Interim Deficiency Rept,Item 143 Re Deviations Between Design Documents & as-built Plant.Initially Reported on 841218.Evaluation of as-built Drawings to Define Scope of Problem Performed
ML20101U075
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 01/18/1985
From: Jens W
DETROIT EDISON CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
143, EF2-70237, NUDOCS 8502060570
Download: ML20101U075 (2)


Text

,

% l.g'.

+

'['

- heyne H. Jene 1

.v vice president

/

Nx%u Qnmas '

~'

- 400 North Dxie Highway No.m. mgan mes January-18, 1985 3

(313) 586-4150 EF2-70237 1

Mr.-James G. Keppler Regional' Administrator Region III-U. S. Nuclear Regulatory Commission 4

799 Roosevelt-Road

~ Glen Ellyn, Illinois 60137 o

Dear Mr. Keppler:

Reference:

Fermi 2 NRC Docket No. 50-341

Subject:

Interim Report of 10 CFR 50.55(e) Item 143

]

" Deviation between Design Documents and the As-Built Plant" On December 18, 1984, Detroit Edison's Mr. J. E. Conen, i

Engineer-Licensing, telephoned Mr. R. C. Knop of NRC Region III, to report the identification of deviations ~between design documents and the as-built plant.

This deficiency is potentially reportable under 10 CFR 50.55(e) and is being tracked as Item 143.

Description of Deficiency Walkdown inspections have revealed some deviations between design documents and the as-built ~ plant.

The NRC has been provided with specific details of the deviations identified during meetings between Detroit Edison. personnel and the Region III staff.

Item 143 is considered potentially reportable under 10 CFR 50.55(e) because hardware deviations from the drawings' require further evalua**on to determine safety significance.

Analysis of Safety Implications Detroit' Edison is' performing an extensive. evaluation of i

Fermi 2 as-built drawings to' define-the scope of the problem..As deviations are identified, they are being documented, evaluated and.dispositioned in accordance with Fermi 2-noncomformance reporting procedures.

JAN 25 EES '

8502060570 850118 9~

g ADocn oS0oo343 g.

PDR

- g i o

i

.Mr. James G. Keppler January-18, 1985 EF2-70237 Page 2 Corrective Action Corrective actions are being formulated consistent with the analysis-described above.

Detroit Edison will provide another report on this itec.

either interim or final, when further information is available.

If you have questions concerning this matter, please contact Mr. Lewis Bregni, (313) 586-5083.

Sincerely, acc: