Forwards Updated Status of 1984 Licensing Items Identified in .Approval of Item 28 Re Deletion of Requirement to Remove Reactor Vessel Capsule Crucial Prior to Scheduled Startup.Decision on Item Needed by 850104
ML20107M150
Person / Time
Site: Farley  
Issue date: 11/06/1984
From: Mcdonald R
ALABAMA POWER CO.
To: Varga S
Office of Nuclear Reactor Regulation
References
TAC-53266, TAC-54234, NUDOCS 8411140044
Download: ML20107M150 (9)


Text

_.

Mailing Address -

' Alabzmn Powsr Company -

600 North 18th Strest -

'I;

- Post Office Box 2641 Birmingham, Alabama 35291

Telephone 205 783-6090 R. P. Mcdonald Senior Vice President Flintridge Building AlabamaPower t"e sou:%m escr c s, s:em November 6,1984

-Docket Nos. 50-348 50-364 Director, Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Washington, D. C.

20555 Attention: Mr. S. A. Varga Joseph M. Farley Nuclear Plant (FNP) - Units 1 and 2 Licensing Items Requiring NRC Approval Gentlemen:

Attached for your information is an updated status of 1984 licensing items identified in Alabama Power Company's letter dated Oc tober 10, 1984. This attachment is tabulated chronologically by Alabama Power Company's requested NRC approval date. Alabar,1a Power Company is ready to discuss modifications to this status to address all licensing issues.

Alabama Power Company acknowledges and appreciates the recent NRC efforts to' complete licensing action on items 16,17,18,19, and 20 of the attached list. There remains, however, 4 items which are.still required to support the upcoming Unit 2 refueling outage which is-scheduled to-start January 4,1985. Specifically, item 28 of the attachment, Revised Heatup and Cooldown Curves, requests deletion of the requirement to remove a reactor vessel capsule during the next Unit 2 refueling outage. As a result of. higher than anticipated fuel burnup resulting in an earlier planned start of the refueling outage and finalization'of ongoing detailed outage planning, the critical date for-a decision on removal of the reactor vessel capsule has been advanced to

' January 4,1985. Without an NRC decision by that date Alabama Power Company will be required to either unnecessarily remove a reactor vessel

-capsule or place itself in jeopardy of extending the outage critical path if approval by NRC is not obtained prior to scheduled startup.

0 g411140044 841106 0,

PDR ADOCK 05000348 PDR l

i g

p L

1

, _ - _.,.. _. _ _ _ _. _.,. _ _ _. ~.. _. _

Mr. S. A. Varga November 6, 1984 U. S. Nuclear Regulatory Comaission Page 2

' Two new items have been added to the attached list. These items arc a request for a Pollution Control Bond Issue Certificate (item 22) and an Administrative change to provide greater working hour flexibility for the operating staff (item 26). NRC staff action is requested in accordance with the attached list for these two new items.

It is Alabama Power Company's understanding that the attached Licensing Items list agrees with the current NRC schedule. The attached schedule is considered acceptable to Alabama Power Company.

If you have any questions, please advise.

o Yours truly, hs L

R. P. Mcdonald RPM /CJS:bdh-D16 Attachment cc: Mr. L. B. Long Mr. J. P. O'Reilly Mr. E. A. Reeves Mr. W. H. Bradford

ATTACIMENT PAGE 1 STATUS OF LICENSING ITEMS REQUIRING NRC APPROVAL PROPOSED ACTUAL REQUESTED ACTUAL APCo APCo NRC NRC NRC SUBMITTAL SUBMITTAL APPROVAL APPROVAL TAC ITEM DATE DATE(S)

DATE DATE REMARKS 01-06-84 COMPLETE 10-25-82 1.

Emergency Preparedness Program Audit Once Per 12 Months, FNP-1 and 2 2.

Administrative 04-06-83 01-09-84 COMPLETE Change to Footnote to T.S. Tabl e 3.3-3, FNP-1 and 2 01-10-84 COMPLETE 12-10-82

.3.

Administrative Change to T.S.

Table 3.7-4a, FNP-2 01-27-84 COMPLETE 10-08-82 4.

Change for Turbine Valve Testing, FNP-1 and 2 5.

Correct Fire 08-26-83 02-09-84 COMPLETE Protection Technical Specifications, FNP-1 and 2 02-29-84 COMPLETE 05-27-84 6.

Administrative Change to Table 3.7-4a, FNP-1 1

COMPLETE 02-29-84 05-27-83 7.

Correct Snubber l

Listing, FNP-1 (T.S. Table 3.7-4)

COMPLETE 04-16-84 8.

10CFR50.49 02-22-84 Environmental Qualification Schedule Extension Submi ttal,

FNP-1 i

ATTAC MENT PAGE 2 STATUS OF LICENSING ITEMS REQUIRING NRC APPROVAL PROPOSED ACTUAL REQUESTED ACTUAL APCo APCo NRC NRC NRC SUBMITTAL SUBMITTAL APPROVAL APPROVAL TAC ITEM DATE DATE(S)

DATE DATE REMARKS 05-17-84 COMPLETE 9.- License Condi-11-24-82 tion 2.C(17) 06-29-83 Containment 03-23-84 Mini-Purge, FNP-2 (T.S.

3.6.1.7) 05-17-84 COMPLETE 11-24-82 10a. Mechanical Snubber Listiag, FNP-2 (T.S. Table 3.7-4B) 10b. Containment 11-24-82 05-17-84 CON'LETE Denetration Overcurrent Protection, FNP-2 (T.S.

Table 3.8-1) 06-06-84 COMPLETE

11. Movable Control 03-04-83 Rod Action 06-03-83 Statement, 07-28-83 FNP-1 and 2 10-10-83 (T.S. 3/4.1.3) 02-17-84 05-03-84 COMPLETE 06-07-84 12-30-82 12a. River Water System 06-20-83 Deletion, FNP-1 03-02-84 and 2 (T.S.

03-27-84 3/4.7.5 and 3/4.7.6) 06-07-84 COMPLETE 08-03-82 12b. Diesel Generator 12-30-82 Overload Test, 06-03-83 FNP-1 and 2 01-31-84 (T.S.

03-02-84 4.8.1.1.2.c.5) 03-27-84 COMPLETE 06 22-84

13. Charcoal Filter 03-04-83 Surveillance.

03-01-84 FNP-1 and 2 (T.S. 4.7.7, 4.7.8 and 4.9.14)

ATTACHMENT PAE. 3 STATUS OF LICENSING ITEMS REQUIRING NRC APPROVAL PROPOSED ACTUAL REQUESTED ACTUAL APCo APCo NRC NRC NRC SUBMITTAL SUBMITTAL APPROVAL APPROVAL TAC ITEM DATE DATE(S)

DATE DATE i

REMARKS 12-12-83 09-12-84 COMPLETE

14. Reactor Head Vent and Other 0737 Items, G.L. 83-37, FNP-1 and 2 (Proposed T.S.

-3/4.4.12 and existing T.S.

Tabl e 3.3-6,

.3.3-11 and 3/4.6.4) 03-01-84 09-21-84 COMPLETE 15a. Change Monthly Channel Calibration of Excore Neutron Detectors to Every 31 EFPD, FNP-1 and 2 (T.S. Table 4.3-1)

COMPLETE 09-21-84 03-01-84 15b. Correct Facility Organization Chart, FNP-1 and 2 (T.S.

Figure 6.2-2)

COMPLETE 03-01-84 09-21-84 15c. Correct Valve Numbers Listed in T.S., FNP-1 and 2 (T.S.

Table 3.6-1)

COMPLETE 10-04-84 03-02-84

16. Meteorological Tower Instrument Surveillance, FNP-1 and 2 (T.S. Tables 3.3-8 and 4.3-5)

ATTACIMENT PAGE 4 STATUS OF LICENSING ITEMS REQUIRING NRC APPROVAL PROPOSED ACTUAL REQUESTED ACTUAL APCo APCo NRC NRC NRC SUBMITTAL SUBMITTAL APPROVAL APPROVAL TAC ITEM DATE DATE(S)

DATE DATE REMARKS 06-18-82 10-04-84

17. Schedul ar COMPLETE Exemption to 07-27-82 Appendix R 05-15-84 Al ternative 08-06-84 Shutdown Requirement, FNP-1 and 2 04-10-84 10-15-84
18. RCS Pressure COMPLETE Isolation Valve Surveillance, FNP-1 and 2 (T.S. 3/4.4.7.2 and 3/4.4.7.3) 08-17-84 10-17-84
19. Administrative COMPLETE Change to Allow AFW Surveillance to be Performed During Operation, FNP 1 and 2 (T.S.

4.7.1.2.2.b.1) 01-13-84 10-23-84 COMPLETE 20.

Respirator Iodine Filter 02-10-84 Exemption 02-13-84 Request. FNP-1 03-05-84 and 2 05-08-84 54672 Critical 21.

