ML20095E274

From kanterella
Jump to navigation Jump to search
Responds to NRC Re Violations Noted in Insp Repts 50-456/92-05 & 50-457/92-05.Corrective Actions:Review of All MOVs Incorporated in Generic Ltr 89-10 Program Identified 36 MOVs Requiring Increased Stem Lubrication Frequencies
ML20095E274
Person / Time
Site: Braidwood  Constellation icon.png
Issue date: 04/23/1992
From: Kovach T
COMMONWEALTH EDISON CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
GL-89-10, NUDOCS 9204270372
Download: ML20095E274 (4)


Text

-_-_-__-__

[l Z /

Commonwealth Edison 1400 Opus Place J Downers Grove, lillnois 60516 April 23,1992 U.S. Nuclear Regulatory Commission Washington, DC 20555 Attn: Document Control Desk

Subject:

Braidwood Nuclear Power Station Units 1 and 2 Response to Notice of Violation inspection Report Nos. 50-456/92005; 50-457/92005 NB C_Do_che1B umbets_50-45fmd_50-452

Reference:

M. Ring letter to C. Reed dated March 24,1992 transmitting NRC Inspection Report 50-456/92005;50-457/92005 Enclosed is the Commonwealth Edison Company (CECO) response to the Notice of Violation (NOV) which was transmitted with the reference letter and Inspection Report The NOV cited one Severity Level IV violation requiring a written response. The violation concerns aspects of the the Motor Operated Valve Program, if your staff has any questions or comments conceming this letter, please refer them to Denise Saccomando, Compliance Engineer at (708) 515 7285.

Sincerely, k $.

6<

T.J. Kovach Nuclear Licensing Manager e

Attachment cc:

A. Eert Davis, NRC Regional Administrator - Rill R. Pulsifer, Project Manager - NRR S. Dupont, Senior Resident laspector i

9204270372 920423 1

PDR ADOCK 05000456

[

t

{

i G

PDR l

t ATTACHMENT A RESPONSE TO NOTICE OFNIOLATION INSPECTION REPORT 456/92005; 457/92005 VIOLATION (450/92005:02A; 450/92005-02B):

10 CFR 50, Appendix B, Criterion V, requires that activities affecting quality be accomplished by documented instructions, procedures, or drawings appropnate to the circumstances.

Commonwealth Edison Whitt Paper MOV-WP101," Justification of Using Coefficient of Friction of u = 0.15 for the Torque to Thrust Conversion of Motor Operated Valves (MOV) with Rising Stems," p;ovided the technical bases for use of stem factors as low as 0.15 and specified a cleaning and lubrication frequency of 18 months.

Commonwealth Edison's MOV lubr:t ation program (LUBO) specified the use of EP-1 lubricant for most valve stems, including MOV's 2 SIB 807A,2Sl8807B and 1CC9473.

Contrary to the above:

A.

As of February 18,1992, stem factors of 0.15 and lower were being used to calculate so.ne torque switch settings without following the lubrication requirements specified by engineering in Commonwealth Edison White Paper MOV-WP101.

B.

As of February 18,1992, procedure BwFP FS-1," Inspection of Limitorque Gear Case Lubrication," Revision 0, Temporary Change 5624, conflicted with the station lubrication program (LUBQ) in that it specified and resulted in the use of Neolube on valves 2Sl8807A, 2Sl88078, and 1CC9473.

1 ZNLD/1754

RESPONSE TO NOTICE.OFNIOLATION l

INSPECTION REPORT 456/92005; 457/92005 REASON FOR THE VIOLATION:(EXAMPLE A)

Commonwealth Edison agrees that Braidwood Station did not follow the lubrication requirements specified by the Nuclear Engineering Department (NED)

Mechanical and Structural Design group in Commonwealth Edison White Paper MOV-WP101. The White Paper did recommend increased lubrication frequency for those valves where the thrust window was calculated using a less conservative coefficient of friction. The station's interpretation cf the White Paper was that a 36 month lubrication frequency was applicable unless an accelerated frequency was explicitly stated on the MOV data sheet. It was NED's intent that if the ta get thrust window was given on the left (lower friction f actor) side of the data sheet, an accelerated lubrication frequency was required. This resulted in valves whose data sheets were based on less conservative coefficients of friction not being identified for stem lubrication on an increased frequency.

