ML20097A707
ML20097A707 | |
Person / Time | |
---|---|
Site: | Byron, Braidwood, Comanche Peak, 05000000 |
Issue date: | 09/07/1984 |
From: | Swartz E COMMONWEALTH EDISON CO. |
To: | Harold Denton Office of Nuclear Reactor Regulation |
References | |
9161N, NUDOCS 8409130352 | |
Download: ML20097A707 (1) | |
Category:CORRESPONDENCE-LETTERS
MONTHYEARTXX-9924, Forwards Responses to Questions by NRC Re Application for Amends to Licenses NPF-87 & NPF-89,by Incorporating Changes Increasing RWST low-level Setpoint from Greater than But Equal to 40% to Greater than But Equal to 45% of Span1999-10-22022 October 1999
[Table view]Forwards Responses to Questions by NRC Re Application for Amends to Licenses NPF-87 & NPF-89,by Incorporating Changes Increasing RWST low-level Setpoint from Greater than But Equal to 40% to Greater than But Equal to 45% of Span ML20217M2871999-10-21021 October 1999 Refers to Rev 5 Submitted in May 1999 for Portions of Byron Nuclear Power Station Generating Stations Emergency Plan Site Annex.Informs That NRC Approval Not Required Based on Determination That Plan Effectiveness Not Decreased ML20217P6171999-10-21021 October 1999 Forwards non-proprietary & Proprietary Versions of HI-982083, Licensing Rept for Byron & Braidwood Nuclear Stations. Proprietary Rept Withheld,Per 10CFR2.790(b)(4) ML20217M5711999-10-20020 October 1999 Forwards Insp Repts 50-445/99-15 & 50-446/99-15 on 990822- 1002.Two Severity Level IV Violations of NRC Requirements Identified & Being Treated as non-cited Violations Consistent with App C of Enforcement Policy ML20217M4361999-10-19019 October 1999 Forwards Rev 46 to Braidwood Station Security Plan, IAW 10CFR50.4(b)(4).Description of Changes,Listed.Encl Withheld Per 10CFR73.21 ML20217H4661999-10-18018 October 1999 Forwards Changes to EPIPs IAW 10CFR50.54(q) & 10CFR50,App E, Section V.Details of Changes Encl TXX-9923, Forwards Monthly Operating Repts for Sept 1999 for CPSES, Units 1 & 2,per Plant TS 5.6.4.No Failures of Challenges to PORVs of SV for Units Occurred1999-10-15015 October 1999 Forwards Monthly Operating Repts for Sept 1999 for CPSES, Units 1 & 2,per Plant TS 5.6.4.No Failures of Challenges to PORVs of SV for Units Occurred ML20217G9791999-10-14014 October 1999 Forwards SE Accepting Relief Requests to Rev 5 of First 10-year Interval Inservice Insp Program for Plant,Units 1 & 2 ML20217E7951999-10-12012 October 1999 Forwards COLR for Unit 1,Cycle 8,per TS 5.6.5 ML20217F7891999-10-0808 October 1999 Forwards Insp Repts 50-454/99-12 & 50-455/99-12 on 990803- 0916.One Violation Occurred Being Treated as NCV ML20217B6351999-10-0505 October 1999 Forwards for Info,Final Accident Sequence Precursor Analysis of Operational Event at Byron Station,Unit 1,reported in LER 454/98-018 & NRC Responses to Util Specific Comments Provided in ML20212L1791999-10-0505 October 1999 Informs That as Result of Staff Review of Util Responses to GL 92-01,rev 1,suppl 1 & Suppl 1 Rai,Staff Revised Info in Rvid & Is Releasing Rvid Version 2 ML20217B2991999-10-0101 October 1999 Forwards Insp Repts 50-454/99-16 & 50-455/99-16 on 990907-10.No Violations Noted.Water Chemisty Program Was Well Implemented,Resulted in Effective Control of Plant Water Chemistry ML20216J5571999-10-0101 October 1999 Provides Final Response to GL 98-01,suppl 1, Y2K Readiness of Computer Sys at Npps ML20212L2891999-10-0101 October 1999 Discusses Closeout of GL 97-06, Degradation of Steam Generator Internals. Purpose of GL Was to Obtain Info That Would Enable NRC to Verify That Condition of Licensee SG Internals Comply with Current Licensing Bases TXX-9922, Forwards Revised COLR, for Cycle 5 for Unit 21999-10-0101 October 1999 Forwards Revised COLR, for Cycle 5 for Unit 2 ML20216J8241999-09-30030 September 1999 Notifies of Removal of NRC Headquarters & Region III Offices from Controlled Copy Distribution of Certain CE Documents. Specific Documents,Associated Controlled Copy Numbers & NRC Location Affected Are Shown on Attachment to Ltr ML20212J6751999-09-30030 September 1999 Forwards Replacement Pages Eight Through Eleven of Insp Repts 50-454/99-15 & 50-455/99-15.Several Inaccuracies with Docket Numbers & Tracking Numbers Occurred in Repts ML20217A5821999-09-29029 September 1999 Advises of NRC Plans for Future Insp Activities at Facility for Licensee to Have Opportunity to Prepare for Insps & to Provide NRC with Feedback on Any Planned Insps Which May Conflict with