ML20100H623

From kanterella
Jump to navigation Jump to search
Rev 0 to Program 6250-PGD-2720, Engineering Support Personnel Training
ML20100H623
Person / Time
Site: Saxton File:GPU Nuclear icon.png
Issue date: 11/10/1995
From:
GENERAL PUBLIC UTILITIES CORP.
To:
Shared Package
ML20100H615 List:
References
6250-PGD-2720, NUDOCS 9602270385
Download: ML20100H623 (11)


Text

-- - .

PII]hr Training Content Record  ;

Program Tide +

Nussbar ENGINEERING SUPPORT PERSONNEL TRAINING 6250 PGD-2720 10.1.20 i

Course Tide Nurnber Continuing Training Session #13 .010 Lasson T.de Number Rev .

CT 13 Sarton CV Incident 11.2.11.066 0  !

I. Behavioral Imarning Obiectives Upon completion of this lesson and with sufficient self study, the trainee shall be able to:

, A. Be aware of the need to field verify drawings.  ;

l B. Define reviewer and approver responsibilities.

l C. Describe corrective actions taken as a msult of this incident. l D. . I.ist Root Causes of Saxton Containment Vessel Incident.

E. Describe lessons learned from the Saxton Containment Vessel Incident.

1. Strengthen the independent technical review process. ,
2. More clearly define reviewer and approver assignments and responsibilities.
3. Verify field drawing as controlled and current. i l

I

4. Perfortn additional walkdowns of field site to increase assurance of accuracy.

l Responsibility Signature Title Date )

Origination /5/*4/A GPUN ESP Coordinator Review / Concurrence /N/ /RH SME Approval Objectives /-T WRA/ Corp. Trnr. Mgr.  !

Final ( M ja.A / Site ESP Coordinator ///tc/f f O

9602270385 960216 PDR ADOCK 05000146 g PDR

1 M Nuolear Training content n. cord  !

Proer. rios numb.c i ENGINEERING SUPPORT PERSONNEL TRAINING 6250-PGD-2720 10.1.40 )

Number l Course Title Position Specific Continuing Training

.010 j i

1 Lasson Tide Number Rev.

Saxton CV Incident 11.2.11.066 0 II. R ferences A. Saxton Nuclear Experimental Corporation to NRC letter, C301-95-2019, 6575-952-501, Docket i No. 50-146, Response to the Request for AdditionalInformation Regarding the 15 Day Report l l

Describing the Inadvenent Breach of the SNEF Contamment Vessel Liner, B. IOSRG Review of May 25,1995 Saxton CV Incident, Memo Dated June 27,1995. l l

C. Human Performance Enhncement System Repon, Inadvenent Penetration of the Saxton containment vessel liner during site characterizatior. activities, June 1995.

D. SAXTON Nuclear Experimental Corporation to NRC letter, C301-95-2011, 6575-952-388, Docket No. 50-146,15 Day repon describing the inadvertent breach of the SNEF containment vessel liner. j l

E. Critique / questions and answer session, perforation of Saxton Containment Vessel (CV) Steel shell via core bore, IOM, Dated June 6,1995, JJB to Distribution, TMI-NOB 2, 5830-95-044,6575-952-391 F. Safety Review Process,1000-ADM-1291.01 ,

III. Duration Approximately one and one half (1.5) hour-4 l

e

. . \

.. i 1

I

=

PROGRAM COURSE LESSON TITLE LESSON REV. PAGE NO.

NO. NO. NO. NO.

10.1.20/6150- .010 ESP Specific Continuing Training il2. tim o u to 3720 Saxton CV Incident 9

DOCUMENT HISTORY Rev.O Provide increase awareness of technical reviewers responsibility when performing technical reviews, especially drawing reviews.

6 i

i l i

1 l

i l

Y 4

~

- GPU Nuclear Corporation ctl3saxt.ho Parsippany, NJ

  • 1095

)

l l FRoGRAM COURSE LESSON TTTLE LESSON REV. PAGE No.

No. . No. No. No. l

.010 ESP Specific Continuing Traimng lulN 0 M to i

10.1.20/6150, l

2m Saxton CV Incident I -

IV. INTRODUCTION A. This training is offered to increase your awareness of the need to adequately verify l correct drawings before use. Secondly, to impress upon you the responsibilities of a reviewer.