CORRECTIVE STEPS TAKEN AND RESULTS ACHIEVED:(EXAMPLE A)

Braidwood station reviewed all MOVs that were incorporated in the Generic Letter 89-10 program. The review identified 36 MOV's which required increased stem lubrication frequencies of 18 months. Of these,29 MOV's are within the 18 month lubrication frequency. The iemaining 7 MOV's (1/2CV8355A,1CV8355B, 1/2CV8355C,1/2CV8355D) fall outside the 18 month frequency. These valves can only bc subricated when the respective unit is shutdown. They are being evaluated by the NED Pressurized Water Reactor (PWR) Systems group to determine their acceptability with decreased lubrication frequencies. The evaluation of the 7 MOV's is scheduled to be completed by May 15,1992. Appropriate actions will be taken based on the evaluation results.

CORRECTIVE STEPSTAKEN TO AVOID FURTHER VIOLATION:(EXAMPLE A)

A letter was issued by the NED Mechanical and Structural Design group to the station clarifying the information given on the data sheets for the use of less conservative stem f actors combined with increased stem lubrication frequency requirements.

The lubrication frequencies for the 36 MOV's identified have been revised in the Station Lubrication System program (LUBO) to agree with the 18 month frequency requirement.

NED Mechanical and Structural Design group will revine White Paper MOV WP101 to clarify the requirement of increased lubrication frequencies. This revision is expected to be completed by September 30,1992.

DATE WHEN RJLLCOMPLIANCE WILL BE ACHIEVED:(EXAMPLE A)

Full compliance will be achieved with the dispositioning of the 7 MOV's being evaluated by the NED PWR Systems group scheduled for May 15,1992.

2 ZNLD/1754

RESPONSEJO NOTICE OF VIOLATION INSPECTION REPORT 456/92005; 457/92005 REASON FOR THE VIOLATION: (EXAMPLE B)

Commonwealth Edison agrees that procedure BwFP FS-1, Temporary Procedure Change 5624 (dated 11/21/90) stated that valve stems should be cleaned and lubricated with Neolube. This conflicted with the Station Lubrication System Program (LUBQ) which stated that various valves, including 2Sl8807A,2Sl8807B and 1CL9473, are to be lubricated with Exxon EP-1. Although Neolube is an approved valve stem lubricant, in 1988, the station decided to change the type of lubricant used on valve stems from Neolube to Exxon EP-1, wNch is used in each valve's main gear case. Procedure BwFP FS-1 was inadvertently not updated following the 1988 change to LUBO.

COBRECTIVEETEPS TAKEllAND_RESULTS_ ACHIEVED: (EXAMPLE B)

On February 25,1992, Temporary Procedure Change 6153 was put in place to address referencing the LUBQ data base for the correct stem lubricant to be used when performing valve stem Iubrication. On March 12,1992, BwFP FS-1, Revision 1 was authorized for use. This revision incorporated Temporary Procedure Chcnge 6153 as well as other changes to enhance the procedure.

CORRECTIVE. STEPS _TAKEN10 AVOID _EURTHER_ VIOLATION:(EXAMPLE B)

The LUBQ data base was reviewed and revised as necessary to ensure that it specified using the correct stem lubricant for each motor operated valve.

A review of Fuel Handling lubrication procedures identified that BwFP FS-1 was the only procedure which addressed the type of lubricant to be used on valve stams. No other procedures required revision.

DATEWHENEULL COMPLIANCEWillBE ACHIEVED.(EXAMPLE D)

Full compliance was achieved wits. the Revisicn of Procedure BwFP FS-1, Revision 1 dated March 12,1992.

3 ZNLD/1754