Plant Activities ML20217A9311999-09-29029 September 1999 Informs That NRC 6-month Review of Braidwood Identified That Performance in Maint Area Warranted Increased NRC Attention. Addl Insps Beyond Core Insp Program Will Be Conducted Over Next 6 Months to Better Understand Causes of Problem ML20212H0461999-09-24024 September 1999 Forwards Rev 6 to CPSES Glen Rose,Tx ASME Section XI ISI Program Plan for 1st Interval on 990820 ML20212G0721999-09-24024 September 1999 Forwards Rev 4 to Augmented Inservice Insp Plan for CPSES, Unit 1. Future Changes & Revs to Unit 1 Augmented Inservice Insp Plan Will Be Available on Site ML20212F7481999-09-24024 September 1999 Forwards SER Authorizing Relief from Exam Requirement of 1986 Edition ASME Code,Section XI Pursuant to 10CFR50.55a(a)(3)(ii) for Relief Request A-3 & 10CFR50.55a(g)(6)(i) for Relief Requests B15,16,17 & C-4 ML20212F1041999-09-23023 September 1999 Requests That NRC Be Informed of Any Changes in Scope of Y2K System Deficiencies Listed or Util Projected Completion Schedule for Comanche Peak Steam Electric Station,Units 1 & 2 ML20216H4301999-09-23023 September 1999 Informs That Arrangements Made for Administration of Licensing re-take Exams at Braidwood Generating Station for Week of 991108 ML20212E6661999-09-21021 September 1999 Advises That Info Contained in Application & Affidavit, (CAW-99-1342) Re WCAP-15009,Rev 0, Comache Peak Unit 1 Evaluation for Tube Vibration Induced Fatigue, Will Be Withheld from Public Disclosure ML20216F8051999-09-17017 September 1999 Forwards Insp Rept 50-454/99-14 & 50-455/99-14 on 990823-27. Security Program Was Effectively Implemented in Areas Inspected.No Violations Were Identified ML20216F7441999-09-17017 September 1999 Forwards Insp Repts 50-456/99-13 & 50-457/99-13 on 990706-0824.Three Violations Noted & Being Treated as Ncvs. Insp Focused on C/As & Activities Addressing Technical Concerns Identified During Design Insp Completed on 980424 ML20212D9111999-09-16016 September 1999 Informs That on 990818,NRC Completed Midcycle PPR of CPSES & Did Not Identify Any Areas in Which Performance Warranted Insp Beyond Core Insp Program.Core Insp Plan at Facility Over Next 7 Months.Insp Plan Through March 2000 Encl ML20212A7601999-09-14014 September 1999 Forwards Insp Repts 50-445/99-14 & 50-446/99-14 on 990707-0821.Four Violations Occurred & Being Treated as Ncvs.Conduct of Activities Was Generally Characterized by safety-conscious Operations & Sound Radiological Controls ML20212A6991999-09-10010 September 1999 Forwards SE Accepting Licensee Second 10-year Interval ISI Program Request for Relief 12R-07 for Plant,Units 1 & 2 TXX-9921, Suppls 981221 LAR 98-010 to Licenses NPF-87 & NPF-89, Clarfying Conditions of Use Re Analytical Methods Used to Determine Core Operating Limits,Per Telcon with NRC1999-09-10010 September 1999 Suppls 981221 LAR 98-010 to Licenses NPF-87 & NPF-89, Clarfying Conditions of Use Re Analytical Methods Used to Determine Core Operating Limits,Per Telcon with NRC ML20211Q9011999-09-0808 September 1999 Advises That Us Postal Service Mailing Address Has Changed for Braidwood Station.New Address Listed ML20211P1841999-09-0808 September 1999 Forwards Insp Repts 50-454/99-15 & 50-455/99-15 on 990824- 26.No Violations Noted.Objective of Insp to Determine Whether Byron Nuclear Generating Station Emergency Plan Adequate & If Emergency Plan Properly Implemented ML20211P3761999-09-0707 September 1999 Ack Receipt of Ltr Dtd 990615,transmitting Rev 30 to Physical Security Plan,Per 10CFR50.54(p).No NRC Approval Is Required ML20211Q6821999-09-0606 September 1999 Informs That NRC Tentatively Scheduled Initial Licensing Exam for Byron Operator Licesne Applicants During Wks of 000619 & 26.Validation of Exam Will Occur at Station During Wk of 000529 ML20211Q6611999-09-0606 September 1999 Informs That NRC Tentatively Scheduled Initial Licensing Exam for Braidwood Operator License Applicants During Wk of 010115 & 22.Validation of Exam Will Occur at Station During Wk of 001218 ML20211P1901999-09-0303 September 1999 Forwards Insp Repts 50-456/99-12 & 50-457/99-12 on 990707-0816.No Violations Noted.Insp Generally Characterized by safety-conscious Operations,Sound Engineering & Maint Practices & Careful Radiological Work Controls ML20211L9871999-09-0303 September 1999 Forwards Rev 31 to Technical Requirements Manual. All Changes Applicable to Plants Have Been Reviewed Under Util 