Monthly Operating Rept for Nov 1984
ML20101B192
Person / Time
Site: Farley Southern Nuclear icon.png
Issue date: 11/30/1984
From: Mcdonald R
ALABAMA POWER CO.
To:
NRC OFFICE OF RESOURCE MANAGEMENT (ORM)
References
NUDOCS 8412200163
Download: ML20101B192 (5)


Text

o i

JOSEPH M. FARLEY NUCLEAR PLANT UNIT 2 NARRAT'VE

SUMMARY

OF OPERATIONS NOVEMBER There were no unit shutdowns or significant power reductions during the month of November.

The following major safety-related maintenance was performed in the month of November:

1.

Performed miscellaneous corrective and preventive maintenance on diesel generators.

8412200163 841130~

PDR ADOCK 05000364 R

pyg lff

JU-JU4 UNIT.

2 i

~

12-5-84 DA21 COMPLETED SY J. D. Woodard (205) 899-51564 TELEPHONE November, 1984

.40E!

DAY AVERACE DAILY POWER LEVEL DAY AVERACE DAILY POWER LEVEL

@lWe Net)

(MWe-Net) 818 g,

g7 837 2

823 13 826 J

~

-- f4 - --

g9_.

4' 827 gg 835 3

828 21 919 836 840 w

6 832 7

23 839 g

838 24 R14 9

91s 25' ou 828 10 26 823 II 836 27 819 834 g3 gu 3

l3 AnA

9 839 839 14 30 817 IS 834 3;

16 81n i

R G UCUONS On tiiis form:r. list the 2ver:ge d:ly. nit power !cvelin MWe Nc! fut e:ch d:y in the reporting month.C.2mpute to 4

, the ne:re:t whole me;: wast.

(9p7)

I l

l

~

I J

4 V)

OPERATING DATA REPORT

(

DOCKET NO.

50-364 DATE 12-5-84 COMPLETED BY J.D. Woodard TELEPHONE (9nsi R99-5156 OPERATING STATUS

1. Unit Name:

J seph M. Parley - Unit 2 Notes

2. Reporting Period:

h amhne 14AA I)' Cumulative data since

3. Licensed Thermal Power (MWt):

2652 7-30-81, date of '

4. Nameplate Rating (Gross MWe):

860 commercial operation, 829

5. Design Electrical Rating (Net MWe):
6. Maximum Dependable Capacity (Gross MWe): 852.5 809.1
7. Maximum Dependable Capacity (Net MWe):
8. If Changes Occur in Capacity Ratings (Items Number 3 Through i) Since Last Report, Give Reasons:

N/A N/A

9. Power Level To Which Restricted,If Any (Net MWe):
10. Reso.s For Restrictions. If Any:

N/A 7N This Mo' nth Yr..to.Date Cu ulative

11. Hours In Reporting Period 720 8,040 29,281
12. Number Of flours Reactor Was Critical 720.0 7,646.8 26,189.6
13. Reactor Rewrve Shutdown Hours 0.0 0.0, 138.0
14. Hours Generator On Line 720.0' 7.562.5 7s.861.3
15. Unit Reserve Shutdown Hours 0.0 0.0 O.0
16. Gross The mal Eriergy Generated (MWH) 1,906,767

'19,743,227 65',08'1,071

17. Gross Electrical Energy Generated (MWH) 626,882 6.382,032 21,368.908
18. Net Electrical Energy Generated (MWH) 598,478 A n7n 7An 9n 97n vnA
19. Unit Service Factor 100.0 94.1 88.1
20. Unit Availability Factor 100.0 94.1 88.3
21. Unit Capacity Factor (Using MDC Net) 102.7 93.3 85.6 100.3 91.1 83.5
22. Unit Capacity Factor (Using DER Net)
23. Unit Forced Outage Rate n.n s.o ss
24. Shutdowns Scheduled Over Next 6 Months (Type. Date.and Duration of Each):

Refuelinc/ maintenance outnee 1/4/85. nonrnrimntelv 5% veeks.

i

25. If Snut Down At End Of Report Period. Estimated Date of Startup:
26. Units In Test Status (Prior to Commercial Operation):

Forecast Achieved h

INITIAL CRITICALITY 05-06-81 05-08-81 UD-24-0I UD-2N-01 INITIAL ELECTRICITY COMMERCIAL OPERATION 08-01-81 07-30-81 en n

DOCK ET NO.

50-364 UNIT SIIU1 DOWNS AND POWER REDUCT10NS UNIT NAhlE J.M. Farlev-Unit 2 DAIE 12-5-84 COhlPLET ED llY

.T n. Unnanra REPORT MONill November. 1984 TEl.LPil0NE. One Aqq s196 w.

E E

jg

}

}s_EE5 Licensee g r,

{n.

Cause & Corrective 2

Event p

g'8 Action to No.

Date g

3g mO U

Prevent Reeverence H

yE 5

jg Report

  • g 6

THERE WERE NO I NIT SHUTDOWNS OR SIGNIFICANT POWER REDUCT: ONS DURIL G THE MONTE OF 30VEMBER.

4 I

2 3

4 F: Forced Reason:

hiethod:

Exhibit G Instructions S: Scheduled A Equipment Failure (Explain) 1.hlanual.

for Preparation or Data ll klaintenance of Test 2 Manual Scram.

En y Shecis for I.icensee C Ilefueling 3 Automatic Scram.

Event ReporI (1. Ell) File (NUREG- '

D llegulatosy Resiriction 4 Other (Explain) 0161) i E-Operator Tsaining & I.icense Examination F Administrative 5

G Opciational Error (lixplain) lishibis I Same Somee (9/77) ll Othes (Explain)

MalHng Address

- Alab ms Pow;r Comp ny 600 North 18th Street Post Office Box 2641 Birmingham, Alabama 35291 Telephone 205 783-6090 R. P. Mcdonald Senior Vice President Flintridge Building AlabamaPower thesoutr rne:ectncsistem e

December 10, 1984 Docket No. 50-364 Director, Office of Resource Management U. S. Nuclear Regulatory Commission Washington, D.C.

20555

Dear Sir:

RE: Joseph M. Farley Nuclear Plant Unit 2 Monthly Operating Data Report Attauned are two (2) copies of the November 1984 Monthly Operating Report for Joseph M. Farley Nuclear Plant, Unit 2, required by Section 6.9.1.10 of Appendix A of the Technical Specifications. As requested by letter from Mr. John F. Stolz to Mr. Alan R. Barton, dated October 21, 1977, a " Narrative Summary of Operating Experience" is included in the attached report.

If you have any questions, please advise.

Yours very truly, s'

R. P. Mcdonald RPM /KWM: sam Enclosures xc: Director, IE (10 copies)

Director, RII (1 copy) lj l

,