.b Washington Public Power Supply System P.O. Box 968 3000GeorgeWashingtonWay Richland, Washington 99352 (509)372-5000 Mr. B. H.- Faulkenberry Deputy Regional Administrator U. S. Nuclear Regulatory Commission Region V 1450 Maria Lane Suite 210 Walnut Creek, CA 94596
SUBJECT:
PROPOSED AGENDA FOR REGION V NRC/ SUPPLY SYSTEM MEETING Enclosed is the proposed agenda as discussed with you on August 31, 1984, for Region V/ Supply System meeting at 9:00 a.m.
on September 24, 1984.
Please note that the "A" part of the agenda is the same as the one for the meeting in NRC Headquarters on September 25, 1984.
R. B. Glasscock, Director Licensing and Assurance kef
Enclosure:
Proposed Agenda
. E'.On
%h9hoh O
h I
II A
Jc-Z8 oo
P f
NRC REGION V/ SUPPLY SYSTEM MEETING SEPTEMBER 24, 1984 PURPOSE A.
Status and Project Completion Plans for WNP-1
.d WNP-3 1.
Review the proposed Supply System role for project completion particularly discuss project management structure concepts that would be consistent with the Supply System role.
2.-
Sumarize ongoing programs and activities.
.3.
Discuss concepts for acceptance of work, particularly _ concurrent inspection and acceptance of work by NRC.
4.
Obtain NRC feedback on ongoing activities and project completion concepts.
B.
Review WNP-2 activities.
AGENDA
-A.
WNP-1 and WNP-3'
-1.
Introduction?
a.
Purpose b.
Background
2.
Current Programs and Activities a.
Preservation Programs b.
Engineering c.
Startup (WNP-3 only) d.
Preparation for Operations (WNP-3 only) e.
Construction f.
Records g.
Interface with other organizations 3.
Supply System Project Completion Role and Project Management Plans for Completion 4.
Concepts for Plant Acceptance 5.
Likelihood of Project completion (how the projects will be financed) 6.
Summary and Conclusions B.
WNP-2 1.
Review of WNP-2 activities.
,