvalL A81Llif F ACT04 E6.St

.17.64 64.6%

21. UNIT CAPAttif FACIOR'-USING MDC NET.

(

22. U1BT CAPAClif FACfDR'-USING DER NET-63.et
65. 75 55.55 g3 I
23. JNIT FORCFD Odi4GE MATE b.0 440%

89%

i

24. 540TUOWM5 SCHEDULED UVER NERT 6 MONTHS

-}.

(

-TYPE. DATE AND OURATION DF EACH-

25. IF 5 HOT D0d4 AT END OF REPOR T PER IOD,

)

(

ESIIMAff IIME 05 STARIUP 12-14-84

26. UNITS IN IEST STATUS FURECAST ACHIEVED

{

-PRIUR TO COMME 4CI AL OPER ATION-i INIIIAI CRITICALily INIllAL ELECTRICITY

  • J -

' ' LJ COMMERCIAL Operating r

1 e

/

s a

h,

.=

l ('

6 N

I s

i VEPCO QPERAilHG DATA REPORT PROGRAM N0512662 10/05/84 11 25 29 j (s DOCKEI NO.

50-285 UAIE SEPI. le 1984 (5

COMPLETED DV V. JONES IELEPHONE 804-357-3184 3PERATING SfaiUS

(%

l

1. J1tf NAME SURRY UNif 2 f-
2. REP 3RTING'PERIDO SEPTEMHFR 1984
1. L ILE NSED THERM AL POWER -MWT-244l 4 N AME PL AT E R A t LNG -b4055 MWE-847.5 l

(*

5. JE SIGN ELEC TRIC AL R AIING -NE T MWE-188

'6.

MARIMJM DEPENOABLE C AP AC l f Y -GROSS MwE-811 i

.f. MAEIMJM DEPENDABLE CAPAttiv -NET MwE -

if5

("

s8. IF CHANGES UCCUR IN CAPACITY R All >GS

-IIE MS 3 THR00GH 7-SIP *CE LA$f' REPORT, GIVE REASONS

(.

9. PowE R LEVEL T3 WHICH RESTRitiED. IF ANf

-NET MWE-

[

('

10. RE ASUN5 FOR RESTRICTION 5e IF ANY THIS MONTH VR-TO-DATE CUMMUL A tl VE ha
11. HauRS 11 REPORilNG PERIOD T20.0 65T5.0 100503 0
12. NJMBER OF HOURS REACTOR WA5 CRlitCAL 678.3 5765. 9 64336. 8

('

13. REatt04 4ESERVE 54Jf00wN HOUR 5 0.0 23.8 328 1 14 Hout S GE NER ATOR UM-LINE 670.7 5702. 3 63278.3

(

15. UNIT RESERVE 5Hof3JdN HOURS 0.0 0.0 0.0

(,

16. 64055 f HERMAL EMEtGV GENER ATE 0 -HhH.

1634208.3 13530672.4 148246545.3 i

II. Ltd55 ELECTRICAL ENERGf GENE R AICO -MwH-510765.0 4296550.0 48091409.0

18. NET ELEC TRIC AL ENERGY GENERATEU -MWH-484061.0 4070622.0 45577682.0
19. UNIT SERvlCE FACTOR
93. 25
86. 75 63.25 h(
20. UMlf AV AIL ABillif FACTOR 93.22 86.75 63.25
21. U1tf CAPatlif FACfDR -USING N00 NET-86.75 79.94 58.75 C
22. J4tf CAPAClif FACTOR -USING DER NET-e6.34 78.65 57.Em
23. UMit FUICEO UUIAGE RATE 6.8%

11.T5 9.n*

24. SHUToowNS SCHEDULED OVER NEX T. 6 MONTHS

(*

-ITPE. OAiE A10 OUR4iIUN OF EACH-Winter Msintenance-11-13-84-10 Days

25. IF 5Hul 00WM At END OF REPU91 PERIUO.

(

t%flMATE TIME UF STARTUP

26. U4115 14 TEST STATUS FURECASI ACH8 'VED i

"RIU9 10 CONMERCIAL OPERAflDN-l

(>

INITIAL CRiflCallif i

(NiilAL {LECTRELIIT

, (s COMMFRCI AL UPER4il0N i

l o e l

DOCKET NO.

