7590-01 UNITED STATES NUCLEAR REGULATORY COP 941SSION DIABLO CANYON NUCLEAR POWER PLANT. UNIT NO. 1 DOCKET NO. 50-275 NOTICE OF CONSIDERATION OF ISSUANCE OF AMENDMENT TO FACILITY OPERATING LICENSE. PROPOSED NO SIGNIFICANT HAZARDS CONSIDERATION DETERMINATION. AND OPPORTUNITY FOR A HEARING The U.S. Nuclear Regulatory Commission (the Commission) is considering issuance of an amendment to Facility Operating License No. DPR-80 issued to Pacific Gas and Electric Company (the licensee) for operation of the Diablo Canyon Nuclear Power Plar.t, Unit No. 1, located in San Luis Obispo County, California.

The proposed amendment would revise the combined Technical Specifications (TS) for the Diablo Canyon Power Plant, Unit Nos. I and 2, to allow operation of Unit 1 in Mode 3 (Hot Standby) during installation of a replacement nonvital auxiliary transformer 1-1.

Specifically, TS 3/4.8.1.1,

" Electrical Power Systems - A.C. Sources - Operating," Action Statement (a),

would be revised to permit a one-time extension of the allowed outage time (A0T) from 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> to 120 hours0.00139 days <br />0.0333 hours <br />1.984127e-4 weeks <br />4.566e-5 months <br />.

Before issuance of the proposed license amendment, the Commission will have made findings required by the Atomic Energy Act of 1954, as amended (the Act), and the Commission's regulations.

The Commission has made a proposed determination that the amendment request involves no significant hazards consideration. Under the Commission's regulations in 10 CFR 50.92, this means that operation of the facility in accordance with the proposed amendment would not (1) involve a significant h

gg20 gag ggagpj, P

1

+

' increase in the probability or consequences of an accident previously j

i evaluated; or (2) create the possibility of a new or different kind of accident from any accident previously evaluated; or (3) involve a significant reduction in a margin of safety. As required by 10 CFR 50.91(a), the licensee has provided its analysis of the issue of no significant hazards consideration, which is presented below:

1.

The proposed change does not involve a significant increase in the probability or consequences of an accident previously evaluated.

A probabilistic risk assessment (PRA) evaluation shows that the probability of a loss of off site power duration is increased slightly by the allowed outage time (A0T) increase from 72 to 120 hours0.00139 days <br />0.0333 hours <br />1.984127e-4 weeks <br />4.566e-5 months <br />. The core damage probability is 1.2 E-7 for the total 120 hour0.00139 days <br />0.0333 hours <br />1.984127e-4 weeks <br />4.566e-5 months <br /> A0T. Based on EPRI/NEI [ Electric Power Research Institute / Nuclear Energy Institute] guidance, this increase is not considered significant.

The consequences of the 230 kV system loss are not affected by increasing the A0T of the 500 ki' system. Additionally, the consequences of the potential event are mitigated by the compensatory measures taken to asstre the reliability of the remaining power sources.

Therefore, the proposed change does not significantly increase the probability or consequences of an accident previously evaluated.

2.

The proposed change does not create the possibility of a new or different kind of accident from any accident previously evaluated.

The proposed change does not affect the method of operating any equipment at Diablo Canyon Power Plant. Additionally, the proposed extension of the A0T does not result in a physical modification to any equipment.

l Therefore, the proposed change does not create the possibility of a new or different kind of accident from any accident previously evaluated.

3.

The proposed change does not involve a significant reduction in a margin of safety.

A PRA evaluation has shown that the impact of extending the A0T has no significant impact on core damage frequency. Additionally,

-.. ~.

_3_

compensatory measures have been implemented to minimize the potential of losing the 230 kV system.

Therefore, the proposed change does not involve a significant reduction in a margin of safety.

The NRC staff has reviewed the licensee's analysis and, based on this review, it appears that the three standards of 10 CFR 50.92(c) are satisfied.

Therefore, the NRC staff proposes to determine that the amendment request involves no significant hazards consideration.

The Commission is seeking public comments on this proposed dotermination.

Any comments received within 30 days after the date of publication of this notice will be considered in making any final determination.

Normally, the Commission will not issue the amendment until the expiration of the 30-day notice period. However, should circumstances change during the notice period such that failure to act in a timely way would result, for example, in derating or shutdown of the facility, the Commission may issue the license amendment before the expiration of the 30-day notice period, provided that its final determination is that the amendment involves no significant hazards consideration. The final determination will consider all public and State comments received.

Should the Commission take this action, it will publish in the FEDERAL REGISTER a notice of issuance and provide for opportunity for a hearing after issuance.

The Commission expects that the need to take this action will occur very infrequently.

Written comments may be submitted by mail to the Rules Review and Directives Branch, Division of Freedom of Information and Publications Services, Office of Administration, U.S. Nuclear Regulatory Commission, Washington, DC 20555, and should cite the publication date and page number of

.4-this FEDERAL REGISTER notice. Written comments may also be delivered to Room 6022, Two White Flint North, 11545 Rockville Pike, Rockville, Maryland, from 7:30 a.m. to 4:15 p.m. Federal workdays. Copies of written comments received may be examined at the NRC Public Document Room, the Gelman Building, 2120 L Street, NW., Washington, DC.

The filing of requests for hearing and petitions for leave to intervene is discussed below.

By March 4, 1996

, the licensee may file a request for a hearing with respect to issuance of the amendment to the subject facility operating license and any person whose interest may be affected by this proceeding and who wishes to participate as a party in the proceeding must file a written request for a hearing and a petition for leave to intervene.