B. Let us now review the learning objectives on page one of your handout. (See Page
I for BLO's)

V. BACKGROUND INFORMATION i

A. Event Description f

! At approximately 0900 hours0.0104 days <br />0.25 hours <br />0.00149 weeks <br />3.4245e-4 months <br /> on May 25,1995 Cutting Technologies Incorporated (the l core boring contractor) personnel bored partially through the SNEF containment vessel liner below the rod room sump at the 765 foot elevation (approximately 47 feet below grade). Hey were in the process of making a three inch diameter,18 inch deep bore

. into the rod room sump when water in excess of that being used to cool the coring bit

!- was observed. The boring operation was secured and action to determine the source of l l the water was initiated.

l When the bit was retracted from the bore location, the core was removed with it. The lower end of the core was smooth and conformed with the curvature of the liner. It was because of these observed characteristics and the water clarity and temperature that liner peragion, at least partially, is considered to be the cause of the in-leakage. The water flowed from the rod room sump through a cross connect line to the larger contamment vessel sump from which it was pumped into 55 gallon drums. At approximately 1300, a temporary plug was installed in the hole and the in-leakage was stopped.

He water was sampled and analyzed to verify that it was ground water in-leakage.

The sample counted at 1000 showed Cs 137 at a level above that expected. His was attributed to contamination of the sample by suW particles from the boring  !

process and residual contamination in the rod room sump. this was later confirmed by a second,1630 hour0.0189 days <br />0.453 hours <br />0.0027 weeks <br />6.20215e-4 months <br /> sample result which showed a reduced Cs 137 level.

B. The reasons for that failure are as follows:

1. The plan originator and other reviewers W_ upon TLG, Inc. to conduct a review of such concerns and to specify sampling locations which would not challenge the liner integrity, while such an exWathi is reasonable, a GPUN j independent review was still required.

'S GPU Nuclear Corporaten etl3saxt.ho Parsippany. NJ ' 1M E_--___.---.______-----__---- - ,, -

_ _. .__ __ _ . _ . _ _- . __ _ - _ _ _ _ . ~ . - _

~

v g .

PROGRAM COURSE -

LESSON TrrLE LESSON REV. PAGE NO.

l. NO. NO. NO. NO.

I- .010 nzum o 5am 10.1.20/6150- ESP Specific Continuing Training 2720 Saxton CV Incident 1

2. The responsible technical reviewer of the plan did not conduct a review
outside his specific area of expertise and j.

did not seek assistance for. technical review of areas such as core bore j activities which were outside his area of expertise as required.

. 3. An inappropriate drawing was used by some reviewers (drawing #D-37794).

! This, drawing shows the area in question (rod room sump), and appears to indicate adequate concrete depth in this area for an 18" core. However, the view shown of the sump is out of plane on this drawing and as such, does not

[ represent the actual location. This fact is not obvious and requires interpolation of the drawing.

[

i 4. When the work instruction was developed to implement the Characterization plan, a different drawing (D-37757) was used to check the core bore locations.

This drawing accurately shows the area in question (rod room sump),

! however, in transposing the measurement of the drill location from the plan i

view to the sectional view of the drawing, the reviewer erred and located the planned bore site closer to the containment center line than the actual core l bore location. Because the containment bottom is sloped, this resulted in the appearance of adequate concrete depth at this location. The estimated depth determined by this reviewer, using drawing D-37757, closely matched the i depth determined in the first review using drawing D-37794. As a result, good correlation was achieved using separate drawings by different reviewers,

however, different errors made by each reviewer resulted in a failure to detect
the inadequate concrete depth at the core bore location.

1

Drawing D-37794 does not reflect the tme location of the sump and will not
be used for planning activities. Drawing D-37757 is accurate but was j misread. 'Ihe errors in applying these drawings and the failure to obtain cross l disciplinary independent technical review of the Characterization plan with-in

.GPUN will be corrected to prevent recurrence as described in the response to '

question 1.

VI. DRAWING VERIFICATION l

i A. I.et's review the errors in the example at SNEC.

]

i

1. Each principle reviewer in the process thought another would review areas j they did not review.

1 i

1 .

's GPU Nuclear Corporation etl3saxt.ho ,

Parsippany. NJ

  • 1995

PROGRAM COURSE LESSON TITLE LESSON REV. PAGE NO.

NO. NO. NO. NO.

10.1.20/6150- .010 ESP Specific Continuing Training i1181**6 0 6 d to 2720 Saxton CV Incident

2. Reviewers limited their reviews to their areas of expertise. l 4

l

3. Reviewers did not seek out reviewers for areas beyond their area of expertise.
4. The drawing sectional view utilized for calculations was the inappropriate Pl ane. (

l

5. The plan view of the drawing was misused in locating the co;t bore site.

B. The " comedy of errors" was: l

1. An inaccurate section view gave a false assurance of adequate concrete.
2. An accurate plane view was used to incorrectly locate a core bore site. ,

l

3. The two errors collaborated each other.

C. Their 1st and 2nd ERROR was the view was out of plane.

4 v

1 I

I l

. 1 I

- GPU Nuclear Corporation ctl3saxt.ho ,

Parsippany. NJ e IMS

-- . - - .- - . - . .. .. - .- ..- . _ - . .. - - . - . - ~ - - - . . . - = .

PROGRAM COURSE LESSON TITLE LESSON REV. PAGE NO.

NO. NO. NO. NO.

t i.2.iim o wio

'10.1.20/6150- .010 ESP Specific Continuing Training 2720 Saxton CV Incident l

.VII. REVIEWER AND APPROVER RERPONSmnrrrFS A.' Responsibilities of the Responsible Technical Reviewer (RTR)

l. The RTR is responsible to perform a thorough review to verify the technical l and safety adequacy of the change.
2. This review is to include the change itself, the Safety Determination, and the Safety Evaluation (if one is required).
3. nis review also includes consideration of other regulations and commitments ,

as was described for the preparer.

4. De RTR must be knowledgeable in the area of affected by the change.
5. The RTR is responsible for ensuring that safety determination / safety evaluation documentation and any supporting evaluations or analyses are applicable to the i document describing the actual change or activity and that draft documents, if used to support safety determination / safety evaluation documentation, are j accurate.

j 6. Obtain cross-disciplinary review or input where asesasary.

l B. Responsibilities of the Independent Safety Reviewer (ISR) i j (Required if a Safety Evaluation was generated) 5

1. The ISR is responsible to perform a thorough review to verify the safety
adequacy of the change.
2. His review is to include the change itself, the Safety Determination, and the i

Safety Evaluatior: (if one is required).

j. 3. ne ISR is also responsible to review and concur with the associated Safety
Evaluation.
4. The ISR is responsible for confirming that the safety evaluation documentation  !

! and any supporting evaluations or analysis are applicable to the document  ;

describing the actual change or activity and that draft documents, if used to  !

support safety evaluation documentation, are accurate.

j. 5. De ISR must be knowledgeable in the area affected by the change.  ;

i .

' GPU Nuclear Corporation .

. ' ctl3saxt.ho Parsippany. NJ

  • 1*5 4

l PROGRAM COURSE LESSON TITLE LESSON REY. PAGE NO.

NO. NO. NO. NO.

10.1.20/6150- .010 ESP Specific Continuing Training 112 11 *

  • 8 d to 2720 Saxton CV Incident I

1

6. The ISR shall not have direct responsibility for the work function under review.
7. The Independent Safety Review is normally accomplished prior to approval j and implementation and must be completed prior to use of the change in plant operation.
8. Obtain cross-disciplinary review or input where necessary.

C. Other Considerations (For Approver)

1. The preparer, the RTR and the ISR must all be separate individuals.
2. The ISR cannot be the approver, since the approver is normally directly ,

responsible for the work function under review. )

i

3. The preparer and reviewers are all equally responsible for the content and conclusions of safety review documentation. Where the conclusions are not
adequately supported or in sufficient detail to allow the reviewer to come to 1 the same conclusion, RTR/ISR's should provide appropriate comments to the 4

preparer. RTR/ISR's are concurring with the safety review documentation  !

l conclusions based on the content of the documentation.

VIII. CORRECTIVE ACTIONS TAKEN The following items describe corrective actions taken or to be taken:

A. All personnel involved with the subject activities have reviewed the HPES report and the findmgs.

I B. The core bore work instruction was revised to include " lessons learned" from the  !

! event review and it underwent additional i%t technical review.

C. Information will be disseminated on the need to field verify Saxton drawings before use. .

I D. A walk-down.of all remaining core bore locations was performed by an independent l technical reviewer, the manager of decommissioning projects and a member of the Independent On-site Safety Review Group, who wrote the HPES report. This l walkdown verified that the renuining core bores would not challenge the l 1 containment liner integrity.

4 1

y; .

s GPU Nuclear Corporation i ctl3saxt.ho Parsippany, NJ e 19o5

COUltSE LESSON TITLE LESSON REV. PAGE NO.

PROGRAM NO. NO.

NO. NO.

11113 N 0 Mo 10.1.20/6150- .010 ESP Specific Continuing Training 2720- Saxton CV Incident Note: The remaining core bores to be taken were verified to be shallow (<6"), and are l not in any location where the concrete depth is less than approximately 18". l E. Plugging materials are on-site to stop a ground water intrusion should a liner penetration occur.

I F. The event and the " lessons learned" will be reviewed as a topic in an upcoming i session of engineering support personnel (ESP) trainmg. l G. The Saxton procedure process was reviewed and is being revised. The revision will improve the review process and more clearly define reviewer responsibilities and 1

assignments.

IX. ROOT CAUSE OF SAXTON CONTAINMENT VESSEL INCIDENT -

The cause of the event was determined to be an inadequate review of design drawings to verify that the depth of the intended core bore without breaching containment integrity.

'Ihe Westinghouse drawing series D37792 to D37790were used by TLG Engineering, Inc. (TLG), the firm contracted to provide a characterization plan for SNEC, in determining the location and characteristics for the core bore to be made in the rod  !

room sump as described in Exhibit 1-6 of the SNEC Site Characterization Plan. l Independent design, review by TLG failed to identify the actual depth of the concrete. There was a failure to verify the adequacy of the depth of the concrete. The i failure to verify the adequacy of the depth of the concrete persisted through the internal reviews of the Charactenzation Plan by GPUN. During the internal reviews, GPUN requested of TLG a specific depth be identified for this core bore. As a result, a depth of 18" was specified by TLG. This depth was chosen to allow characterization of j possible deep activation from postulated high energy neutron streaming from the control t

rod drive mechanisms.

Since the initial characterization plan drafted by TLG and the one ultimately utihzed by GPUN to perform the characterization activities varied only in fonnat, the original l

error was carried forward. Both plans were reviewed with the practical and technical emphasis on the adequacy'of the characterization effort to provide meaningful data for the decommissioning of the SNEF containment vessel. Bsfore the boring began, an engineer utilizing Westinghouse drawing D37757, a suitable structural drawing for the j location, misread the drawing during the walkdown to locate the specific core bore

site. Work instruction procedure drafts were revised to include precautions and depth stops to prevent inadvertent breach of the liner. Although these actions were taken, the GPU Nuclear Corporaimn ctl3saxt.ho Parsippany, NJ
  • le

< mem w -

PROGRAM COURSE . LESSON TITLE LESSON REV. PAGE NO. l No. No. -

No. No. i 11211066 ~ 0 to of 10 10.1.20/6150- .010 ESP Specific Continuing Training 2720 Saxton CV Incident

. 1 error was not prevented since the depth of concrete below the proposed bore location remained incorrectly identified. j i

X. IFRSONS IRARNED/

SUMMARY

We need to:

A. Strengthen the independent technical review process.

B. Clearly define reviewer and approver assignments and responsibilities. l C. Field verify drawings. )

i D. Conduct additional reviews and walkdowns prior to commencing work process.

i l

1 l

l t'

i N GPU Nuclear Corporation Parsippany NJ

  • 1995 j Ctl3saxt.ho  ;

e 1 I

, N t 9

. l t

Attachment 2 SNEC PROCEDURE DEVELOPMENT, GHANGE REQUESTS AND SAFETY REVIEWS PROCEDURE #6575-ADM-4500.07 l

N

  • s u_._