Advises That Unqualified Seismic Volt Meter Replaced.Backup in-core Thermocouple Reading & Display Sys Testing Will Not Be Performed
ML20100N070
Person / Time
Site: Three Mile Island Constellation icon.png
Issue date: 04/12/1985
From: Hukill H
GENERAL PUBLIC UTILITIES CORP.
To: Stolz J
Office of Nuclear Reactor Regulation
References
5211-85-2072, NUDOCS 8504180269
Download: ML20100N070 (1)


Text

GPU Nuclear Corporation ENuclear  :::,omer8o Middletown, Pennsylvania 17057-0191 717 944-7621 i

TELEX 84 2386 1 Writer's Direct Olal Number:

April 12, 1985 5211-85-2072 Office of Nuclear Reactor Regulation Attn: J. F. Stolz, Chief Operating Reactor Branch No. 4 Division of Licensing U.S. Nuclear Regulatory Commission Washington, DC 20555

Dear Mr. Stolz:

Three Mile Island Nuclear Station Unit 1 (TMI-1)

Operating License No. DPR-50 Docket No. 50-289 Backup Incore Thermocouple Reading and Display System Testing Requirements By letter dated May 31, 1984, GPUN provided information on five NRC comments on the seismic capability of the backup incore thermocouple reading and display system. Comment #5 required adoption of proper calibration procedures for converting portable voltmeter readings into thermocouple temperatures because the installed backup incore thermocouple readout meter was not seismically qualified. GPUN agreed to incorporate a test comparing computer readings with the results of the portable voltmeter into the Startup and Test Program per T.P. 846/1, Incore Thermocouple Operation Test. This test will not be performed in T.P. 846/1 because the unqualified meter has recently been replaced with a seismically qualified meter.

Sincerely, f

H. D. ukill Director, TMI-1 HDH/SM0/spb: 0230A cc: R. Conte J. Thoma 8504180269 850412 I PDR ADOCK 05000289

&f P PDR. /

Ifo GPU Nuclear Corporation is a subsidiary of the General Public Utilities Corporation