10CFR50.59 Process & Found Not to Include Any USQs TXX-9915, Responds to 990701 & 0825 RAI Telcons Re Spent Fuel Pool Temp,Per LAR 98-008,which Requested Increase in Spent Fuel Storage capacity.Marked-up Page 4-1 of CPSES Fuel Storage Licensing Rept, Encl1999-09-0303 September 1999 Responds to 990701 & 0825 RAI Telcons Re Spent Fuel Pool Temp,Per LAR 98-008,which Requested Increase in Spent Fuel Storage capacity.Marked-up Page 4-1 of CPSES Fuel Storage Licensing Rept, Encl ML20211N5151999-09-0303 September 1999 Ack Receipt of Re Safety Culture & Overtime Practices at Byron Nuclear Power Station.Copy of Recent Ltr from NRC to Commonwealth Edison Re Overtime Practices & Safety Culture Being Provided ML20211M1371999-09-0202 September 1999 Discusses 990527 Meeting with Ceco & Byron Station Mgt Re Overtime Practices & Conduciveness of Work Environ to Raising Safety Concerns at Byron Station.Insp Rept Assigned for NRC Tracking Purposes.No Insp Rept Encl ML20211K1081999-09-0202 September 1999 Responds to Request for Addl Info to GL 92-01,Rev 1,Suppl 1, Reactor Vessel Structural Integrity, for Braidwood,Units 1 & 2 & Byron,Unit 2 ML20211P1761999-09-0202 September 1999 Discusses Licensee Aug 1998 Rev 3K to Portions of Braidwood Nuclear Power Station Generating Stations Emergency Plan Site Annex Submitted Under Provisions of 10CFR50.54(q). NRC Approval Not Required ML20211K2231999-08-31031 August 1999 Forwards Txu Electric Comments of Rvid,Version 2 ML20211J3801999-08-27027 August 1999 Forwards Corrected TS Page 3.8-26 to Amend 66 to Licenses NPF-87 & NPF-89,respectively.Footnote on TS Page 3.8-26 Incorrectly Deleted ML20211G1221999-08-27027 August 1999 Forwards fitness-for-duty Program Performance Data for Each of Comm Ed Nuclear Power Stations & Corporate Support Employees within Scope of Rule for six-month Period Ending 990630,IAW 10CFR26.71(d) ML20211G7301999-08-26026 August 1999 Forwards Revs 29 & 30 to CPSES Technical Requirements Manual (Trm). Attachments 1 & 2 Contain Description of Changes for Revs 29 & 30 Respectively ML20211G1081999-08-26026 August 1999 Responds to NRR Staff RAI Re Util Mar 1999 Submittal for NRC Review & Approval of Changes to CPSES Emergency Classification Procedure ML20211G3441999-08-25025 August 1999 Forwards Response to NRC RAI on LAR 98-010 for Cpses,Units 1 & 2.Communication Contains No New Licensing Commitments Re Cpses,Units 1 & 2 1999-09-08 Category:INCOMING CORRESPONDENCE MONTHYEARTXX-9924, Forwards Responses to Questions by NRC Re Application for Amends to Licenses NPF-87 & NPF-89,by Incorporating Changes Increasing RWST low-level Setpoint from Greater than But Equal to 40% to Greater than But Equal to 45% of Span1999-10-22022 October 1999
[Table view]Forwards Responses to Questions by NRC Re Application for Amends to Licenses NPF-87 & NPF-89,by Incorporating Changes Increasing RWST low-level Setpoint from Greater than But Equal to 40% to Greater than But Equal to 45% of Span ML20217P6171999-10-21021 October 1999 Forwards non-proprietary & Proprietary Versions of HI-982083, Licensing Rept for Byron & Braidwood Nuclear Stations. Proprietary Rept Withheld,Per 10CFR2.790(b)(4) ML20217M4361999-10-19019 October 1999 Forwards Rev 46 to Braidwood Station Security Plan, IAW 10CFR50.4(b)(4).Description of Changes,Listed.Encl Withheld Per 10CFR73.21 ML20217H4661999-10-18018 October 1999 Forwards Changes to EPIPs IAW 10CFR50.54(q) & 10CFR50,App E, Section V.Details of Changes Encl TXX-9923, Forwards Monthly Operating Repts for Sept 1999 for CPSES, Units 1 & 2,per Plant TS 5.6.4.No Failures of Challenges to PORVs of SV for Units Occurred1999-10-15015 October 1999 Forwards Monthly Operating Repts for Sept 1999 for CPSES, Units 1 & 2,per Plant TS 5.6.4.No Failures of Challenges to PORVs of SV for Units Occurred ML20217E7951999-10-12012 October 1999 Forwards COLR for Unit 1,Cycle 8,per TS 5.6.5 ML20216J5571999-10-0101 October 1999 Provides Final Response to GL 98-01,suppl 1, Y2K Readiness of Computer Sys at Npps TXX-9922, Forwards Revised COLR, for Cycle 5 for Unit 21999-10-0101 October 1999 Forwards Revised COLR, for Cycle 5 for Unit 2 ML20216J8241999-09-30030 September 1999 Notifies of Removal of NRC Headquarters & Region III Offices from Controlled Copy Distribution of Certain CE Documents. Specific Documents,Associated Controlled Copy Numbers & NRC Location Affected Are Shown on Attachment to Ltr ML20212G0721999-09-24024 September 