- Georgia Power Company Route 2. Box 299A Waynesboro. Georgta 30830
. Telephone 404 554-9961. Ext. 3360 404 724 8114. Ext. 3360 D. O. Foster Georgia Power V e Pres dent and Protect tr soottu.vn e!ccroc system e
Vogtle Project June 1, 1984 Chief, Management Information Branch Office of Management and Program Analysis U. S. Nuclear Regulatory Commission File: X7BG48 Washington, D. C.
20555 Log:
GN-365
Reference:
50-424/50-425 Gentlemen:
Attached is the current status of. Plant Vogtle, Units 1 and 2,
~through March 25, 1984, to be used for updating the NRC Construction StatusReport(YellowBook). This report ~ reflects present construction plans and approved trends. The method for reporting percent complete for the various commodities has been changed from an earned manhour basis to an installed quantity basis. The overall percent complete is still based upon earned manhours against the Definitive Estimate total manhours with approved trends.
Should you have any questions pertaining to this report, please contact my office at (404) 724-8114.
' Very truly /your,
/
D.d.Foste REF/D0F/tdm s
Attachment xc: -James P. O'Reilly R. E. Conway-W. T.~Nickerson G. Bockhold, Jr.
O. Batum
.R. A. Thomas L. T. Gucwa
'H. H.' Gregory, III
.F. P. Castrichini c
B409060298 840601 PDR ADOCK 05000424 A
PDR g
-w
-,iw.
y.
m
-y
C0NSTRUCT_I0N STATUS REP 0RT PAGE NO:
2-139 UNIT 1 NUCLEAR P0WER-PLANTS STATUS AS OF: 03-25-84 CONSTRUCTION S T A T U.S:
APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:
09-01-86 APPLICANT'S CONSTRUCTION COW LETION APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:
11-00-84 ESTIMATE AS DEFINED IN CP:
APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:
.10-01-79 (EARLIEST) 03-01-86 APPLICANT'S CURRENT ESTIMATED CO MERCIAL OPERATION DATE: 03-01-87 (LATEST) 03-01-88 i
CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE:
64.5%
DATE CONSTRUCTION STARTED:
08-01-76 l
i CURRENT ESTIMATED CONSTRUCTION DURATION IN MONTHS: 126 COMENTS REGARDING CURRENT CONSTRUCTION STATUS:
i ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED-t START START COMPLETION COMPLETION
% C0W LETE MOBILIZE AND PREPARE SITE:
08-01-76 09-15-77 100.0 PLACE STRUCTURAL CONCRETE: (Reforecast Finish For Radwaste 08-01-78 01-01-85E 86.2 Solidification Building)
INSTALL REACTOR PRESSURE VESSEL:
02-21-83 03-16-83 100.0 j
l INSTALLED LARGE 80RE PROCESS PIPE:
09-01-80 05-01-86 77.0 INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SNUBBERS:
09-01-80 05-01-86 21.0 INSTALL SMALL BORE PIPE: w/o Hargers
- Includes New Trend 07-01-81 05-01-86 45.9 INSTALL CABLE TRAY:
09-22-80 04-01-85 81.4 INSTALL EXPOSED METAL CONDUIT:
11-01-81 12-01-85 60.8-INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:
01-15-83 01-01-P6 16.4 INSTALL ELECTRICAL TERMINATIONS:
09-30-83 02-01-86 0.0' CONDUCT REACTOR COLD HYDR 0 STATIC TEST:
03-01-86 04-01 0.0 CONDUCT HOT FUNCTIONAL TEST:
05-15-86 07-15-86
-0.0 CONDUCT PRE 0P AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:
07-24-84 08-01-86 0.0
C0NSTRUCTION STATUS REP 0RT PAGE N0:
2-i40 UNIT 1 NUCLEAR P0WER PLANTS STATUS AS OF: 03-25-84 PLANT C H A R A C T E R I S T I C S:
KEY P E R S O N N E L:
DOCKET N0:
05000424 CORPORATE CONTACT:
D. O. FOSTER, VICE PRESIDENT CP NO. & DATE ISSUED:
CPR-108/06-28-74 AND PROJECT GENERAL MANAGER CP EXPIRATION DATE:
03-01-88 CORPORATE ADDRESS:
GEORGIA POWER COMPANY; RT.2 BOX APPLICANT:
GEORGIA POWER COMPANY 299A, WAYNESB0RO, GA 30830 PLANT LOCATION:
BURKE COUNTY / GEORGIA CORPORATE PHONE N0:
(404) 724-8114. EXT. 3360 11 REGION:
11 NRC LPM:
M. NILLER AE:
SOUTHERN SERVICES /BECHTEL IE PRINCIPAL INSPECTOR:
V. PANCIERA NSSS:
-CONSTRUCTION:
CONSTRUCTOR:
GPC
-TEST AND STARTUP:
REACTOR TYPE:
W. F. SANDERS DER (MWE):
1167 INSPECTION S T A T U S:
FUEL LOAD DATE CHANGES TIME PERIOD AS REP 0RTED BY U T I L I T Y:
REPORT BEG DATE END DATE REPORT NEW REASON FOR CHANGE NUMBER OF INSP.
