ML20101Q602

From kanterella
Jump to navigation Jump to search
Advises That Fuel Load Dates Changed to 860601 for Byron Unit 2,Apr 1986 for Braidwood Unit 1 & Jul 1987 for Braidwood Unit 2
ML20101Q602
Person / Time
Site: Byron, Braidwood, 05000000
Issue date: 12/24/1984
From: Reed C
COMMONWEALTH EDISON CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
References
9559N, NUDOCS 8501080174
Download: ML20101Q602 (1)


Text

1 O

N Commonwealth ECson

/

~

) one First National Plaza, Chicago Illinois k C } Address Reply to: Post Office Box 767

\\

Chicago, Illinois 60690 f

December 24, 1984 Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, DC 20555

Subject:

Revision to the Expected Fuel Load Dates For Byron Station Unit 2 and Braidwood Station Units 1 and 2 NRC Docket Nos. 50-455, 50-456/457 References (a):

Cordell Reed letter to H. R. Denton dated October 4, 1984

Dear Mr. Denton:

The most recent budget review of the schedcle of engir.eering and construction activities and preoperational testing has resulted in a change in the estimate of the fuel load dates of Byron Station Unit 2 and Braidwood Station Units 1 and 2 to slightly later dates.

The current estimate is that fuel can be loaded in Byron Unit 2 by not later than June 1, 1986, and in Braidwood Units 1 and 2 in April, 1986, and. July, 1987, respectively.

While it is conceivable that fuel loading could be accomplished earlier, Commonwealth Edison Company is using these dates for planning purposes.

There are, of course, contingencies which could cause fuel load to occur later than the above dates.

I will continue to keep you advised of any changes in the scheduled fuel load date for these units.

Very truly yours, 0-D--e Cordell Reed Vice President cc:

J. G. Keppler - RIII u

8501000174 841224 PDR ADOCK 05000455 A

PDR 9559N e\\

D 4'0

..