50-280 ;,,

UNITsituTDOWNs ANbi'0WER REDUCTIONS IJNIT NAME Surry 1 I

  • DATE Oct. 08-1984 COMrLETED BY Y. H. Jman I

REPORT MONT11 September.1984 TELErilONE 804-357 '41n4 o

g Cause A Connective l_lcensee

[*,,

kl

.!'E

3. h L

1 Acelon to W.

Date E-gg gne Event u3 8

N oE M

jdi Reppel #

@v v

Preveal Recussence i

t l

Reactor trip caused by "C" RCPtripping 84-9 09-26-84 S

97.5 A

3 on instantaneous overcurrent. The failure was apparently the " A" phase connectbr.It j

will be r*: paired by performing a field replacement of,the stator coil tee on the motor. Commenced refueling outage.

W l

1

/

I 6

1 t

i 3

4 1

2 Method:

Exhibit G Instructions.

F: ForteJ Reesem:

I Mannst

^ for Preparatism of Dats S: Schesluled A. Equipment Failure (Explain)

D Maintenance of Test 2 Mannsl Setsm.

Entry Sheels for Licensee 3 Automalle Screm.

Event Repini (LER) File (NUREG-J C.Hefueling D Regulatony Resicletion 4 Other (Emplain) 0161) i E Operator Training & Ucense Examination 3

i l

F Asiminististive Exhibis I Ssme Source G Opevallonal Essor (Emplain) i l's/77)

Il Other (Explain)

50-281 i)DCKET NO.

0 NIT SilOTDOWNS AND POWi R REDUC 110NS UNIT NAME Surry 11

+DA1E Oct. 08,1984 COMPLETED BY V.11. Jcnes REPORT MONiil September.1984 1ELEril0NE 804-357-3184 "h

~

m Cause A Corrective

',]g

  • Yj licensee

$4 "L

g=

3yoc Event -

g 1g Acihm in No.,

DJoe h

g}

j g

Prevent Recurrence a$

M jg itepoet #

wte l-i 1

1 Unit was taken off the line to repair a pipe 84-24 9-18-84 F

49.3 A

1 leak on line coming from "A" MSR to the l

HP drain tank. Several elbows and sections of pipe were replaced on this line prior to starting unit back up.

s s

i l

+

4 I

2 3

4 F: Forced Reason:

Methml:

Exhibil G-Instructions.

i S: Scheduled A Equipment Falluse(Emplain) l Manuel for Pseparation of Dais l

D Maintenance or Test 2-Manual Scism.

Entry Sheets foe Lleensee

.1 Automstic Scrain.

Event Repues (LER) File (NUREG.

C. Refueling D Reguistory Restiletion 4-Other (Emplain) 0161)

E-Opession Training & IJcense Emendnation 5

F.Adminisissilve Exhibit I Same Source G-Opersilonal Eeros (Explain) 19/77)

II.0ther (E plain)

5 s

LOAD REDUCTIONS DUE TO ENVIRONMENTAL RESTRICTIONS MONTH _: Septenter, 1984 I

UNIT No. 1 i

DATE -

TIME HOURS-LOAD MW REDUCTIONS, MW MWH REASON

D E DURING iHIS NSiuGANG PERI @.

o t

e 9

6 e

e MONTHLY TOTAL

=e 6*e-

6 O

8 LOAD REDUCTM

~UE TO ENVIRONMENTAL RESTRICTIONS _

UNIT NO.2 MONTE: Septaber,1984 s....

DATE, TIME HOURS-LOAD, MW.

REDUCTIONS, MW MWH REASON e

NCNE DURING IHIS REPCRTING PER]CD.

e e

e i

4 9

i O

e e

MONTHLY TOTAL d* * - *

=

ee ow

" ='

e--o-

VEPCO AwERAGE JaitV uni i POWER L E VE L

%URRY POWE R STAi!UN PROGR AM N0512681 10/04/84 09 22.20 REPilRilNG MONTH - SE PI F.Mt4ER 199*

DOCRE T NO. 50-280 00LRET NO. 50-2nl DATE SEPT.'I. 1984 COMPLETED Bf

v. JONES ON I T ONE UN I T TW O AVERALE DAILf POWER L E VE L A VE R abE UAILY POWER LEVEL Dat

-MWE-NET-

-MWE-NET-1 569.2 727.7 2

566.5 728.5 3

568. 5 721 8 4

572 4 724.3 5

57%.0 729.5 6

570 4 734.9 t

571.5 733.3 l

8 575 5 731.9 9

574.9 733 1 10 574.3 736.0 11 574. 3 728. 7 12 572. 4 731.0 573. 7 730.8 13 14 574.5 728.5 15 574 6 731.1

