Requests one-time Schedule Change for Annual Requalification Training Program to Allow Written Exam to Be Given in Oct/Nov 1985,due to Delay in Start of Classroom Training Caused by Scheduled Refueling Outages
ML20101P683
Person / Time
Site: Farley  
Issue date: 01/02/1985
From: Mcdonald R
ALABAMA POWER CO.
To: Varga S
Office of Nuclear Reactor Regulation
References
NUDOCS 8501070248
Download: ML20101P683 (2)


Text

-

-(

-7.

Malling Address Alabama Power Company -

v.

600 North 18th Strest Post Offace Box 2641

, Birmingham, Alabama 35291

. Telephone 205 783-6090 R. P. Mcdonald

  • dLL%"Ja*o*"'

Alabama Power January 2, 1985

. Docket Nos. 50-348 50-364~

Director, Nuclear Reactor Regulation U. S. Nuclear Regulatory Cornission Washington, D.C.

20555 Attention: Mr. S. A. Varga Joseph M. Farley Nuclear Plant - Units 1 and 2 Annual Requalification Examination Schedule Change Request--

Gentlemen:

Pursuant to 10CFR55, Appendix. A, paragraph 4.a. Alabama Power Company has been conducting annual written examinations as part of its requalification training program. The requalification training program consists of simulator and classroom training.

Based on' discussions with the NRC Staff, administrative procedures were established to-ensure that the -

written examination is given within two months of the previous year's examination. This bracket of time allows for flexibility in the scheduling of the classroom training while ensuring that the written examinations occur at a nominal one year interval.

In 1984, the written examination was given -

in May/ June.

Refueling outages are scheduled to commence in January 1985 for Unit 2 and in' April 1985 for Unit 1.

The close proximity of these outages will necessitate a.d' lay in the start of the classroom training until.May 1985.

The earliest possible time for the written examination to be given would then be during the five week period connencing the third week of October 1985.' 'This schedule allows for adequate staffing during the refueling outages and completion of:the classroom training program.- It should be emphasized that'the simulator portion of requalification training program is still scheduled to be conducted during the two refueling outages noted ~

abovt.

i 9501070248 850102 PDR ADOCK 0500034s v

pog i

Mr. S. A. Varga January 2, 1985 U. S. Nuclear Regulatory Consnission Page 2 It is requested that the NRC grant a one-time change to the requalification training program to allow the written examination to be -

given in October / November 1985. Alabama Power Company-will return to the -

NRC regular written examination schedule in 1986 with a base month of May.

approval of this change is requested by March 29, 1985.

If you have any questions, please advise.

Very truly your,

R. P.

Donald RPM / JAR:bdh-034 cc: Mr. L. B. Long Mr. J. P. O' Reilly Mr. E. A. Reeves Mr. W. H. Bradford Mr. D. H. Beckman Mr. H. Booher I