1999 Forwards Rev 4 to Augmented Inservice Insp Plan for CPSES, Unit 1. Future Changes & Revs to Unit 1 Augmented Inservice Insp Plan Will Be Available on Site ML20212H0461999-09-24024 September 1999 Forwards Rev 6 to CPSES Glen Rose,Tx ASME Section XI ISI Program Plan for 1st Interval on 990820 TXX-9921, Suppls 981221 LAR 98-010 to Licenses NPF-87 & NPF-89, Clarfying Conditions of Use Re Analytical Methods Used to Determine Core Operating Limits,Per Telcon with NRC1999-09-10010 September 1999 Suppls 981221 LAR 98-010 to Licenses NPF-87 & NPF-89, Clarfying Conditions of Use Re Analytical Methods Used to Determine Core Operating Limits,Per Telcon with NRC ML20211Q9011999-09-0808 September 1999 Advises That Us Postal Service Mailing Address Has Changed for Braidwood Station.New Address Listed TXX-9915, Responds to 990701 & 0825 RAI Telcons Re Spent Fuel Pool Temp,Per LAR 98-008,which Requested Increase in Spent Fuel Storage capacity.Marked-up Page 4-1 of CPSES Fuel Storage Licensing Rept, Encl1999-09-0303 September 1999 Responds to 990701 & 0825 RAI Telcons Re Spent Fuel Pool Temp,Per LAR 98-008,which Requested Increase in Spent Fuel Storage capacity.Marked-up Page 4-1 of CPSES Fuel Storage Licensing Rept, Encl ML20211L9871999-09-0303 September 1999 Forwards Rev 31 to Technical Requirements Manual. All Changes Applicable to Plants Have Been Reviewed Under Util 10CFR50.59 Process & Found Not to Include Any USQs ML20211K2231999-08-31031 August 1999 Forwards Txu Electric Comments of Rvid,Version 2 ML20211G1221999-08-27027 August 1999 Forwards fitness-for-duty Program Performance Data for Each of Comm Ed Nuclear Power Stations & Corporate Support Employees within Scope of Rule for six-month Period Ending 990630,IAW 10CFR26.71(d) ML20211G1081999-08-26026 August 1999 Responds to NRR Staff RAI Re Util Mar 1999 Submittal for NRC Review & Approval of Changes to CPSES Emergency Classification Procedure ML20211G7301999-08-26026 August 1999 Forwards Revs 29 & 30 to CPSES Technical Requirements Manual (Trm). Attachments 1 & 2 Contain Description of Changes for Revs 29 & 30 Respectively ML20211G3441999-08-25025 August 1999 Forwards Response to NRC RAI on LAR 98-010 for Cpses,Units 1 & 2.Communication Contains No New Licensing Commitments Re Cpses,Units 1 & 2 ML20210U3981999-08-17017 August 1999 Forwards Monthly Operating Repts for July 1999 for CPSES, Units 1 & 2,per TS 6.9.1.5.No Failures or Challenges to PORVs or SVs for Plant Occurred ML20211C0991999-08-17017 August 1999 Forwards Rev 3 to ASME Section XI ISI Program Plan,Unit 2 - 1st Interval, Replacing Rev 2 in Entirety TXX-9919, Forwards Relief Request A-3,Rev 1 to Unit 1 ISI Program,Per Conversations Between NRC & Txu Electric on 9908021999-08-16016 August 1999 Forwards Relief Request A-3,Rev 1 to Unit 1 ISI Program,Per Conversations Between NRC & Txu Electric on 990802 BW990053, Forwards post-outage Summary Rept for ISI Examinations Conducted During Seventh Refueling Outage of Braidwood Station,Unit 21999-08-13013 August 1999 Forwards post-outage Summary Rept for ISI Examinations Conducted During Seventh Refueling Outage of Braidwood Station,Unit 2 ML20210R6561999-08-13013 August 1999 Forwards Response to NRR 990805 Telcon RAI Re License Amend Request 98-010,to Increase Power for Operation of CPSES Unit 2 to 3445 Mwth & Incorporating Addl Changes Into Units 1 & 2 TS ML20210S6411999-08-12012 August 1999 Informs That Wg Guldemond,License SOP-43780,is No Longer Performing Licensed Duties.Discontinuation of License Is Requested BW990052, Informs That RW Clay,License OP-31044,no Longer Requires Operator License at Braidwood Station1999-08-12012 August 1999 Informs That RW Clay,License OP-31044,no Longer Requires Operator License at Braidwood Station 05000454/LER-1998-008, Informs That Licensee Determined That Suppl Rept to LER 98-008 Is Not Warranted.No Addl Info Was Generated Following Completion of Root Cause Investigation of Following Completion of Corrective Actions Stated in Original LER1999-08-12012 August 1999 Informs That Licensee Determined That Suppl Rept to LER 98-008 Is Not Warranted.No Addl Info Was Generated Following Completion of Root Cause Investigation of Following Completion of Corrective Actions Stated in Original LER ML20210N5651999-08-0606 August 1999 Forwards Rev 8 to Nuclear Generating Stations Emergency Plan, for Plants.With Summary of Changes BW990049, Informs NRC of Plans to Demonstrate