'J 16 577.4 735.3 17 579.5 715.7 IN 570.1 313 0 19 563 5 0.0 20 563.5 1*6.3 21 569.4 707.0 22 573 4 733 2-23 571 3 731 7 29 572 3 732.8 25 564.0 728.8 -

26 53*.6 710.0 27 00 728.5 28 0.0 736.2 29 00 739.8 30 0.0 7*0.3 f

8

SUMMARY

OF OPERATING EXPERIENCE MONTH / YEAR September,1984 Listed below in chronological sequence by unit is a summary of operating experiences for this month which required loed reductions or resulted in significant non-load related incidents.

UNIT ONE 09-01-84 0000 This reporting period begins with the unit at 80% power (600 MW's).

09-20-84 0 815 Commenced plant emergency drill.

1400 Completed plant emergency drill.

09-26-84 2229 Reacter trip, caused by loss of "C" RCP.

09-27-84 0321 Commenced plant cooldown for refueling outage.

0936 RCS <3500F/450 psig, RHR in service.

1530 RCS <2000F.

09-30-84 1700 RCS degassed.

2400 This reporting period ends with the unit at CSD on RHR.

f em-we,e

+= w

' ~ ~~

~ * -

~

' ~ ~

  • * ' ~

9-

SUMMARY

OF OPERATING EXPERIENCE MONTH / YEAR September,1984 Listed below in chronological sequence by unit is a summary of operating experiences for this month which required load reductions or resulted in significant non-load related incidents.

UNIT TWO 09-01-84 0000- This reporting period begins with the unit at 100% power (770 MW's).

09-18-84 0750 Commenced plant shutdown at 150 MW's/hr for repair of hole on pipe coming from "A" MSR drain line.

1347 Unit off the line.

1423 Reactor shutdown.

09-20-84 0805 Reactor critical.

1503 Unit on the Lae, increasing power at 150 MW's/hr.

1548 Holding power at 35% (240 MW's) for Chemistry.

1711 Commenced power increase at 150 MW's/hr.

1935 Holding power at 75% (540 MW's) due to indicated flux tilt.

2243 Commenced power increase at 150 MW's/hr.

2323 Holding power at 89% (680 MW's) due to lowered flux trip setpoints due to indicated flux tilt.

09-21-84 0505 Commenced power increase at 150 MW's/hr. calculated flux tilt less than 2%.

0615 Unit at 100% power (770 MW's).

09-30-84 2400 This reporting period ends with the unit at 100% power (775 MW's).

e.

4

-. - - ~ -- - ---

"~

10 -

AMENDMENTS TO FACILITY LICENSE OR TECHNICAL SPECIFICATIONS MONTH / YEAR September,1984 The Nuclear Regulatory Commission issued, on June 12, 1984, an Order for Surry Power Station Unit Nos.1 and 2. The Order is issued to encourage implementation of NUREG

- 0737 Supplement 1 items. Effectively immediately, the Order requires that the licensee shall;

" Implement the specific items described in the Attachment to this ORDER in the manner described in the licensee's submittals noted in Section III no later than the dates in the Attachment.'

i l

l l

l l

t

11 FACILITY CHANGES REQUIRING NRC APPROVAL Septernber, 1984 NCIE DURING 'IHIS talucuG PERICD.

4 i

e i

f.

l l

I I

l l

i l

l l

l

,c_

6 l

12 FACILTIY CHMKES 'INAT DID NOT PEQUIRE !RC APPORVAL Septerrber, 1984 UNIT DC 82-15 Servi Air AMitianal Capacity 1

'Ihis design change ccnnected the spare Servi Air ocmpressor (1-SA-C-2) and Tank (1-SA 'IK-2) that was used during SGRP to the existing Service Air System.

I Simrary of Safety Analysis

'Ihis modificaticn does not affect. staticn operaticn or the operaticn of any safety related equignent.

