ML20106F214

From kanterella
Jump to navigation Jump to search
Confirmatory Order - Michael Meier Email Vogtle Units 3 & 4
ML20106F214
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 04/14/2020
From: Meier M
Southern Nuclear Operating Co
To: George Wilson
NRC/OE
Thompson C
References
Download: ML20106F214 (1)


Text

1

Subject:

FW: Confirmatory Order - Vogtle Units 3 & 4 From:Meier,Michael<MDMEIER@southernco.com>

Sent:Tuesday,April14,20204:46PM To:Wilson,George<George.Wilson@nrc.gov>

Subject:

[External_Sender]ConfirmatoryOrderVogtleUnits3&4

George, Aswediscussedtoday,wehavetwoactionsinourVogtleUnits3&4ConfirmatoryOrderthatwillbedifficultto completeduetotheCoronavirusPandemic.Thetwoare:
1. Withintwelve(12)monthsoftheissuanceofthisorder,SNCwilldeliverapresentationtoprovideSCWEinsights thatwerederivedfromtheseeventstopresentatanappropriateindustrysharingforum(e.g.,theNRC'sRegulatory InformationConference,theNationalAssociationofEmployeeConcernsProfessionals).Thepresentationshallbemade availableforNRCreview.
1. Withinsix(6)monthsofissuanceofthisorder,SNCVwillobtainathirdparty,independentSCWEsurveyofVogtle3 and4projectsite.SNCVwillobtainasecondthirdparty,independentSCWEsurveyofVogtle3and4nolaterthan thirty(30)monthsafterissuanceofthisconfirmatoryorder.Resultsofeachsurveywillbesummarizedintoreports whichwillbemadeavailableforinspectionbyNRC.Recommendations(ifany)fromthesurveyreportswillbeentered intotheCorrectiveActionProgramorEmployeeConcernsProgram,asappropriate,dependingonthenatureofthe recommendation,fordisposition.

Aswediscussed,wewilltakenoactionfornumber1.above,atthistime.Youwillprovideusyourthoughtsonhowto fulfillthiscommitmentatalaterdate.

Fornumber2.,weproposea5monthextensiontothecurrentduedateofMay20th;ournewcommitmentdatewould beOctober20th,2020.

PleaseletmeknowifIcapturedourconversationcorrectlyandifyouagreewithournewdatefornumber2.above.

Thanks.

Mike