Compliance with 10CFR50.46 Requirements for Fuel Predicted to Experience Fuel Pellet to Rod Cladding Gap Reopening,During Current Cycle1999-08-0404 August 1999 Informs NRC of Plans to Demonstrate Compliance with 10CFR50.46 Requirements for Fuel Predicted to Experience Fuel Pellet to Rod Cladding Gap Reopening,During Current Cycle ML20210N1101999-08-0404 August 1999 Provides Supplemental Info to Util 990623 License Amend Request 99-005 Re Bypassing DG Trips.Info Replaces Info Contained in Subject Submittal in Attachment 2,Section II, Description of TS Change Request ML20210J2301999-08-0202 August 1999 Forwards Amend 96 to CPSES Ufsar.Replacement of FSAR Figures with Plant Process Flow Diagrams Meets Intent & Requirements of NRC Reg Guide 1.70,Rev 2 ML20210J6071999-08-0202 August 1999 Forwards line-by-line Descriptions of Changes in Amend 96 to CPSES UFSAR Transmitted by Util Ltr TXX-99166,dtd 990802. Replacment of FSAR Figures with Plant Process Flow Diagrams Meets Intent & Requirements of NRC Reg Guide 1.70,rev 2 TXX-9918, Forwards CPSES 10CFR50.59 Evaluation Summary Rept 0008,for 970802-990201 & CPSES Commitment Matl Change Evaluation Rept 0003,for 970802-9906301999-08-0202 August 1999 Forwards CPSES 10CFR50.59 Evaluation Summary Rept 0008,for 970802-990201 & CPSES Commitment Matl Change Evaluation Rept 0003,for 970802-990630 TXX-9916, Notifies NRC That CPSES Units 1 & 2,improved TS Implemented on 9907271999-08-0202 August 1999 Notifies NRC That CPSES Units 1 & 2,improved TS Implemented on 990727 ML20210M9131999-08-0202 August 1999 Forwards Response to NRC AL 99-02, Operating Reactor Licensing Action Estimates, for Fys 2000 & 2001 for Comed ML20210K0771999-07-30030 July 1999 Submits 30-day Rept Re Discovery of ECCS Evaluation Model Error for Byron & Braidwood Stations,As Required by 10CFR50.46 ML20210J8951999-07-29029 July 1999 Submits Other Actions,As Described,To Be Taken for Valves to Resolve Potential Pressure Locking Concerns,In Light of Extended Period for Valve Bonnet Natural Depressurization,In Response to GL 95-07, Pressure Locking & Thermal.. ML20210G5861999-07-29029 July 1999 Forwards fitness-for-duty Program Performance Data for Six Month Period of Jan-June 1999 BW990045, Forwards Errata to 1998 Radioactive Effluent Release Rept. Info Has Been Corrected & Revised Spreadsheets Included in Attachment to Ltr1999-07-28028 July 1999 Forwards Errata to 1998 Radioactive Effluent Release Rept. Info Has Been Corrected & Revised Spreadsheets Included in Attachment to Ltr ML20210J0121999-07-27027 July 1999 Forwards Summary of Methodology for Determination of NDE Measurement Uncertainty,In Response to Recent Discussions with NRC Re LAR 98-006 Concerning Rev to SG Tube Plugging Criteria ML20210F3121999-07-26026 July 1999 Responds to GL 99-02, Laboratory Testing of Nuclear-Grade Activated Charcoal, TXX-9917, Provides Info Re Augmented Inservice Insp Plan,Which Requires Periodic Insp of Rv Head & Internals Lifting Devices at CPSES1999-07-26026 July 1999 Provides Info Re Augmented Inservice Insp Plan,Which Requires Periodic Insp of Rv Head & Internals Lifting Devices at CPSES ML20210E2151999-07-23023 July 1999 Forwards Byron Unit 1 B1R09 ISI Summary Rept Spring 1999 Outage,980309-990424, in Compliance with Requirements of Article IWA-6000, Records & Repts of Section XI of ASME & P&PV,1989 Edition ML20216D3781999-07-21021 July 1999 Forwards Revised NFM9900022, Braidwood Unit 2 Cycle 8 COLR on ITS Format & W(Z) Function, to Account for Error That W Discovered in Computer Code Used to Calculate PCT During LBLOCA ML20210C2931999-07-21021 July 1999 Supplements 880323 Response to NRC Bulletin 88-02, Rapidly Propagating...Sg Tubes, Non-proprietary WCAP-15010 & Proprietary Rev 0 to WCAP-15009, CP Unit 1 Evaluation for Tube Vibration... Encl.Proprietary Rept Withheld ML20210D3211999-07-21021 July 1999 Provides List of Estimates of Licensing Actions,In Response to Administrative Ltr 99-02,dtd 990603 ML20216D7061999-07-19019 July 1999 Forwards Rev 45 to Braidwood Station Security Plan,Iaw 10CFR50.4(b)(4).Plan Includes Listed Changes.Rev Withheld, Per 10CFR73.21 BW990042, Forwards Braidwood Station,Unit 1 Post Accident Monitoring Rept for Reactor Vessel Level Indication Sys (Rvlis),Due to Facility Train B RVLIS Being Restored to Operable Status After 7-day Completion Time,Per TS 3.3.3 & 5.6.71999-07-16016 July 1999 Forwards Braidwood Station,Unit 1 Post Accident Monitoring Rept for Reactor Vessel Level Indication Sys (Rvlis),Due to Facility Train B RVLIS Being Restored to Operable Status After 7-day Completion Time,Per TS 3.3.3 & 5.6.7 ML20209H2991999-07-16016 July 1999 Withdraws 980529 LAR to Credit Automatic PORV Operation for Mitigation of Inadvertent Safety Injection at Power Accident.Response to NRC 990513 RAI Re LAR Encl 1999-09-08 Category:UTILITY TO NRC MONTHYEARML20059K6741990-09-17017 September 1990
