Application to Amend Licenses DPR-53 & DPR-69,revising Tech Specs to Incorporate New Meteorological Instrumentation Providing Essential Parameters in Support of Dose Assessment Calculations for Emergency Preparedness.Fee Paid
ML20098D177
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 09/20/1984
From: Lundvall A
BALTIMORE GAS & ELECTRIC CO.
To: John Miller
Office of Nuclear Reactor Regulation
Shared Package
ML20098D181 List:
References
NUDOCS 8409270396
Download: ML20098D177 (4)


Text

.

BALTIM ORE GAS AND ELECTRIC CHARLES CENTER P.O. BOX 1475 BALTIMORE, MARYLAND 21203 ARTHUR E. LUNDVALL. JR.

vice me.ioca" SUPPLY September 20,1984 CERTIFIED MAIL U. S. Nuclear Regulatory Commission Office of Nuclear Reactor Regulation Washington, D. C. 20555 ATTENTION: Mr. James. R. Miller, Chief Operating Reactors Branch #3 Division of Licensing

SUBJECT:

Calvert Cliffs Nuclear Power Plant Unit Nos.1 & 2, Docket Nos. 50-317 & 50-318 Request for Amendment

REFERENCES:

(a) I&E Inspection Report 50-317/83-35; 30-318/83-35 (b) Letter from Mr. A. E. Lundvall, Jr., to Mr. T. T. Martin dated June 29,1984, Radiological Dose Assessment Capability During Emergencies Gentlemen:

The Baltimore Gas and Electric Company hereby requests an amendment to its operating i! License Nos. DPR-53 and DPR-69 for Calvert Cliffs Unit Nos.1 & 2, respectively, with the submittal of the enclosed proposed change to the Technical Specifications.

CHANGE (BG&E FCR 84-110)

Remove existing pages 3/4 3-35, 3/4 3-36, B 3/4 3-2, and 5-2 of the Unit Nos. I and 2 l Technical Specifications and replace with attached marked up pages.

DISCUSSION This proposed change to the Technical Specifications is being processed in response to reference (a), Open Item 83-35-06, concerning incorporation of new meteorological instrumentation into the Technical Specifications.

8409270396 840920 t DR ADOCK 05000 I

g hcHe #

L

m h .,;, . X

- Mr. James R. Miller

~

September 20,- 1984

' Page 2 This proposed change requests incorporation of'a new meteorological. system that will provide the essential. parameters used in support of dose assessment calculations for.

Lemergency. preparedness. . The new meteorological tower and associated instruments were installed to correct Instrument exposure problems identified with the older instruments and tower, improve instrument accuracy and provide wind measurements at

~t he 10 meter elevation to conform to Regulatory Guide 1.23-Rev. I and NUREG's 0654

- and 0737. The new meteorological system represents a marked improvement over the old system. iThe.new system will be considered the " primary" meteorological system as addressed in Regulatory Guide 1.23-Rev.1.

A ~ description of the meteorological instrument channels proposed to be added to the

' operability requirements is as follows:

- Lwind speed at elevations of 10 meters and 60 meters to replace old wind speed at 125 feet and 200 feet respectively; T wind direction at elevations of 10 meters and 60 meters to replace old wind direction et 125 feet and 200 feet respectively; and,

- differential - temperature between 10 and 60 meters to replace old differential temperature between 30 and 200 feet In addition ~ it'is proposed to delete the operability requirement for the differential temperature- measurement channel between 30 and 125 feet as this measurement

- m provides no' additional useful information.and is not specified by regulatory guidance.

Operating experience has shown that daily channel checks and semi-annual calibrations are ; adequate: to' ensure %at the equipment provides the minimum data availability

! required by regulatory guidance for these instruments. It is also proposed to show the location of the new tower and delete the labeling of the old tower on Figure 5.1-1 in the Design Features section of the Technical Specifications.

The new tower and associated instruments substantially conform to and meet the intent L of guidance provided in NUREG 0654 and Regulatory Guide 1.23-Rev. I concerning the

primary meteorological system. In two cases the design of the new tower and system differ from the literal statements in Regulatory Guide 1.23-Rev.1. However, in both cases the . intent of the Regulatory Guide is met. The Regulatory Guide states that,

= whenever possible, the base of the primary tower should be at the same elevation as

. plant grade so that the upper sensor set at 60 meters corresponds to the effluent release

~

point at the plant vent. The base of the new tower is 65 feet (approximately 20 meters)

. above plant grade. However, the intent of the regulatory guidance is met in that, especially during low wind (laminar flow) conditions which are conservative, the upper sensors on'the new tower measure conditions indicative of the conditions at the plant vent. Regulatory Guide 1.23-Rev. I also requires that meteorological parameters from the primary tower be displayed in the control room, reference (a) item 83-35-05 refers.

' The new. system utilizes a dose assessment computer terminal in lieu of strip chart

-recorders in the control room. The operator can call up either 10 second data in real i

k m.~ . ,' . . , , , . , , ,,- , ,,,,,,, - . ,. - . ,_.__ ,m.r _ .., m - r ..,,,,mM

y 4

Mr. James R. Miller September 20,1984 Page 3 time or 15 minute averaged data and obtain hard copy if desired. The intent of the regulatory guidance is met in that information from the primary instruments is readily available through a series of simple commands. These concerns are addressed in more detail in enclosure (1) of reference (b).

The possiblity of the continued use of the old meteorological instruments as the "back up" system as addressed in Regulatory Guide 1.23-Rev. I and the use of strip chart recorders or other continuous display devices in the control room for the primary instruments is currently being evaluated.

DETERMINATION OF SIGNIFICANT HAZARDS CONSIDERATIONS This proposed change to the Technical Specifications has been determined to involve no significant hazards considerations, in that operation of the facility in accordance with the proposed license amendment would not:

(i) involve any significant increase in the probability or consequences of an accident previously evaluated; or (ii) create the possibility of a new or different kind of accident kom any accident previously evaluated; or (iii) involve any reduction in the margin of safety In fact, since the new meteorological instruments are more accurate and better located, this proposed change should result in an improvement to the margin of safety.

SAFETY REVIEW COMMITTEE This proposed change to the Technical Specifications and our determination of significant hazards have been reviewed by our Plant Operations and Off-Site Safety Review Committees, and they have concluded that implementation of these changes will not result in an undue risk to the health and safety of the public.

, - - - - , - y -- - - - -

w =

r-Mr. James R. Miller September 20,1984 Page 4

' FEE DETERMINATION Pursuant to 10 CFR 170.21, we are including BG&E check number B394554 in the amount of $150.00 to cover the application fee for this request.

Very truly yours,

/ ~

y- c . Jan~

AEL/MTF/sjb

- STATE OF MARYLAND :

TO WIT: .

CITY OF BALTIMORE :

Arthur E. Lundvall, Jr., being duly sworn states that he is Vice President of the Baltimore Gas and Electric Company, a corporation of the State of Maryland; that he provides the foregoing response for the purpose therein set forth; that the statements made are true and correct to the best of his knowledge, information, and belief; and that he was authorized to provide the response on behalf of said Corporation.

WITNESS my Hand and Notarial Seal: Y[uic.Notary Public My Commission Expires: kro// ,/f[b cc: D. A. Brune, Esquire '

G. F. Trowbridge, Esquire D. H. Jaffe, NRC T. Foley, NRC R. E. Corcoran, DHMH

. .,. .-. -.