Order Extending Latest Const Completion Date to 950801
ML20099B811
Person / Time
Site: Comanche Peak Luminant icon.png
Issue date: 07/28/1992
From: Boger B
Office of Nuclear Reactor Regulation
To:
Shared Package
ML20099B815 List:
References
NUDOCS 9208030092
Download: ML20099B811 (2)


Text

r 4

7590-1 NUCLEAR REGULATORY COMMISSION TEXA5 UTILITIES ELECTRIC COMPANY. ET AL.

COMANCHE PEAK STEAM ELECTRIC STATION. UNIT 2 DOCKET NO. 50-446 ORDER EXTENDING LATEST CONSTRUCTION COMPLEliON DATE The Texas Utilities Electric Company (TV Electric) is the holder of Construction Permit No. CPPR-127 issued by the Atomic Energy Commission on December 19, 1974, for construction of the Comanche Peak Steam Electric Station, Unit 2, a nuclear facility utilizing a Westinghouse Electric Corporation nuclear steam supply system, at the Applicant's site in Somervell County, Texas.

By letter dated February 3, 1992, as supplemented on March 16, 1992, TV Electric filed a request for extension of the latest construction completion date specified in Construction Permit No. CPPR-127 to August 1, 1995.

In its justification for the extension request TV Electric stated that the estimated one-year suspension of Unit 2 construction, which began in April 1988, was necessary to allow TV Electric to concentrate its resources on the completion l

of Unit 1.

The completion and startup of Unit I tock longer than anticipated, i'

forcing TV Electric to delay significant design activities on Unit 2 until l

l June 1990, followed by the resumption of significant coristruction activity in l

l January 1991.

As discussed raore fully in the staff's evaluation of the requested

(

extension, we have concluded good cause nas been shown for the delay and that 1

the requested extension is for a reasonable period. We have further concluded that the requested extension involves no significant hazards consideration, l_

and therefore no prior public notice is required.

1 9208030092 920728 PDR ADOCK 05000446-A PDR

. The NRC staff has prepared an Environmental Assessment and Findina of No Significant impact which was published in the Federal Register on June 29, 1992 (57 FR 28885).

The NRC staff has concluded that this action will not have a significant impact on the quality of the human environment, and therefore, no environmental impact statement need be prepared.

For further details with respect to this action, see the applicant's i

request for extension dated February 3, 1992, as supplemented by letter dated March 16, 1992, and the staff's evaluation of the request, which are available for public inspection at the Commission's Public Document Rcom, the Gelman Building, 2120 L Street, N.W., Washington, D.C.

20555, and at the University of Texas at Arlington Library, Government Publications / Maps, 701 South Cooper, P. O. Box 19497, Arlington, Texas 76019.

IT IS HEREBY ORDERED that the latest construction completion date for CPPR-127 be extended to August 1, 1995.

FOR THE NUCLEAR REGULATORY COMMISSION WA Bruce A. Bcger, Director Division of Reactor Projects IlljlV/V Office of Nuclear Reactor Regulation Dated at Rockville, Maryland this 28thday of July 1992.