Text
.
r e
PHILADELPHIA ELECTRIC COMPANY 2301 M ARKET STREET P.O. BOX 8699 PHILADELPHIA. PA.19101
"",^ " f, $,[,^,,,'"' ' "'
12 s184i-4ooo A9so OsfesNAb CoWNesk CUGENE J. BR ADLEY mesoctava sanun AL counse6 DON ALD ELANKEN RUDOLPH A. CHILLEMI C. C. KIR K H ALL T. H. M AHER CORNELL PAUL AUERS ACM September 27, 1984 assesvant ennemat counsso CDWARD J. CULLEN, J R.
THOM AS H. MILLER. J R.
IREME A. McKEMM A Assestant counssh Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Comission Washington, D.C. 20555 RE: Peach Bottom Atomic Power Station, Unit 3 Dccket No. 50-278
Dear Mr. Denton:
Enclosed for filing with the Commissic,n are three originals and nineteen copies of Philadelphia Electric Company's Second Amendment to its May 30, 1984 Application for Amendment of Facility Operating License DPR-56. This Amendment revises the application by providing additional thermal hydraulic specifications as requested by the NRC Staff.
Pursuant to Section 50.91 of the Comission's regulations, it is hereby requested that the license amendment requested in the Company's May 30, 1984 Application, as amended, be issued without prior notice and opportunity for hearing. The May 30, 1984 application requested an amendment to the Peach Bottom Unit 3 Technical Specifications to permit full power operation at higher core flows. When the application was filed, it was anticipated that the current core flow limitations, unless modified as requested in the Application, would require a derating of Peach Bottom Unit 3 in September 1984.
In August, 1984, the Staff requested Philadelphia Electric Company to
. amend its May 30 Application to address certain thermal hydraulic issues, and on September 12 the Staff requested a further amendment to the May 30 Application to incorporate further thermal hydraulic specifications. Unit 3 is presently operating at approximately 98% of its rated capacity and will continue to operate at reduced capacity until a license amendment authorizing operation at increased core flows is issued. Philadelphia Electric Company estimates that tM accumulated cost of replacement power resulting from the operationofUnit3atreducedpowerlevelswillreach$1millionby mid-November 1984.
l 7
84 0 fok k
P
c-r e
--2--
In view.of the foregoing, Philadelphia Electric Conpany hereby requests 30, 1984 application, as amended, be that the amendment requested.in its May issued as' expeditiously as practicable, without prior notice and opportunity for a hearing.-
Very truly yours, Euge e J radley FJB:pkc Enclosures t
4 j,
^
t
/-
BEFC'RE THE UNITED S'2ATES NUCLEAR REGULATORY COMMISSION In the Matter of Docket No. 50-278 PHILADELPHIA ELECTRIC COMPANY SECOND AMENDMENT TO MAY 30, 1984 APPLICATION FOR AMENOMENT OF FACILITY OPERATING LICENSE DPR-56 Edward G. Bauer, Jr.
Eugene J. Bradley 2301 Market Street Philadelphia, Pennsylvania 19101 Attorneys for Philadelphia Electric Company W-e-
D-+
.---g
_yy w
w----
yw -
-w-
-y
, - ---.gw g-
BEFORE THE UNITED STATES NUCLEAR REGULATORY COMMISSION In the Matter of Docket No. 50-278 PHILADELPHIA ELECTRIC COMPANY SECOND AMENDMENT TO MAY 30, 1984 APPLICATION-FOR AMENDMENT OF FACILITY OPERATING LICENSE DPR-56 On May 30, 1984, Philadelphia Electric Company,, Licensee
_-acility Operating License DPR-56 for Peach Bottom Unit 3, an' Application for Amen 3 ment of the License which requested that the Technical specifications conteined in Appendix A of the Operating License be amended by making certain changes to allow operation of Peach Bottom Unit 3 in the increased core flow mode. 4
.y.-
.y.
.,._,_y,
..7.
By letter dated July 17, 1984 (S.
L.
Daltroff, PECo to J. F. Stolz, NRC), Philadelphia Electric Company provided additional information requested by the NRC staff concerning the j
implementation of General Electric Company SIL-380, Rev. 1, BWR Core Thermal Hydraulic Stability, dated February 4, 1984.
On August 10, 1984, in a telephone conversation with the NRC project manager, Licensee was requested to amend the
' aforementioned application by including a Technical Specification to address BWR thermal hydraulic stability.
Accordingly, on August 24, 1984 Philadelphia Electric Company amended its Application of May 30, 1984 by establishing power and core flow operating limits when operating in either the single or dual recirculation loop modes.
Additionally, the proposed changes require monitoring of, and appropriate response to, APRM and LPRM noise levels when operating at certain high power / low flow conditions identified in the aforementioned SIL-380, Revision 1.
On September 12, 1984, in a telephone conversation with the NRC project manager, Licensee was requested to further amend its Application by incorporating additional thermal hydraulic specifications.
Accordingly, Philadelphia Electric Company, Licensee under Facility Operating License DPR-56 for Peach Bottom Atomic Power Station Unit 3, hereby further amends its Application by revising certain sections as indicated by a vertical bar in the margin of the attached pages iv, 149, 149a, 149b and 164d.
Page 149c is added to accommodate a redistribution of material.
Changes to pages 10 and 160 proposed _
in the August 24, 1984 Amendment'and changes proposed in the May j
30, 1984 Application remain unchanged by this Amendment Application.
s The proposed changes add the requirement to perform core plate. differential pressure-noise monitoring during single recirculation loop operation, and modify the operability and surveillance requirements associated with APRM and LPRM neutron flux noise monitoring.
Significant Hazards Consideration Determination The proposed changes involve additional surveillance and operating restrictions which minimize the possiblity of core thermal hydraulic instability.
These changes are being proposed 4
in accordance with guidance received from the Division of Licensing of the Nuclear Regulatory Commission during the September 12, 1984 telephone conversation.
The Commission has provided guidance concerning the application of the standards for determining whether license caendments involve no significant hazards consideration by providing certain examples (48 FR 14870).
Example (ii) is a 3
change that constitutes an additional limitation, restriction, or control not presently-included in the Technical Specifications.
The changes proposed by this application fit this e-mple of actions not involving a significant hazards consideration.
Consequently, Licensee has concluded, in accordance with NRC Guidance (48 FR 14870) and the provisions of Section 50.92 of the Commission's regulations, that these changes do not constitute a significant hazards consideration since'they do not:
(1) involve a significant increase in the probability or consequences of an accident previously evaluated, or (2) create the possibility of a new or different kind of accident from any accident previously evaluated, or (3) involve a significant reduction in a margin of safety.
The Plant Operating Review Committee and the Nuclear Review Board (off-site safety review committee) have reviewed these proposed changes to the Technical Specificatior.s and have concluded that they do not involve an unreviewed safety question or a significant hazard consideration, and will not endanger the health and safety of the public.
Respectfully submitted, PHILADELPHIA ELECTRIC COMPANY By:
i Vice President' COMMONWEALTH OF. PENNSYLVANIA ss.
COUNTY OF PHILADELPHIA S'.
L. Daltroff, being first duly sworn,-deposes and says:
That he is Vice President of Philadelphia Electric Company, the Applicant herein; that he has read the foregoing Amendment to Application for Amendment of Facility Operating Licenses and knows the contents thereof; and that the state nts and matters set forth therein are true and correct to the best of his knowledge, information and belief.
f/lr
-w, s itM: W//'
Subscribed and sworn to before me this hlY day of U
l$W I
T l
. Notary.Public l
PATRICIA 0. SCHOLL Notary Publ.c, PNiadeipdia. Philadchhia Co.
~
My Cornmission.Espees february 10,1386
CERTIFICATE OF SERVICE I certify that service of the foregoing Amendment was made upon the' Commonwealth of Pennsylvania, by mailing a copy thereof, via first-class' mail, to Thomas R..Gerusky, Director, Bureau
- of Radiological Protection, P.O. Box 2063, Harrisburg, PA 17120;.
all this 27th. day. of September, 19814.
A Eug-e[.Bradley At orney for Philadelphia Electric Company p