'Ihe Sevice Air Systs will have increased capacity and reliability.

.m y

13 e

TESTS AND EXPERIMENTS REQUIRING NRC APPROVAL Septertber, 1984 IKNE DURING 'IEIS xwutadG PERIOD.

TESTS AND EXPERIMENTS THAT DID NOT REQUIRE NRC APPROVAL NCNE DURING 'IHIS REPORI'ING PERIOD.

I 1

I d

s 1

3-r+r-

+

---e

,y-y--...

rv-p--w.,-

.-w=.r-sg-ywwvw+y*,

-wm-v-y

.-&dw-e-c--ww-

-:,y, w*ys-mw--vem-+-

1 14 OTHER CHANGES, TESTS AND EXPERIMENTS Septatber, 1984 i

NCNE DURING 'IHIS REPORTING PERICD.

4 1

4

+

f t

1 4

[,..

.m.

e, y-

..c,-+-

15 POW 28-06 VIRGINIA ELECTRIC AND POWER COMPANY SURRY POWER STATION CHEMISTRY REPORT Septenber

-1984 _.

PRIMARY COOLANT UNIT NO. 1 UNIT NO. 2 ANALYSIS 4

MAXIMUM-MINIMUM AVERAGE MAXIMUM MINIMUM AVERAGE Gross Radioact., uCi/ml 1.67 E+0 1.00 E-1 9.10 E-1 9.99 E-2 5.16 E-3 6.10 E-?

Suscended Solids, pom 0.0 0.0 0.0 0.0 0.0 0.0 Gross Tritium, uCi/ml 7.20 E-2 5.61 E-2 6.71 E-2 1.90 E-1 7.18 E-2 1.50 E-1 Iodine 131, ECi/ml 6.31 E-1 5.50 E-3 7.49 E-2 1.7A E-d 9.47 E-5 1.70 E-d 1

I

/I 0.53 0.18 0.30 0.24 0.06 0.12 l31 l33 Hvdrocen, cc/kc

. 47.'7 3.fB) 20.2 46.3 29.5 37.4 Lithium, com (A) 1.86 0.36 0.53 1.44 0.79 0.95 Boron-10, com*

205 10 53 142 62 80 (B)

(B)

Oxycen, (D.O.),com 0.600 1 0.005

'O.029 1 0.005 1 0.005 1 0.005 i

Chloride, opm 1 0.02 1 0.02 1 0.02 1 0.02 1 0.07 10 n?

pH 9 25'C 7.22 5.23 6.61 A.AR g.11 c na

  • Boron-10 = Total Boron x 0.196 NON-RADIOACTIVE CEEMICAL RELEASES, POUNDS T.S.

4.13.A.6 Boron.

46 (C)

Phosphate I

Sulfate Chromate 0.0 Chlorine 50% NaOH REMARKS: (A) Lithiun additions made to Unit 1: 3250 grams on 9/27, Lithiun additions made to Unit 2: 385 grams on 9/18, 300 grams on 9/19, 275 arams on 9/20, 230 crams On 9/21, t

145 grams on 9/22; Cation bed clarad in service on Unit 1 on 9/25 to determine removal efficiercy, clarwl in service on 9/27 fnr sys+e r1=anuo rn-ine to refwlina. r'acinn haa 4

placed > service on Unit 2 on 9/15 and 9/25 r'or Lithiun removal.

(B) Unit i demenoa and exvmataa fnv vpfelinc (C) '&p levole of tF_r_~ rhamical m ahnn1 A dure no adverse envinnsr_nLgl imnart.

i


e v.

-+

-pny, y..m,-

-o.-----

--r-

--a wwe. - - < -, -. - -

g,-y.m

,y--9,egy-----we,,e v-v

..ar.:i.-mm

w..y g-eywe&-.9ei+y.,--

,-g-**-

yv

16 DESCRIPTION OF ALLINSTAMOES WHERE THERMAL DISCHARGE LInsin WERE EXClTDED Septernber, 1984 NCNE IIRING THIS NuuGidG PERICD.

E' h

4 t

I

~

  • ' *~ *

+

,e---

g w

17 FUEL HANDLING UNIT 4 1

MONTH / YEAR September,1984- "- -

DATE NO. OF ANSI NO.