[Table view]Suppls Responses to Violations Noted in Insp Repts 50-454/89-11,50-455/89-13,50-456/89-11 & 50-457/89-11. Corrective Actions:Procedures Changed & Valve Tagging Status Provided ML20059K6141990-09-17017 September 1990 Submits Documentation of 900906 Telcon Re Addl Util Candidate for Licensed Operator Generic Fundamentals Exam Section ML20059K5081990-09-14014 September 1990 Forwards Tj Kovach to E Delatorre Re Visit by Soviet Delegation to Braidwood Nuclear Station in May 1990 ML20059L6611990-09-10010 September 1990 Forwards Byron Station Units 1 & 2 Inservice Insp Program ML20059G8761990-09-10010 September 1990 Forwards Rev 8 to Physical Security Plan.Rev Withheld (Ref 10CFR73.21) ML20059F8461990-09-0404 September 1990 Responds to NRC Re Violations Noted in Insp Repts 50-445/90-22 & 50-446/90-22 on 900606-0705.Corrective action:OPT-467A Changed to Provide Addl Prerequisite Info Re Solid State Protection Sys Switch Lineup During Testing ML20059E4981990-08-31031 August 1990 Forwards Revised Radial Peaking Factor Limit Rept for Cycle 1 Per Tech Specs Through Amend 1 & ML20059E4201990-08-30030 August 1990 Forwards Objectives & Guidelines for 1990 Emergency Preparedness Exercise Scheduled for 901113 ML20028G8281990-08-29029 August 1990 Forwards Comanche Peak Unit 1 Semiannual Radioactive Effluent Release Rept,900403-0630 & ODCM TXX-9030, Forwards Endorsements 40 & 4 to Nelia Policy NF-274 & Maelu Policy M-90,respectively & Endorsements 10,11,12,13,14 & 15 to Maelu Policy MF-1311990-08-27027 August 1990 Forwards Endorsements 40 & 4 to Nelia Policy NF-274 & Maelu Policy M-90,respectively & Endorsements 10,11,12,13,14 & 15 to Maelu Policy MF-131 ML20064A3681990-08-24024 August 1990 Forwards Response to 900517 Request for Addl Info Re Design of Containment Hydrogen Monitoring Sys.Util Proposes Alternative Design That Ensures Both Containment Isolation & Hydrogen Monitoring Sys Operability in Event of LOCA ML20064A3751990-08-24024 August 1990 Forwards Revised Pages to Operating Limits Rept for Cycle 2, Correcting Fxy Portion of Rept,Per Tech Spec 6.9.1.9, Operating Limits Rept ML20059F4381990-08-23023 August 1990 Forwards Public Version of Revised Emergency Plan & Corporate Emergency Response Procedures,Consisting of Rev 1 to EPP-313,Rev 7 to CERP-101,Rev 7 to CERP-102 & Revised Forms.W/Dh Grimsley 900906 Release Memo TXX-9029, Responds to NRC Re Violations Noted in Insp Repts 50-445/89-57 & 50-446/89-57.Corrective Actions:Storage Facilities for Instrumentation & Control Work Packages Improved to Provide Acceptable Protection for Documents1990-08-20020 August 1990 Responds to NRC Re Violations Noted in Insp Repts 50-445/89-57 & 50-446/89-57.Corrective Actions:Storage Facilities for Instrumentation & Control Work Packages Improved to Provide Acceptable Protection for Documents ML20064A0181990-08-16016 August 1990 Submits Supplemental Response to NRC Bulletin 88-008,Suppls 1 & 2.Surveillance Testing Revealed No Leakage,Therefore Charging Pump to Cold Leg Outage Injection Lines Would Not Be Subjected to Excessive Thermal Stresses ML20059A3991990-08-15015 August 1990 Forwards Response to NRC 900521 Request for Addl Info Re Plant Inservice Insp Program ML20058P0571990-08-13013 August 1990 Forwards, Comanche Peak Steam Electric Station Unit 1 Control Room Simulator 10CFR55 Certification Initial Rept ML20063Q1051990-08-10010 August 1990 Forwards Monthly Operating Repts for Jul 1990 for Byron Units 1 & 2 & Corrected Monthly Operating Rept for June 1990 for Unit 2 ML20058N2311990-08-0909 August 1990 Forwards First Half 1990 fitness-for-duty Program Performance Data,Per 10CFR26.71(d).Point of Contact for Personnel,Random Testing Program Results & Confirmed Positive Tests Summary & Mgt Summary Included in Data ML20058N0551990-08-0707 August 1990 Provides Supplemental Response to NRC Bulletin 88-008, Suppls 1 & 2.Surveillance Testing Performed Revealed No Leakage,Therefore,Charging Pump to Cold Leg Injection Lines Would