Enhancements to the Fuel Cycle Oversight Program Eric Michel Region 2/Division of Fuel Facility Inspection T7: Enhancements to Fuel Cycle and Independent Spent Fuel Storage Installation Oversight Programs
Orientation
- 10 CFR Part 40 and 10 CFR Part 70 licensees
- Conversion
- Enrichment
- Fabrication 2
Drivers for Change
- The industry continues to evolve
- Historic changes implemented incrementally 3
Evolution of industry Holistic review
Fuel Cycle Core Inspections 4
Safety Operations Plant Operations Criticality Safety Fire Protection Safeguards Material Control &
Accountability Physical Protection Information Security Radiological Controls Radiation Protection Environmental Protection Waste Management Transportation Facility Support Maintenance/
Surveillance Emergency Preparedness Plant Modifications Function Area
Smarter Inspection Program
- Fast Facts:
- Working Group established and charter issued in April 2019
- Collaboration between Headquarters and Region 2 staff 5
Smarter Inspection Program
- Fast Facts:
- Physical security and information security areas omitted
- Sought significant feedback from stakeholders
- 10 public engagements
- Current program adequate 6
Considerations
- Principles of Good Regulation
- Efficiency
- Independence
- Openness
- Clarity 7
EvaluationInformation Gathering 8
Expert panel and ranking matrix Public Input Violations Performance Reviews Operating Experience Report
EvaluationExpert Panel
- Reviewed inspection procedures and manual chapters for:
- Redundancies and gaps
- Opportunities for more efficient use of resources 9
EvaluationPrioritization and Ranking
- Evaluated eight program areas 10 Safety Operations Plant Operations Criticality Safety Fire Protection Safeguards Material Control &
Accountability Physical Protection Information Security Radiological Controls Radiation Protection Environmental Protection Waste Management Transportation Facility Support Maintenance/
Surveillance Emergency Preparedness Plant Modifications
EvaluationPrioritization and Ranking
- Evaluated eight program areas against four criteria
- Accident sequences
- Operating experience
- Complexity of regulatory requirements
- Public interest
- Factors were weighted 11
Topics for Consideration
- Reactor engineering inspection benchmarking
- System of annual, focused, and comprehensive inspections designed to increase program flexibility
- Resident inspectors
- Shift some inspection from the region to the senior resident inspectors 12
Topics for Consideration
- Approved Corrective Action Program (CAP)
- Reduce inspection resourcing based on an approved CAP
- Integrated Safety Analysis (ISA)
- Modify the core based on each plants ISA 13
Recommended Tiering 14
Example Recommendations 15
- Operations (Category 1 facilities)
- Reassigned hours from residents, criticality safety and maintenance, re-emphasized chemical sequences
- Resourcing change: 25 hour2.893519e-4 days <br />0.00694 hours <br />4.133598e-5 weeks <br />9.5125e-6 months <br />s/year to 90 hour0.00104 days <br />0.025 hours <br />1.488095e-4 weeks <br />3.4245e-5 months <br />s/year
- Fire Protection (Category 1 facilities)
- New biennial procedure
- Resourcing change: 50 hour5.787037e-4 days <br />0.0139 hours <br />8.267196e-5 weeks <br />1.9025e-5 months <br />s/year to 15 hour1.736111e-4 days <br />0.00417 hours <br />2.480159e-5 weeks <br />5.7075e-6 months <br />s/year
Overall Recommended Results Annual Hours Direct Inspection 16 Category I Category III Uranium Conversion Gas Centrifuge Gas Centrifuge w/CAP Laser Enrichment Current 1672 500 364 708 708 136 Proposed 1502 397 277 573 520 136
% Change
-10.2%
-20.6%
-23.9%
-19.1%
-26.6%
0.0%
Next Steps, and Timeframe 17
- The NRC will make a final decision and issue a tasking memorandum with the final recommendations report
- Program documents will be revised consistent with the final decision.
- Implement revised programcalendar year 2021