OF INSP. -
DATE SCHEDULE REPORTED BY UTILITY 09-27-74 Not Known Construction Suspended For Financial Reasons 05-11-77 05-00-83 No Reason Given 01-09-78 05-01-84 Overestimated Projected Need For Power 07-17-80 11-00-84 No Reason Given 11-18-81 09-01-86 Schedule Reassessment L0 CAL POBLIC D0CUMENT R 0 0 M:
BURKE COUNTY LIBRARY 4TH STREET WAYNESBORD, GEORGIA 30830
C0NSTRUCTI0N STATUS R E P 0 R.T PAGE N0:
2-141 UNIT 2 NUCLEAR P0WER PLANTS STATUS AS OF: 03-25 (.'
CONSTRUCTION S T A T U S:
APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:
03-01-88 APPLICANT'S CONSTRUCTION COMPLETION 1
APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:
05-00-87 ESTIMATE AS DEFINED IN CP:
APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:
10-01-80 (EARLIEST) 09-19-87 APPLICANT'S CURRENT ESTIMATED COMERCIAL OPERATION DATE: 09-01-88 (LATEST) 09-19-89 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE:
21.9%
DATE CONSTRUCTION STARTED:
08-01-76 CURRENT ESTIMATED CONSTRUCTION DURATION IN MONTHS: 147 j
COMENTS REGARDING CURRENT CONSTRUCTION STATUS:
ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED 2
START START COMPLETION COMPLETION
% COMPLETE MOBILIZE AND PREPARE SITE:
08T01-76 09-15-77 100.0 PLACE STRUCTURAL CONCRETE:
08-01-78 06-01-86 62.3 INSTALL REACTOR PRESSURE VESSEL:
08-01-84 09-15-84 0.0 INSTALLED LARGE BORE PROCESS PIPE:
09-01-80 11-01-87 23.9 INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SNUBBERS:
09-01-80 11-01-87 1.2 INSTALL SMALL BORE PIPE: w/o Hangers "(Includes New Trend) 02-06-83 12-01-87 5.8 INSTALL CABLE TRAY:
09-22-80 10-01-86 15.7 l
INSTALL EXPOSED METAL CONDUIT:
04-08-83 04-01-87 12.8 INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:
09-01-84 05-01-87 0.0 INSTALL ELECTRICAL TERMINATIONS:
11-01-84 07-01-87 0.0 '
CONDUCT REACTOR COLD HYDROSTATIC TEST:
09-01-87 10-01-87 0.0 i
CONDUCT HOT FUNCTIONAL TEST:
12-15-87 02-15-88 0.0 CONDUCT PRE 0P AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:
01-24-86 02-01-88 0.0
!l'
C0NSTRUCTION STATUS REP 0RT PAGE N0:
2-142 UNIT 2 NUCLEAR P0WER PLANTS STATUS AS OF: 03-25-84 PLANT' C H A R A C T E R I S T I C.S:
KEY P E R S O N N E L:
DOCKET NO:
05000424 CORPORATE CONTACT:
.D. O. FOSTER, VICE PRESIDENT CP NO. & DATE ISSUED: CPR-108/06-28-74 AND PROJECT GENERAL MANAGER CP EXPIRATION DATE:
03-01-88 CORPORATE ADDRESS:
GEORGIA POWER COWANY; RT. 2 BOX APPLICANT:
GEORGIA POWER COMPANY 299A, WAYNESBOR0, GA 30830 PLANT LOCATION:
BURKE COUNTY / GEORGIA CORPORATE PHONE N0:
(404) 724-8114. EXT. 3360 II REGION:
II NRC LPM:
H. NILLER AE:
SOUTHERN SERVICES /BECHTEL IE PRINCIPAL INSPECTOR: V. PANCIERA NSSS:
-CONSTRUCTION:
CONSTRUCTOR:
GPC
-TEST AND STARTUF:
REACTOR TYPE:
W. F. SANDERS l
DER (ME):
- 1167, INSPECTION S T A T U S:
FUEL LOAD DATE CHANGES TIME PERIOD AS REP 0RTED BY U T I L I T Y:
REPORT BEG DATE END DATE REPORT NEW REASON FOR CHANGE
{
NUMBER OF INSP.
