ML20106D476
| ML20106D476 | |
| Person / Time | |
|---|---|
| Site: | Wolf Creek |
| Issue date: | 10/05/1992 |
| From: | Withers B WOLF CREEK NUCLEAR OPERATING CORP. |
| To: | NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM) |
| References | |
| WM-92-0162, WM-92-162, NUDOCS 9210130010 | |
| Download: ML20106D476 (2) | |
Text
P, I
A t
' NUCLEAR OPtERATING CORPORAT}ON Barto wimem October 5, 1992 Ptederit and CNel i muteve Of%cer VM 92-0162 U.S. Nuclear Regulatory Commission ATTN Document Control Desk Mail Station F1-137 Washington, D. C.
20555
Reference:
Letter dated July 30, 1992 from B. D. Withers, WCNOC to U. S. Nuclear Regulatory Commission
Subject:
Docket No. 50-482:
Extension of Commitment Gentlemen:
This letter provides a revised schedJle for the completion of corrective actions identified in the Reference.
The Reference tz ansmitted Wolf Creek Nuclear Operating Corporation's (WCNOC) respoase to Violation 9208-02 concerning a failure to follow procedures by performing maintenance without a Work Requeet.
As part of the corrective actions associated with thic violation, WCNOC committed to hsve all Mechanical Maintenance personnel participate in a review session of Administrative Procedure ADM 01-057, ' Work Request" by September 18, 1992.
These corrective actiono are being t'acked by Performance Improvement Request (PIR) 92-0504.
Review sessiont have been held with approximately 80 percent of Mechanical Maintenance personnel.
Mechanical craft personnel have participated in these review sessions, including the crew involved in Violation 9208-02.
Review sessions with the remaining personnel have been delayed because of activities associated with the formation of a Mechanical Coordinator position.
As a result of concerns with the work control process. WCNOC is creating this coordinator position to assure the necessary resources are available to perform the work activity and ensure proper system restoration.
This activity is documented in URC Inspection Report 50-482/92-05.
At the time of the inspection, implementation of the coordinator position was scheduled for third quarter 1092.
The individual responsible for conducting review cessions for AD"01-057 is also involved in the implementation of the Mechanical Coordinator position.
Corrective actions associated with PIR 92-0504 were delayed to allow increased emphasis on the implementation of the Mechanical anrdinator p)sition.
080000 g
9210130010 921005 a\\ t t
f4 lji u
PDR ADOCK 05000482 G
PDR J Box 01 : Bu>on, KS 66339 - Phone (316) 3M 8831 ir V An Equ Oppo%mty Employe, M r HC VET
(-
Page 2 of 2 i
3 The due date for the completion of corrective actions associated with PIR 92-
{
0594 was extended to Oc t.o be r 7,
1992.
Therefore, the remaining Mechanical Maintenance personnel will participate in review sessions for ADM 01-057 by I
this date.
This extension of a commitment has been discussed with the NRC Senior Resident Inspector.
If you have eny questions concerning t:iis matter, please contact Mr. Kevin J.
l Moles of my staff.
j l
Very truly yours, l
- Au L' Bart D. Withers President and Chief Executive Officer EDW/jra ec:
A. T. liowell (NRC)
J. L. Milhoan (NRC)
G.
A. Pick (NRC)
W. D. Reckley (NRC) l ll-
.