MISS:5SIPPI POWER & LIGHT COMPANY Helping Build Mississippi N
P. O. B OX 1640, J ACK S O N, MIS SIS SIP PI 3 9 205 August 14, 1984 NUCLEAR LICENSING & $AFETY DEPARTMENT U. S. Nuclear Regulatory Commission Office of Nuclear Reactor Regulation Washington, D. C.
20555 Attention: Mr. Harold R. Denton, Director
Dear Mr. Denton:
SUBJECT:
Grand Gulf Nuclear Station Unit 1 Docket 50-416 License No. NPF-13 File: 0260/15320 Compensating Actions for NUREG-0654, Appendix 2, Requirements AECM-84/0354 Mississippi Power & Light (MP&L), in AECM-81/0327 (copy attached) outlined on April 10, 1981 several compensating actions which would'be provided until the backup meteorological tower at Grand Gulf Nuclear Station (GGNS) was operational. Since that time many changes have taken place in GGNS Technical Specifications and procedures which deal with the meteorological system.
For this reason, we wish to supersede some of those commitments outlined in AECM-81/0327 with the more recent commitments in the GGNS Technical Specifications and Emergency Procedures.
The specific commitments and the proposed replacements are listed below:
AECM-81/0327 Commitment MP&L personnel will check communications with the National Weather Service on a monthly basis to ensure that routine meteorological observations and forecasts are available.
Requested Change MP&L personnel routinely communicate with the National Weather Service concerning weather forecasts. Requiring contact to be made with them on a nonthly basis serves no purpose other than to check the pnene lines which is not an activity related to meteorological monitoring. Therefore, this requirement should be deleted and replaced with the commitment existing in GGNS Emergency Procedures that the
~
National Weather Service will be contacted during emergencies for consultation concerning weather forecasts.
AECM-81/0327 Ccmmitment Quarterly calibration of meterological sensors.
k 04062104s4 g4cg34 Member Middle South Utilities System pDRApoCMc5000416 PDR A
r-AECM-84/0354 MICI:'CIPPI POWER Q Ll2HT COMPANY Page 2 Requested Change The GGNS meteorological system has duplicate sensors at all levels. GGNS Technical Specification 3.3.7.3 and Safety Guide 23 require calibration of these sensors to be performed on a semiannual basis. The requirement for quarterly calibrations identified in AECM-81/0327 is unnecessary and should be eliminated and replaced with a requirement for semiannual calibrations.
If you have any questions concerning these changes, please contact Mr. G. O. Smith, Supervisor, Environmental Services, at (601) 969-2672.
Sincerely, L. F. Dale Director GOS/LRM:ay Attachment cc: Mr. J. B. Richard (w/a)
Mr. R. B. McGehee (w/a)
Mr. N. S. Reynolds (w/a)
Mr. G. B. Taylor (w/a)
Mr. Richard C. DeYoung, Director (w/a)
Office of Inspection & Enforcement U. S. Nuclear Regulatory Comission Washington, D. C.
20555 Mr. J. P. O'Reilly, Regional Administrator (w/a)
U. S. Nuclear Regulatory Commission Region II 101 Marietta Street, N. W.
Suite 2900 Atlanta, Georgia 30323
v-
]
MISSISSIPPI POWER & LIGHT COMPANY Helping Build Mississippi g*
P. O. B O X 164 0. J AC K S O N. MIS SIS SIP PI 3 9 2 0 5 August 28, 1981 NAE AR PRooOCTioN DEPARTMENT l
U.S. Nuclear Regulatory Commission Office of Nuclear Reactor Regulation Washington, D.C.
20555 Attention:
Mr. Harold R. Denton, Director
Dear Mr. Denton:
SUBJECT:
Grand Gulf Nuclear Station Units 1 and 2 Docket Nos. 50-416 and 50-417 File 0260/0272/3700 Compensating Actions for NUREG-0654, Appendix 2, Annex 1 Requirements AECM-81/327 On April 10, 1981, by AECM-81/103, a description of the backup meteorological system and Class A Model for Grand Gulf Nuclear Station were submitted to the Commission.