Requests for a hearing and a petition for leave to intervene shall be filed in accordance with the Commission's " Rules of Pr actice for Domestic Licensing Proceedings" in 10 CFR Part 2.

Interested persons should consult a current copy of 10 CFR 2.714 which is available at the Commission's Public Document' Room, the Gelman Building, 2120 L Street, NW., Washington, DC, and at the local public document room located at the California Polytechnic State University, Robert E. Kennedy Library, Government Documents and Maps Department, San Luis Obispo, California 93407.

If a request for a hearing or petition for leave to intervene is filed by the above date, the Commission or an Atomic Safety and Licensing Board, designated by the Commission or by the Chairman of the Atomic Safety and Licensing Board Panel, will rule on the request and/or petition; and the Secretary or the designated Atomic Safety and Licensing Board will issue a notice of hearing or an appropriate order.

As required by 10 CFR 2.714, a petition for leave to intervene shall set forth with particularity. the interest of the petitioner in the proceeding, and how that interest may be affected by the results of the proceeding.

The petition should specifically explain the reasons why intervention should be permitted with particular reference to the following factors:

(1) the nature of the petitioner's right under the Act to be made party to the proceeding; (2) the nature and extent of the petitioner's property, financial, or other interest in th'e proceeding; and (3) the possible effect of any order which may be entered in the proceeding on the petitioner's interest.

The petition should also identify the specific aspect (s) of the subject matter of the proceeding as to which petitioner wishes to intervene. Any person who has filed a petition for leave to intervene or who has been admitted as a party may amend the petition without requesting leave of the Board up to 15 days prior to the first prehearing conference scheduled in the proceeding, but such an amended petition must satisfy the specificity requirements described above.

Not later than 15 days prior to the first prehearing conference scheduled in the proceeding, a petitioner shall file a supplement to the petition to intervene which must include a list of the contentions which are sought to be litigated in the matter.

Each contention must consist of a specific statement of the issue of law or fact to be raised or controverted.

In addition, the petitioner shall provide a brief explanation of the bases of the contention and a concise statement of the alleged facts or expert opinion which support the contention and on which the petitioner intends to rely in proving the contention at the hearing. The petitioner must also provide references to those specific sources and documents of which the petitioner is aware and on which the petitioner intends to rely to establish those facts or

" expert opinion.

Petitioner must provide sufficient information to show that a genuine dispute exists with the applicant on a material issue of law or fact.

Contentions shall be limited to matters within the scope of the amendment under consideration. The contention must be one which, if proven, would entitle the petitioner to relief. A petitioner who fails to file such a supplement which satisfies these requirements with respect to at least one contention will not be pennitted to participate as a party.

Those permitted to intervene become parties to the proceeding, subject to any limitations in the order granting leave to intervene, and have the opportunity to participate fully in the conduct of the hearing, including the opportunity to present evidence and cross-examine witnesses.

If a hearing is requested, the Comission will make a final determination on the issue of no significant hazards consideration.

The final determination will serve to decide when the hearing is held.

If the final determination is that the amendment request involves no significant hazards consideration, the Comission may issue the amendment and make it imediately effective, notwithstanding the request for a hearing. Any hearing held would take place after issuance of the amendment.

If the final determination is that the amendment request involves a significant hazards consideration, any hearing held would take place before the issuance of any amendment.

A request for a hearing or a petition for leave to intervene must be filed with the Secretary of the Commission, U.S. Nuclear Regulatory Commission, Washington, DC 20555, Attention: Docketing and Services Branch, or may be delivered to the Comission's Public Document Room, the Gelman Building, 2120 L Street, NW., Washington, DC, by the above date.

Where

~

': l petitions are filed during the last 10 days of the notice period, it is requested that the petitioner promptly so inform the Commission by a toll-free telephone call to Western Union at 1-(800) 248-5100 (in Missouri 1-(800) 342-6700). The Western Union operator should be given Datagram Identification Number N1023 and the following message addressed to William H. Bateman, Director, Project Directorate IV-2: petitioner's name and telephone number, date petition was mailed, plant name, and publication date and page number of this FEDERAL REGISTER notice. A copy of the petition should also be sent to the Office of the General Counsel, U.S. Nuclear Regulatory Commission, Washington, DC 20556, and to Christopher J. Warner, Esq., Pacific Gas and Electric Company, P.O. Box 7442, San Francisco, California 94120, attorney for the licensee.

Nontimely filings of petitions for leave to intervene, amended petitions, supplemental petitions and/or requests for hearing will not be entertained absent a determination by the Commission, the presiding officer or the presiding Atomic Safety and Licensing Board that the petition and/or request should be granted based upon a balancing of the factors specified in 10 CFR 2.714(a)(1)(1)-(v) and 2.714(d).

For further details with respect to this action, see the application for amendment dated January 18, 1996, which is available for public inspection at the Commission's Public Document Room, the Gelman Building, 2120 L Street, NW., Washington, DC, and at the local public document room located at the i

l

~

i l

4 l

CLiifornia Polytechnic State University, Robert E. Kennedy Library, Government i

Documents and Maps Department, San Luis Obispo, California 93407.

Dated at Rockville, Maryland, this 26th day of January 1996.

FOR THE NUCLEAR REGULATORY COMISSION n

l '

/ Steven D. Bloom, Project Manager Project Directorate IV-2 Division of Reactor Projects - III/IV Office of Nuclear Reactor Regulation

- - --- l