OF INSP.
DATE SCHEDULE REPORTED BY' UTILITY 09-27-84 Not Known Construction Suspended For Financial Reasons 05-11-74 05-00-84 No Reason Given 11-02-77 05-00-85 Overestimated Projected Need For Power 07-17-80 05-00-87 No Reason Provided 1
11-18-81 03-01-88 Schedule Reassessment L0 CAL PUBLIC D0CUMENT R 0 0 M:
BURKE COUNTY LIBRARY 4TH STREET WAYNESBOR0, GEORGIA 30830
C0NSTRUCTI0N STATUS REP 0RT PAGE N0:
2-i40 UNIT 1 NUCLEAR P0WER PLANTS STATUS AS OF: 03-25-84 PLANT C H A R A C T E R I S T I C S:
KEY P E R S O N N E L:
DOCKET N0:
05000424 CORPORA,TE CONTACT:
D. O. F0 STER, VICE PRESIDENT '
CP M9. & DATE ISSUED:
CPR-108/06-28-74 AND PROJECT GENERAL MANAGER CP EXPIRATION DATE:
03-01-88 CORPORATE ADDRESS:
GEORGIA POWER COMPANY; RT.2 80X APPLICANT:
GEORGIA POWER COMPANY 299A, WAYNESBOR0, GA 30830 PLANT LOCATION:
BURKE COUNTY / GEORGIA CORPORATE PHONE N0:
(404) 724-8114. EXT 3360 II REGION:
II NRC LPM:
- 11. MILLER AE:
SOUTHERN SERVICES /BECHTEL IE PRINCIPAL INSPECTOR:
V. PANCIERA NSSS:
-CONSTRUCTION:
CONSTRUCTOR:
GPC
-TEST AND STARTUP:
REACTOR TYPE:
W. F. SANDERS DER (MWE):
1167 INSPECTION S T A T U S:
FUEL L0AD DATE CHANGES TIME PERIOD AS REP 0RTED BY U T I L I T Y:
REPORT BEG DATE END DATE REPORT NEW REASON FOR CHANGE NUMBER OF INSP.
OF INSP.
DATE SCHEDULE REPORTED BY UTILITY 09-27-74 Not Known Construction Suspended For Financial Reasons 05-11-77 05-00-83 No Reason Given 01-09-78 05-01-84 Overestimated Projected Need For Power 07-17-80 11-00-84 No Reason Given 11-18-81 09-01-86 Schedule Reassessment L0 CAL PUBLIC D0CUMENT R 0 0 M:
BURKE COUNTY LIBRARY 4TH STREET UAYNESBOR0, GEORGIA 30830
C0NSTRUC'TI0N STATUS R E-P 0 R T PAGE N0:
2-142 UNIT 2 NUCLEAR
-P0WER PLANTS STATUS AS OF: 03-25-84 PLANT C H A R A C T E R I S T I C S:
KEY P E R S O N N E L:
DOCKET N0:
05000424 CORPORATE CONTACT:
D. O. FOSTER, VICE PRESIDENT CP N0. & DATE ISSUED: CPP-108/06-28-74 AND PROJECT GENERAL MANAGER CP EXPIRATION DATE:
03-01-83 CORPORATE ADDRESS:
GEORGIA POWER COMPANY; RT. 2 BOX APPLICANT:
GEORGIA POWER COMPANY 299A, WAYNESBOR0, GA 30830 PLANT LOCATION:
BURKE COUNTY / GEORGIA CORPORATE PHONE N0:
(404) 724-8114. EXT. 3360 II REGION:
II NRC LPM:
M. MILLER AE:
SOUTHERN SERVICES /BECHTEL IE PRINCIPAL INSPECTOR: V. PANCIERA NSSS:
-CONSTRUCTION:
CONSTRUCTOR:
GPC
-TEST AND STARTUP:
REACTOR TYPE:
W. F. SANDERS DER (MWE):
1167 INSPECTION S T A T U S:
FUEL LOAD DATE CHANGES TIME PERIOD AS REP 0RTED 8Y U T I L I T Y:
REPORT BEG DATE END DATE REPORT NEW REASON FOR CHANGE NUMBER OF INSP.
OF INSP.
DATE SCHEDULE REPORTED BY UTILITY 09-27-84 Not Known Construction Suspended For Financial Reasons 05-11-74 05-00-84 No Reason Given 11-02-77 05-00-85 Overestimated Projected Need For Power 07-17-80 05-00-87 No Reason Provided 11-18-81 03-01-88 Schedule Reassessment L0 CAL PUBLIC D0CUMENT R 0 0 M: