ML20101U059
| ML20101U059 | |
| Person / Time | |
|---|---|
| Site: | Fermi |
| Issue date: | 01/15/1985 |
| From: | Jens W DETROIT EDISON CO. |
| To: | James Keppler NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III) |
| References | |
| 111, EF2-70232, NUDOCS 8502060561 | |
| Download: ML20101U059 (1) | |
Text
1 Wayne H. Jens
. Vt23 PrCsident Nuclear Operations
[hehtWt
"-"2 6400 North Dixie Highway Edison :=r--
Januery 15, 1985 EF2-70232 Mr. James G. Keppler Regional Administrator Region III.
U..S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, Illinois 60137
Dear Mr. Keppler:
Reference:
(1) Fermi 2 NRC Docket;No.-50-341 (2) Letter, D. A.
Wells to J. G. Keppler February 6,1984, QA-84-0079 (3) Letter, W. H. Jens to J. G. Keppler July 5, 198 4, EF2-69272 i
l (4) Letter, W. H. Jens to J. G. Keppler November 30, 19 8 4, EF 2-70219
Subject:
Amended Report of 10CFR50.55(e)
Item 111, " Design Deficiency on the RHR Reservoir Freeze Over" l
Detroit Edison will use a temporary auxiliary boiler to add any heat necessary to prevent freezing of'the~ Residual Heat Removal Service Water (RHRSW) reservoirs tais winter.
Therefore, Detroit Edison will not operate the Emergency 4
Diesel Generators to supply heat'to the RHRSW reservoirs as had been indicated in References (3) and (4).
If.you have any questions concerning this matter, please contact Mr.' Lewis Bregni,.(313)'586-5083.
1 Sincerely, J.