Text
. -..
f chY
&@-M 9 July 23, 1992 J
Mr. N. G. Metcalf Assistant United States Attorney
.j U.S. Department of Justice Main Street centre - Suite 1800 600 E. Main Street
-Richmond, Virginia 23219-2447 Dear George -
Ret North Anna Power Station
_As I discussed. with you by telephone, the settlement offor described in your letter of April 10, 1992 is. acceptable to Virginia Power. Regarding the three elements of the proposal which you considered to be -essential, one has been completad and the other two are in progress.
Item -3 of your proposal, the employee - environmental awareness video, has been awarded to Echo Films, _Inc. and'the script is being written.
Item 4,
the -customer Connection article, was published and distributed-in our_May billing cycle to 1.8 million customers and is expected to.have exposure to 4.8 million pecsple.
A few extra copies are enclosed for your use.-
e Item 5, the public service video, has been completed with the USFWS logo.
Thirty copies - are available for The Service.
As we discussed, and you requested, the television programming package on stations WUSA,: WTVR, and WVEC will be handled by our Corporate Communications department.
While not censidered by you as part of the settlement proposal,_I want to let you_know that the site barriers to nesting, consisting of expanded metal' screen doors and covers have been constructed to cover ' the entrances-to the _ - security blockhouse, the - auxiliary feedwater pump houses and associated exhaust fans.
These barriers
. wore insta?. led at a cost of $20,506.
- Also, the
.wlternate nest structures were completed for I
approximate)y $1,000.
//
f
()0Y l
.f
~
^
-9207305012 920723 PDR ADOCK 05000338-p PDR u
e n..
r t
Mr. N. G. Metcalf Jul'y 23, 1992 Page 2 In summary, implementation of the three conponents of your settlement proposal, the site barriers, and the alternate nest structures will require a total expenditure by Virginia Power of i
approx 1'rately $80,000.
l on behalf of the company, I can assure you that protection of migratory birds is a consideration in routine operations.
I can i
cite several recent instances where field crews have altered work plans or delayed actions in deference to active nests.
Our environmental awareness video is being designed so that all emninyees having potential for interaction with nest sites or i
migratory birds will understand their obligations under the applicable laws.
Please let me know what is nocessary to conclude this matter.
Also, I need to know whether to contact you or Al Hundley about progress with the PSA programming.
Sincerely, c-B. M. Marshall, P.E.
Manager Water Quality Enclosures cca Mr. A.
C. Hundley, Special Agent U.S.
Fish and Wildlife Service p.
O.
Box 446 Fredericksburg, VA 22401-0446 U.S. Nuclear Regulatory Commission Docket No. 50-338/50-339 101 Marietta St., NW Suite 2900 Atlanta, GA 30323 U.S. Nuclear Regulatory Commissionv' Attnt Docket Control Desk Docket No. 50-338/50-339 Washington, D.C.
20555 Mr. M. S.
Lesser NRC Sr. Resident L jector North Anna Power Station
- -.- -. - -. -