N Commonwealth Edison. _
j f -One First NationIl Pins, ChicTgo, lilinois 0,
T
~'? Address Reply to: Post Office Box 767
.\\
/ Chicago, Illinois 60690 -
August'15, 1984 Mr. Harold R. Denton, Director
-Offic'e of Nuclear Reactor Regulation U.S.: Nuclear Regulatory Commission Washington, DC 20555'
Subject:
- _ Byron Station Units 1 and 2 Technical. Specifications NRC Docket-Nos. 50-454/455-Reference (a): _' December 16, 1983 memorandum from Cecil 0.' Thomas
Dear Mr. Denton:
This is to provide _ additional comments.regarding the proof and. review version of the Byron Unit 1 Technical Specifications that were distributed-by Reference-(a).
References to-the three loop operation.during Modes 1, 2, 3 and 4 should be removed from the Technical Specifications.
Because we_do not have supporting Westinghouse analyses to do so, three loop operation will not be used during these modes of operation.
Additionally, our operating' personnel-have not been trained to operate in these modes.
Very truly ours A
/,.
e-E.
ouglas Swar z Nuclear Licensing Administrator cc:
RIII Inspector - Byron L.
N. 01shan - LB 1 9081N 8408220368 840815 PDR ADOCK 05000454 A
PDR g
Y,o