Not Be Subjected to Excessive Thermal Stresses ML20059A5831990-08-0404 August 1990 Responds to Info Request Made During 900802 Meeting Re Inadvertent Safety Injections on 900726 & 30 & Results of 100% Power Plateau Testing TXX-9024, Provides Status of Exam Activity & Revised Completion Schedule for Portion of Exam.Util Deferred Preoperational Testing of Facility Spent Fuel Pool Cooling & Cleanup Sys Until Prior to First Off Loading of Spent Fuel1990-08-0303 August 1990 Provides Status of Exam Activity & Revised Completion Schedule for Portion of Exam.Util Deferred Preoperational Testing of Facility Spent Fuel Pool Cooling & Cleanup Sys Until Prior to First Off Loading of Spent Fuel ML20056A3351990-08-0202 August 1990 Responds to NRC Bulletin 88-009 Requesting That Addressees Establish & Implement Insp Program to Periodically Confirm in-core Neutron Power Reactors.All Timble Tubes Used at Plant Inspected & 18 Recorded Evidence of Degradation TXX-9022, Forwards Detailed Descriptions of Changes in Amend 79 to FSAR for Comanche Peak Steam Electric Station1990-07-31031 July 1990 Forwards Detailed Descriptions of Changes in Amend 79 to FSAR for Comanche Peak Steam Electric Station TXX-9027, Responds to NRC Re Violations Noted in Insp Repts 50-445/90-19 & 50-446/90-19.Corrective Action:Specific Activity within Tech Spec Limits.No Further Corrective Action Required1990-07-30030 July 1990 Responds to NRC Re Violations Noted in Insp Repts 50-445/90-19 & 50-446/90-19.Corrective Action:Specific Activity within Tech Spec Limits.No Further Corrective Action Required ML20055J1571990-07-27027 July 1990 Submits Info Re Replacement of Borg-Warner/Intl Pump,Inc Check Valve Swing Arms,Per .Swing Arms in ASME Code Class 2 Check Valves Will Be Replaced During First Refueling Outage ML20055J1221990-07-25025 July 1990 Notifies That Plants Current Outage Plannings Will Not Include Removal of Snubbers.Removal of Snubbers Scheduled for Future Outages.Completion of Review by NRC by 900801 No Longer Necessary ML20055J1261990-07-25025 July 1990 Notifies That Replacement of 13 Snubbers w/8 Seismic Stops on Reactor Coolant Bypass Line Being Deferred Until Later Outage,Per Rl Cloud Assoc Nonlinear Piping Analyses ML20055H7631990-07-25025 July 1990 Forwards Financial Info Re Decommissioning of Plants ML20056A0461990-07-24024 July 1990 Requests Regional Waiver of Compliance for Containment Pressure Transmitter 1-PT-934 During Coming Outage TXX-9023, Responds to NRC Bulletin 90-001, Loss of Fill-Oil in Transmitters Mfg by Rosemount. No Subj Transmitters in Existence at Facility1990-07-18018 July 1990 Responds to NRC Bulletin 90-001, Loss of Fill-Oil in Transmitters Mfg by Rosemount. No Subj Transmitters in Existence at Facility ML20055G6351990-07-17017 July 1990 Submits Results of Remote Shutdown Panel Environ Survey ML20055H0291990-07-17017 July 1990 Forwards Revised Monthly Performance Rept for Braidwood Unit 2 for June 1990 ML20055G3251990-07-16016 July 1990 Responds to SALP Board Repts 50-454/90-01 & 50-455/90-01 for Reporting Period Nov 1988 - Mar 1990.Effort Will Be Made to Continue High Level of Performance in Areas of Radiological Controls,Plant Operations,Emergency Preparedness & Security ML20055F9391990-07-13013 July 1990 Advises That Operators Have Gained Significant Experience in Operating Plant Under Wide Range of Conditions & Have Demonstrated Necessary Proficiency to Safely Operate Unit ML20055F9371990-07-13013 July 1990 Submits Info Re Revised Acceptance Criteria for THERMO-LAG Fire Barrier,Per 900705 Telcon.On Exposure to Heat Flux at Surface of Barrier,Listed Mechanisms Activated.Fire Testing Demonstrates That Panels Qualified W/Variation in Thickness ML20055G4631990-07-13013 July 1990 Responds to NRC Re Violations Noted in Insp Repts 50-456/90-08 & 50-457/90-08.Corrective Actions:Discrepancy Record for Cable Generated & Cable That Had Been Previously Approved for Use on Solenoid Obtained & Installed ML20044A9621990-07-13013 July 1990 Forwards Rev 0 to Topical Rept NFSR-0081, Comm Ed Topical Rept on Benchmark of PWR Nuclear Design Methods Using PHOENIX-P & Advanced Nodal Code (Anc) Computer Codes, in Support of Implementation of PHOENIX-P & Anc ML20044B1411990-07-12012 July 1990 Forwards Addl B&W Rept 77-1159832-00 to Facilitate Completion of Reviews & Closeout of Pressurized Thermal Shock Issue,Per NRC Request ML20044B2081990-07-11011 July 1990 Responds to Generic