NEW OR SPENT FUEL SHIPPED / RECEIVED ASSEMBLIES PER SHIPMENT INITIAL ENRICHMENT SHIPPING CASK ACTIVITY LEVEI NONE D JRING THIS REPORTING PERII )D.

l I

ewe--

-w--

m m

m-m

~-v w

-v-m a

emv---

  • c-_

er w

18 s

FUEL HANDLING

~

UNIT 4 2

MONTH / YEAR. September,1984- ---

DATE NO. OF ANSI NO.

NEW OR SPENT FUEL SHIPPED / RECEIVED ASSEMBLIES PER SHIPMENT INITIAL ENRICHMENT SHIPPING CASK ACTIVITY LEVEL NONE D JRING THIS REPORTING PERIt)D.

1 l

1 O

e e

=-e.

a

.e w

-,.--_m-m

r 19 1

PROCEDURE REVISIONS THAT CHANGED THE OPERATING MODE DESCRIBED IN THE FSAR seoternberi 1984 NCNE DURING 'IHIS mauuuGG PERIOD.

4 e

e l,

4

~

,,,-m

--,w,ww,y

-~-vr~w-n

---wv, m--s-,e4 7

,wwe,,-w-3 pq,-,mp-

,,-,w ym-,-

w em---,ye p-.-n,,

s 6

'20

.o DESCRIPTION OF PERIODIC TESTS WHICH WERE NOT COMPLETED WITHIN THE TIME LIMITS SPECIFIED IN TECHNICAL SPECIFICATIONS Septer:ber, 1984 e

NCNE DURING THIS REEORITNG PERIOD.

O e

l i

-21.

4

~

i 1

M AINTEN ANCE OF SAFETY RELATED SYSTEMS DURING OUTAGE OR REDUCED POWER PERIODS UNIT NO. I MECHANICAL MAINTENANCE I

l e

t l

,e 3

.w,

- ~ -, -

--e

22 JiAFETY RELATED BURING pmrrn POWER SORTED BY LMIT AND IIEPARTIENT FROM 09 m /84 THRU 0940/84 LMIT 01 SURRY RETURPG TO WO IEPT SERVICE MARK MJMBER NLMBER WO TITLE HISTORY SUP9tARY

~-221 ~~006434 COWECT SAPPLE TUBING TO BUILT SAPPLE TUBING RIG, GAVE TO ' i

~

R03 09/28/84 01-GW -

1-N-221 OPERATIONS TO HOOK UP.

e i

e e

9 e-a d

7 e

S

\\

\\

^

23 g..

  • P W

MAINTENANCE OF SAFETY RELATED SYSTEMS DURING OUTAGE OR REDUCED POWER PERIODS UNIT NO. 2 MECHANICAL MAINTENANCE S

4 I

j

,,. - - -.,, - -, - - - -. - + - - -,,, - -,-

,-.g----.---

c.

24 VEPCO SAPETY RELATED DURING Rmrvn P0lF< SORTED BY LMIT AND DEPARTENT FROM 09/10/84 TW" 09/21/84 LMIT 02 URRY

~

RETURNED TO WO DEPT SERVICE MARK NUMBER NLMER WO TITLE HISTORY

SUMMARY

~

R03 09/21/84 02-ttS -

-158 005069 VALVE HAS PACKING LEAK ADJJSTED PACKING STILL LEAKS AT PAC-KING GLAND EEDS REPACKING SUBMITTED lE 4098604 TO REPACK

' R03 09/19/84 02-SW-NSS -31 005270 REFILL RESERVOIR-WORK NOT REQUIRED AS PER ASE SECTI-2-SHP-HSS-31 ON'XI FOLLDER AND E WONG R03 09/19/84 02-SW-HSS -34A 005309 REFILL RESERVOIR WORK NOT REQUIRED AS PER ATTACED 2-SHP-HSS-34A ASME SECTION XI FULLOWER AND D WONG

\\

\\

F G

l 9

4 l

G e

w em v

--w,-

ei+

-m

25 e

W s s s s e e

~

MAINTENANCE OF SAFETY RELATED SYSTEMS DURING OUTAGE OR REDUCED POWER PERIODS UNIT NO.1 ELECTRICAL MAINTENANCE 4

1 i

5

~.

,,.-,--n

,,.--,,,,_%-,,,w,,-

.,,-----,m-,.y

..~,as+.w-...

-,m..,y-

-.w,

hTED LMIT AND DEPARTPENT FROM 09

/84

/3o

.LMIT 01 SLRRY RETURED TO gg NN N

WO TITLE HISTORY

SUMMARY

R04 09/29/84 01-RC -

-MISC 003940 ASSIST OPS IN REMOVING VALVES ASSISTED GPS IN TAK BACK SEAT R04 09/29/84 01-RC -P

-1B 005413 DISASSDSLE MOTOR AND REASSEH-FOLND FITTING LE BLE AFTER WESTINGHOUSE CECK UALVE T10HTEED FITTING STOP LEAK REPAIRS R04 09/29/94 01-SI -MOV -1869A' 006433 ADJET TORQUE SETTING SO YLV.

RESET TORQUE SWITCH TO SETTING OF 2 FOR CLOSE AND 1 1/2 FOR OPEN DIRECT WILL GO FULL CLOSED. IT ION. VALVE DRIFTED TOWARDS OFEN DIRE HAS EXCESSIVE LEAKAGE CTION WEN VALVE WAS C0tFLETELY AS PER PT 16.4.

CLOSED 1/4" NOTIFIED J SIPPSON G

6 h

o 9

e me

-e ep.-a pm m

m.,,,.,

2 72 MAINTENANCE OF SAFETY RELATED SYSTEMS DURING OUTAGE OR REDUCED POWER PERIODS UNIT NO. 2 ELECTRICAL MAINTENANCE 1

e e

O D

h-um-e---

y-y- - -, -

m.s-,r-<-

we----

---m ee_y---,.--er

,r-

---g.--

4-

28 VEPCO SAFETY RELATED BLRING REDUCED POER SORTED BY WIT AND DEPARTPENT FROM 09/18/84 TMtu 09/21/94 WIT 02 SIERY RETURED TD WO

- DEPT SERVICE-MARK NLMBER LAMBER WO TITLE HISTORY SLBMARY R04 09/18/84 02-EPH-BKR -25J11 004684 REPLACE PIN AND EPRING INSTALLED SPRING & REPLACED EW COTTER PIN SPRING 4604936 PIN 4604937 R04 09/18/84 02-EPH-BKR -25J2. 004676 REPLACE PIN AND SPRIMi REPLACED COTTER PIN AND INSTALLED EW SPRIMi SPRING 4609436 COTTER PIN 4604937 R04 09/18/84 02-EPH-BUS -A 005358 OVEREATING NORMALGROLMD STRAP CLEAED SLRFACE AROUND BUS DUCT STRAPS. INSTALLED SOE EW STRAPS.

FOLMD CABLES WITH BAD COMECTIONS.

REMOVED STRAPS & CLEANED CONTACT SLRFACE & RE-INSTALLED. TESTED St.T.

R04 09/18/84 02-fW -MOV -251A 002943 REPLACE OVERLDADS WITH SIZE 10 REPLACED OVERLOADS, VALVE CYCLID SAT BY (FS OVERLOAD EATERS (2) 0735038 R04 09/18/84 02-FW -MOV -251B 002944 REPLACE OVERLOADS WITH SIZE 10 REPLACED DVERLDADS VALVE CYCLED SAT BY OPS OVERLDAD EATERS (2) 0735038 R04 09/18/84 02-FW -401 -251D 002946 REPLACE OVERLOADS WITH SIZE 10 REPLACED DVERLOADS VALUE CYCLED SAT BY OPS OVERLOAD EATERS (2) 0735038 R04 09/18/84 02-FW -MOV -251E 002947 REPLACE OVERLOADS WITH SIZE 10 REPLACED OVERLOADS VALVE CYCLED SAT BY (FS OVERLOAD EATERS (2) 0735038 R04 09/18/84 02-FW -MOV -251F 002948 REFLACE OVERLOADS WITH SIZE 10 REPLACED OVERLOADS VALVE CYCLED SAT BY OPS OVERLOAD EATERS (2) 0735038 I

I l

l e

.e S

9 4

4

+-

-rc-

,e, a-

,.--w-v-,--3 y----

-e--

---ww-m

  • e--e,--

-.g g

-,-,.----w-wew-w e r-w-

==r-w-- - - -

ew p----==

- - = * **--

I 29 l

MAINTENANCE OF SAFETY RELATED SYSTEMS DURING OUTAGE OR REDUCED POWER PERIODS UNIT NO.1 INSTRUMENT MAINTENANCE S

I 9

6 l

.s

_.1 y

7

-p

__m,_

---n

,.m..~-,.-,,y-

30 UEPCO SAFETY RELATED DLRING REDLEED POER StRTD BY LMIT Me DEPARTENT FROM 09/27/94 TMtu 09/30/84 LMIT 01 SURRY RETURED TO WD IEPT SERVICE MARK NUMBER M

WO TITLE HISTORY SLMtARY FOLND RELAY 44 CR STUCK, PtA1ED RE-T22 09/27/94 01-RPI-

-J 7 006337 NO ROD BOTTOM LIGHT AFTER TRIP LAY, REINSTALLED, VERIFIED THAT RE-LAY WAS SEATED PROPERLY IN SOCKET.

UPON DOING THIS ROD BOTTOM LIGHT INDICATION RETLRED TO NORMAL UNPLUG SENSING LINES T22 09/27/94 01-VS -S

-1A 005937 Q.EAN OUT SENSING LIES l

T22 09/29/94 01-RC -RV -551B 005158 SETPOINT LIGHTS ARE ERRATIC, REPLACED LtMIGRAPH WITH EWLY CALIBRATED DE CECK SAT t

4 O

o 6

e 9

N 31

+

e.

.i O

a 9'

s e + ep i

MAINTENANCE OF SAFETY RELATED SYSTEMS DURING OUTAGE OR REDUCED POWER PERIODS UNIT NO. 2 INSTRUMENT MAINTENANCE e

t 4

e 6

l l

l l

I r

-~

a

,.w-

.--.n-.,,., - -.. -.-, --, - - - -.,,,, -,,..,-,

f 32 N...

RELATED DLRING REDUCED POWER SORTED BY WIT AND DEPARTENT FROM 09/18/84 TiftU 09/21/84 LMIT 02 St#tRY RETtB D TO WO DEPT SERVICE MARK NUMBER IAMBER WO TITLE HISTORY

SUMMARY

T22 09/19/84 02-ftP -TI -412C 005076 LOOP 'A' OVER 1DP DELTA T CECKED ISOLATOR AND INDICATOR.

FOLMD INDICATOR Olli 0F ADAETMENT.

ADJJSTED INDICATOR. CECKED SAT.

l T22 09/'il/84 C2-FW -FCV -480 005510 CECK OUT "B" FEEDWATER CONTROL ADAETED E/P MINOR ADJET.ADAETED SPAN /ZERO ON V/P MINOR FERFORMED PT System 2.34 ON B YALVE CLEARED PILOT RELAY

.OP SAT T22 09/21/34 02-FU -LI -495 004565 LEVEL INDICATION DRIFTING HIGH CECKED XMTR CALIBRATION CECKED SAT.PT SENT TD ENGIEERIE

~

9 j

4 0

e e

--*.m

-=

f*!l:g.

e :

?u

'O:

VIRGINIA ELucTnIC AND Powan CoxPANY Ricnwown, VIRGINIA 20261

~.W.L.Stawaar Vice Pa eimewe

wace.

o,.

October-15, 1984 Mr. Maurice R. Beebe Serial No.' 601

. Office of. Resource. Management' N0/JDH:aca

-U. S. Nuclear Regulato:y Commission:

Docket Nos. 50-280 Washington,~D. C.-20555 50-281~

License Nos. DPR-32

Dear Mr. Beebe:

.DPR-37

-VIRGINIA ELECTRIC AND POWER COMPANY SURRY POWER STATION UNIT NOS. 1 AND 2 MONTHLY OPERATING REPORT Enclosed is'the Monthly Operating Report for Surry Power Station Unit Nos. 1 and 2 for the month of September, 1984.

ery truly yours, MJ W. L. Stewart Enclosure (3 copies) cc:

Mr. R. C. DeYoung, Director (12 copies)

Office of Inspection and Enforcement Mr. James P. O'Reilly (1 copy)

Regional Administrator Region II Mr. D. J. Burke..

NRC Resident Inspector Surry Power Station

,/r