Submits Rept 92-002 Re 920422 Steam Generator Tube Plugging & Repair Work.Complete Results of SG Tube ISI Will Be Reported,Per TS 4.4.6.5.b
ML20096B760
Person / Time
Site: Farley 
Issue date: 05/06/1992
From: Woodard J
SOUTHERN NUCLEAR OPERATING CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9205120261
Download: ML20096B760 (2)


Text

then Nxiev Opewg Comrany IO!:1 OthC$ DOW 1hl!s Omungham, AW>ama 31P01 Telet#one ?05 b68 !>080 n

J. D. Woodard h

h

.V vee Precaent May 6, 1992 t'+" M c'" o n t" W *'"

ra w ircyct Docket No. 50-364 U. S. Nuclear Regulatory Conunission ATIN: Document Control Desk Washington, DC 20555 Joseph M. farley Nuclear Plant - Unit 2 SEccial Report No.92-002. Steam Generator Tqbe Pluanino Gentlemen:

Joseph M. f arley Nuclear Plant, Unit 2, Special Report No.92-002 is being submitted in accordance with Technical Specification 4.4.6.5.a.

If you have any questions, please advise.

Respectfully submitted, (4)ha tn Woodard JDW/ REM: map 2360 Enclosure cc:

'Mr. S. D. Ebneter Mr. S. i. Hoffman Mr. G. F. Maxweli 9205120261 920506 p t/.7 gDR ADOCK 0500 4

'//

f Special Repoi 92-002, Unit 2 Steam Generator Tube Plugging The following steam generator tube plugging report is being submitted in accordanco with Technical Specification 4.4.6.5.a.

The eddy current testing results of the Unit 2 eighth refueling outage are as follows.

SLQ h SIG B SJk_C Plugged Tubes 11 21 10 Repaired Tubes 18 0

11 F* Tubes 16 36 165

-The plugging and repair work was completed on April 22, 1992.

The complete results of the steam generator tube inservice inspection will be reported in accordance with Technical Specification 4.4.6.5.b.