Requests That Required Date of 920316 for Submittal of PTS, Per 10CFR50.61(b)(4) Be Extended Until 920515,since Calculations of Latest Projected Screening Values Are Still Being Performed
ML20094K888
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 03/17/1992
From: Gates W
OMAHA PUBLIC POWER DISTRICT
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
LIC-92-093R, LIC-92-93R, NUDOCS 9203230258
Download: ML20094K888 (1)


Text

,

u_[ '

m

' i ;.; j.I '..Z-(( [.$

_ _, m

~

n n.n,.

p.m.-_w

/-

Omaha Public Power District March 17, 1992 444 South 16th Street Mall LIC-92-093R Ornaha. Nebraska 68102-2247 402/636-2000 O. S. Nuclear Regulatory Cownission ATTN: Document Control Desk Mail Station Pl-137 Washington, DC 20555

References:

1.

Docket No. 50-285 2.

10 CFR 50.61 Gentlemen:

SUBJECT:

Request for Delayed Submittal of Pressurized Thermal Shock (PTS)

Analysis and Schedule 10 CFR 50.61(b)(4 requires submittal by March 16, 1992 of an analysis and schedule for imple) mentation of such flux reduction programs as are reasonabiy practicable to avoid exceeding the PTS screening criterion set forth in paragraph wh)ich the value of RT(b (2) of this section. This requirement is spplicable to each PWR licensee for ru for any material in the beltline is projected to exceed the PTS screening criterion before the expiration date of the operating license, or the projected expiration date if a change in the license has been requested, or the end of a renewal term if a request for license renewal has been submitted.

Communications between Mr. S. D. Bloom of your staff and lle. T. G. Therkildsen of my stalf have determined that this requirement is now applicable to Ornaba Publle Power District 03PD), due to recent activation nf a dormant re change in the expirat(ion date of the Fort Calhoun Station (FCS) Un1uest for t No. 1 operating license. Sinco calculations of the latest projected screening values for FCS are still being performea, OPPD cannot meet the March 16, 1992 submittal date requirement noted above.

As discussed between Mr. Bloom and Mr.

Therkildsen, OPPD requests that the submittal date for compliance with 10 CFR 50.51(b)(4) be extended until May 15, 1992.

If you should have any questions, please contact me.

Sincerely, 4V. k b'6k:

W. G. Gates Division Manager Duclear Operations h06/sel c:

1.eBoeuf, Lamb, Leiby & MacRae i

D. L. Wigginton, NRC Senior Project Manager S. D. Bloom, NRC Project Engineer R. D. Martin, NRC Realonal 4dministrator, Region IV i

,R., P. Mullikin, NRC Senior Resident Inspector 920323025a 920317 PDR ADOCK 05000285 1

0 Af g

e P

PDR 45':?4 Employan Op;;cnunny