Since then an informal request for additional information has been received, concerning proposed compensating actions to be taken in the event these two systems are not operational prior to the issuance of an Operating License.
In response to this request, attached is an outline of the compensating actions Mississippi Power & Light Company will take, if necessary, to provide for meteorological monitoring capability as described in NUREG-0654, Appendix 2, Annex 1.
Yours truly, 8
L. F. Dale
,/
Manager of Nuclear Services GOS/LRM/JDR:Im i
Attachment l
cc:
(See Next Page)
AE2U1 Member Middi Scath Utilities System g<f34Cf
,i l'
,r i
r j
AECM-81/327 9' ;. ' '
MISils:IPPI POWER O LIGHT COMPANY Page 2 j'
cc:
Mr. N. L. Stampley (w/1)
Mr. G. B. Taylor (w/1)
Mr. R. B. McGehee (w/1)
Mr. T. B. Conner (w/1)
Mr. Victor Stello, Jr., Director (w/1)
Office of Inspection & Enforcement U.S. Nuclear Regulatory Commission Washington, D.C.
20555 Mr. J. P. O'Reilly, Director (w/3)
Office of Inspection & Enforcement U.S. Nuclear Regulatory Commission Region II' 101 Marietta St., N.W., Suite 3100 Atlanta, Georgia 30303 i
AE2U2
m
,7 Compinactieg Actiens Rrquirsd by NUREG-0654, AppIndix 2,
)
Ann::x 1 for GGNS Mitecrolegical Systems Mississippi Power & Light Company (MP&L) is in th process of
+
developing a Class A Model and a backup meteorological system for Grand Gulf Nuclear Station (GGNS).
If these two systems are not operational prior to receipt of an Operating License, then the following compensating actions, as specified in NUREG-0654, Appendix 2, Annex 1, will be taken:
o MP&L personnel at GGNS will check communications with the Jackson, Mississippi branch of the National Weather Service on a monthly basis to ensure that routine meteorological observations and forecasts are available.
o GGNS primary meteorological systems consist of duplicate sets of wind speed, wind direction, and ambient temperature sensors at two levels on the primary meteorological tower.. These sensors will be calibrated on a quarterly basis. No alternate sources of meteorological data will be necessary during these calibrations, because each sensor will be calibrated individually, thereby enabling the meteorological system to maintain a constant inventory of meteorological information for each parameter monitored at each level.
o In the unlikely event that one or all meteorological parameters from the primary meteorological tower are lost at both measuring levels, the Jackson, Mississippi, branch of the National Weather Service will be utilized to provide backup meteorological information to GGNS.
The primary meteorological system will be inspected on a o
weekly basis to ensure its proper operation.
o Any periods of quarterly data unavailability which exceed the goals outlined in Regulatory Guide 1.23 will be reported to the Commission.
o The Offsite Dose Calculation Manual will contain procedures for calculating the transport and diffusion of gaseous effluents which are consistent with the characteristics outlined in NUREG-0654, Appendix 2.
1 o
If a radiological emergency at GGNS should develop, direct telephone access to the Radiation Protection Manager (Chemistry & Radiation Control Superintendent) or the Radiation Emergency Manager (Corporate Health Physicist) will be provided.
During the early stages of an accident, offsite dose projection is performed by the Chemistry & Radiation Control Superintendent as part of his emergency responsibilities in the Technical Support Center (TSC).
If the accident becomes serious enough to require activation of the Near-Site Emergency Operatings Facility (EOF), offsite dose projection becomes the primary responsibility of the Corporate Health Physicist. The method of establishing this direct telephone access with the Commission will be outlined in GGNS Energency Plan Procedures or MP&L Corporate Emergency Plan Procedures at the next available revisica.
AE2VI
~
,