U 0728 L20-84 ( 08-22)-L 0982-L

/LLINDIS POWER 00MPANY CLINTON POWER STATION. P.o. BOX 678. CLINTON, ILLINOIS 61727 August 22, 1984 Docket No. 50-461 Dr. Harold R. Denton, Director l Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Washington, D.C. 20555

Subject:

Clinton Power Station Unit 1 Extension of Construction Permit No. CPPR-137

Dear Dr. Denton:

In letters U-0286, dated August 31, 1981, and U-0467, dated April 23, 1982, Illinois Power Company (IP) requested that the latest date for completion of construction of Clinton Power Station (CPS), as specified in Construction Permit No. CPPR-137, be extended from October 1, 1981 to October 1, 1984. The Nuclear Regulatory Commission (NRC) granted this request on June 7, 1982. (See 47 Fed. Reg. 28185, June 29, 1982.) IP, on behalf of itself and as agent for Soyland Power Cooperative, Inc.,

and Western Illinois Power Cooperative, Inc., hereby requests that the latest date for completion of construction of CPS be further extended to October 1, 1986.

10 CFR 50.55(a) of the Commission's regulations states that each constructor shall state the earliest and latest date for completion of construction. As we informed you in letter 0982-L dated May 24, 1983, IP has revised its fuel load date from January 1984 to January 1986.

Nevertheless, to allow for unexpected centingencies, IP is requesting that the latest completion date be extended to October 1, 1986 pursuant to 10 CFR 50.55(b).

The following factors constitute the basis for extension of the latest completion date:

1. In 1982, IP initiated a series of stop work orders and
recovery programs to implement corrective action and improve construction programs for several areas of construction.
2. In 1982, IP also initiated an Overinspection Program and Record Verification Program to verify the quality of construction of large portions of CPS.

The time required to lift the stop work orders and complete the recovery programs, Overinspection Program, and the Record Verification Program was not accounted for in IP's previous request for an extension of the 8408280094 840822 PDR ADOCK 05000461 A PDR 3/. [

g i F-#tro'"

Fl

.- .- U-0728 L20-84(08-22)-L construction permit for CPS to October 1, 1984. Since the purpose of

-these programs is to ensure the protection of the public health and safety, these programs constitute good cause for the extension of the

' latest completion date to October 1, 1986.

As required by 10'CFR 170.21, our check for $150 is enclosed to cover the filing fee for this application for amendment to the construction permit for CPS.

Finally, IP notes that the NRC has not acted on proposed amendments to Section 3E of Construction Permit No. CPPR-137 which were requested in the aforementioned letter U-0286, as modified by letter U-0445, dated March 29, 1982, from IP to_the NRC. Your prompt consideration of this request would be appreciated.

rel yours, D. P. Hall Vice President SPF/lm Attachment - Notarization cc:. See Attached Distribution List

~

w

- =

U-0728 L20-84(08-22)-L STATE OF ILLINOIS COUNTY OF De Witt DONALD P. HALL, Being first duly sworn, deposes and says:

-That he is Vice President of Illinois Power Company; that the foregoing request for an extension of the latest completion date has been prepared under his supervision and direction; that he knows the contents thereof; and that to the best of his knowledge and belief said request and the facts contained therein are true and correct.

DATED: This M adday of August, 1984.

Signed: -

Donald P. Hall Subscribed and sworn to before me this oPJ M day of August, 1984.

I bboltL $ HSAsv

(

Notary Public f My connaission expires:

f)Mau 1,19S4 i

l t-

- .w,

.. . - *- U-0728 L20-84(08-22)-L 0982-L Distribution List-Dr. Harold R. Denton, Director A. Samelson, Esq.

Office of Nuclear Reactor Regulation- Assistant Attorney General U. S. Nuclear Regulatory Commission Environmental' Control Division Washington, D.C. 20555- Southern Region 500 South Second Street cc: .J. G. Keppler Springfield Illinois 61706 Regional Administrator Region III J. Foy U. S. Nuclear Regulatory Commission Spokesperson, Prairie Alliance 799 Roosevelt Road 511 W. Nevada Glen Ellyn, Illinois 60137 Urbana, Illinois 61801 B.lL. Siegel H. K. Clark, Esq.

Clinton' Licensing Project Manager Chairman, Atomic Safety and Mail Code 416 Licensing Board U. S. Nuclear Regulatory Commission .P. O. Box 127A Washington,'D.C. 20555 Kennedyville, Maryland 21645 F. Christianson Dr. O. H. Paris Mail Code _V-690 Atomic Safety and Licensing Board NRC Resident Office U. S. Nuclear Regulatory Commission Clinton Power Station Washington, D.C. 20555 R. R. #3, Box 228 Clinton,. Illinois 61727 Dr. G. A. Ferguson Atomic Safety and Licensing Board Dr. D. Etchison School of Engineering Director, Illinois Department Howard University of Nuclear Safety 2300 Sixth Street, N.W.

-1035 Outer Park Drive Washington, D.C. 20059 Springfield, Illinois 62704

__R. J. Goddard, Esq.

Office of the Legal Director U. S. Nuclear Regulatory Commission Washington, D.C. 20535