Increase Fuel 03-30-84 10-01-84 Enrichment 05-29-84 11-09-84 54673 outage Design Limit item for Reload Fuel and New Fuel Racks, FNP-1 and 2 (T.S.

5.3.1 and l

5.6.1.2) l New item to 10-19-84 11-19-84 l 22. Pollution l

Control Bond support bond Issue issuance by

[

Certificate 11-30-84 i

\\

l

p ATTACl54ENT PAGE 5 STATUS OF LICENSING ITEMS REQUIRING NRC APPROVAL PROPOSED ACTUAL REQUESTED ACTUAL APCo APCo NRC NRC NRC SUBMITTAL SUBMITTAL APPROVAL APPROVAL TAC ITEM DATE DATE(S)

DATE DATE REMMtKS

23. Administrative 05-14-84 11-24-84 55029 Change to 55030 Reflect Senior Vice President Change, FNP-1 and 2 (T.S.

6.1, 6.2, 6.5, 6.6, 6.7 and Figure 6.2.1)

24. RWST and 06-01-84 11-30-84 55169 Critical Accumulator IST 55170 outage J u sti fication, item FNP-1 and 2 (IST Program)
25. Administrative 06-25-84 12-01-84 55412 Change to 09-24-84 55413 Reflect 2 Assistant Plant Managers, FNP-1 and 2 (T.S.

Figure 6.2-2)

26. Administrative 11-02-84 12-31-84 New item to

-~~

Change for support Operator Shift revised Fl exibility, operations FNP-1 and 2 staff (T.S. 6.2.2. f) scheduled to commence 01-07-85

27. ISI Program 07-27-84 11-30-84 55496 Critical ASME XI 12-31-84 outage Request, FNP-2 item
28. Revised Heatup 04-20-84 03-01-85 54894

' and Cooldown (FNP-1)

(FNP-1)

Curves Based on Reactor Vessel Material 02-10-84 01-04-85 54234 Critical Surveillance 06-18-84 (FNP-2) outage item Program, FNP-1 (FNP-2) for Unit 2 and 2

ATTACMENT PAGE 6

~

STATUS OF LICENSING ITEMS REQUIRING NRC APPROVAL PROPOSED ACTUAL REQUESTED ACTUAL APCo APCo NRC NRC MC StBMITTAL SUBMITTAL APPROVAL APPROVAL TAC ITEM DATE DATE(S)

DATE DATE f

REMARKS

29. Administrative 07-06-84 01-07-85 55409 Change to 55410 Remove Snubber Tables and Other Minor Changes, FNP-1 and 2 (T.S.

Tables 3.7-4a and b)

30. Safety Related 05-03-83 11-03-83 51629 8attery 06-29-83 05-01-84 51631 Surveillance, 07-29-83 06-01-84 FNP-1 and 2 08-26-83 08-15-84 (T.S.3/4.8.2.3, 09-23-83 09-06-84 3/4.8.2.4 and 01-27-84 10-06-84 3/4.8.2.5) 09-06-84 12-07-84 01-11-85
31. Generic Letter 02-03-84 09-01-84 54235 APCo 83-43, 09-14-84 10-25-84 54236 responding Reporting 11-05-84 to verbal Requirements of 01-21-85 NRC 50.73, FNP-1 questions and 2 (T.S.

6.9.1.11,12,13) 32.

ISI Program 08-16-84 03-01-85 Critical ASME XI outage Code Relief item Request, FNP-1

33. Technical 30 days To be Specification after deter-Optimization NRC mined Program, FNP-1 approval and 2 (T.S.

of 3/4.3) generic changes 34.

Special Test Placed on Exception to hold by Eliminate APCo.

Excessive Flux Mapping During Startup After R.0., FNP-1 and 2 (T.S.

3/4.10.2)

r 1

ATTACIMENT PAGE 7 STATUS OF LICENSING ITEMS REQUIRING NRC APPROVAL t

PROPOSED ACTUAL REQUESTED ACTUAL APCo APCo NRC NRC NRC SUBMITTAL SUBMITTAL APPROVAL APPROVAL TAC ITEM DATE DATE(S)

_ DATE DATE i

REMARKS

35. Chlorine Placed on Detection hold by Systems, FNP-1 APC9.

and 2 (T.S.

3.3.3.6)

Placed on

36. RCP Breaker Position Trip hold by Deletion, FNP-1 APCo.

and 2 (T.S.

Table 3.3-1) l. CJS:bdh-016 l

.. - -.