Ltr 90-04 Re Status of GSI Resolved W/ Imposition of Requirements or Corrective Actions.Status of GSI Implementation Encl ML20044B2141990-07-11011 July 1990 Withdraws 891003 Amend Request to Allow Sufficient Time to Reevaluate Technical Position & Develop Addl Technical Justification ML20044A9521990-07-10010 July 1990 Provides Supplemental Response to NRC Bulletin 88-001. Remaining 48 Breakers Inspected During Facility Spring Refueling Outage ML20044B2871990-07-0909 July 1990 Forwards Brief Description of Calculations Performed in Accordance W/Facility Procedure Used to Make Rod Worth Measurements,Per NUREG-1002 & Util 900629 Original Submittal ML20055D4811990-06-29029 June 1990 Discusses Revised Schedule for Implementation of Generic Ltr 89-04 Re Frequently Identified Weaknesses of Inservice Testing Programs.All Procedure Revs Have Either Been Approved or Drafted & in Onsite Review & Approval Process ML20044A7991990-06-29029 June 1990 Forwards Description of Change Re Design of Containment Hydrogen Monitoring Sys,Per 900517 Request.Util Proposing Alternative Design Ensuring Containment & Hydrogen Monitoring Sys Operability in Event of Power Loss ML20044A7001990-06-26026 June 1990 Responds to Generic Ltr 90-04, Request for Info on Status of Licensee Implementation of Generic Safety Issues Resolved W/Imposition of Requirements or Corrective Actions. Util Will Implement for Unit 2 Activities Performed for Unit 1 ML20058K3521990-06-22022 June 1990 Requests Withdrawal of 900315 Application for Amends to Licenses NPF-37,NPF-66,NPF-72 & NPF-77,changing Tech Specs 3.8.1.1 & 4.8.1.1.2 to Clarify How Gradual Loading of Diesel Generator Applied to Minimize Mechanical Stress on Diesel ML20055D2951990-06-22022 June 1990 Discusses Results of 900529-0607 Requalification Exam.Based on Results of Exam,Station Removed/Prohibited Both Shift & Staff Teams & JPM Failure from License Duties.Shift Team Placed in Remediation Program from 900611-14 ML20044A1411990-06-20020 June 1990 Forwards Endorsements 4 & 5 to Nelia Certificate N-90, Endorsements 5 & 6 to Maelu Certificate M-90 & Endorsements 34,35,36,37,38 & 39 to Nelia Policy NF-274 ML20043H7031990-06-18018 June 1990 Discusses Mod/Rework to Auxiliary Feedwater Sys Check Valves Mfg by Bw/Ip Intl,Inc.All But One Affected Check Valve modified.Motor-driven Auxiliary Feedwater Pump Discharge Valve Check Valve Body Replaced 1990-09-04 |
Text
[ N Commonwealth Edison
[ ) One First Nation 11 Praza. Chicago, lihnois
( E 7 Address Reply to: Post Othee Box 767
( / Chicago, Illinois 60690 September 7, 1984 Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, DC 20555 Sub ject: Byron Station Units 1 and 2 Braidwood Station Units 1 and 2 Pipe Whip Restraints Utilizing Crushable Energy Absorbing Material NRC Docket Nos. 50-454/455 and 50-456/457
Dear Mr. Denton:
. . On August 29, 1984, a meeting was held in the NRC Region III offices between Region III, NRR, and Commonwealth Edison and our consultant (Sargent & Lundy) personnel to discuss the remaining NRC concerns with the use of energy absorbing material (EAM) in certain of' the pipe whip restraints utilized at our Byron and Braidwood Stations. At this meeting, the NRC staf f requested that we provide, by September 7, 1984, simplified drawings of each originally
-designed pipe whip restraint installation utilizing crushable EAM.
These sketches were to show the pipe whip restraint number, the direction of force enacted on the EAM, the tension rod orientation, the magnitude of the dynamic force (R) on the EAM, the kinetic energy absorbed (E) by the EAM, and the dimensions of the EAM.
The purpose of this letter is to formally transmit a full set of such simplified sketches for the seventy-nine Sargent'and Lundy designed pipe whip restraints, and the twenty-three Westinghouse designed pipe whip restraints utilized at our Byron and Braidwood Stations. We expect to submit information to formally
. address the remaining open items identified and discussed during the meeting by September 14, 1984.
One signed original and fifteen copies of this letter are enclosed for your use. Due to the volume of the attachment, this information package is being sent directly to Ms. Janice A.
Stevens. Additionally, this information package is being sent
~directly.to Region III.
Very truly yours E. uglas Sw Nuclear Licensing Administrator EDS/ rap cc: J. A. Stevens - LB1 J. Streeter - RIII 9161N 849gl28 0