Suppls 840517 Response to Violation & Proposed Imposition of Civil Penalties.Procedure 6.1-024 Revised on 840718 to Provide More Specific Guidance Re Labeling Radioactive Matl Containers
ML20094K446
Person / Time
Site: Pilgrim
Issue date: 08/08/1984
From: Harrington W
BOSTON EDISON CO.
To: Deyoung R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
References
84-120, NUDOCS 8408150055
Download: ML20094K446 (2)


Text

.

BOSTON EntsON COMPANY.

800 BOYLsTON STREET BOSTON, M AssACHusETTs 02199 WILLIAM D. HARRINGTON mwaam vses passiotut MU G LE MB August 8,1984 BEco Ltr. #84-120 Mr. Richard C. DeYoung Director, Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission Washington, D.C.

20555 License No. DPR-35 Docket No. 50-293

Subject:

Amended Response to Notice of Violation "A"

(NRC Inspection No. 50-293/84-03)

References:

BECo Ltr. 84-72, dated May 17, 1984, " Response To Violation and Proposed Imposition of Civil Penalties"

Dear Sir:

Review of the subject Inspection and our subsequent response has led us to i

conclude that additional corrective acilon to preclude recurrence of Violation "A" is appropriate. This letter is therefore submitted as a supplement to the reference and outlines additional corrective action Boston Edison Company has taken to ensure compliance with 10CFR20.203(f).

Although not specifically related to the incident of January 14-18, 1984 involving the unlabeled container of high radiation material, our Health Physics organization has recently reviewed Procedure 6.1-024, " Radiological Posting of Areas of the Station," from the perspective of compliance with 10CFR20.203(f). As a result of this review, the subject procedure was revised on July 18, 1984 to provide more specific guidance to Health Physics personnel regarding labeling of radioactive material containers. This procedural change, having been communicated to Health Physics personnel, will ensure compliance with 10CFR20.203 as they apply to present and future Station activities.

. rely 840815C055 840808 PDR ADOCK 05000293 f)

O PDR

BOSTON EDISON COMPANY Mr. Richard C. DeYoung U.S. Nuclear Regulatory Commission August 8, 1984' Page Two If you have any specific questions regarding the above-stated additional actions or the general issues involved, please do not hesitate to contact me.

Very truly yours, W. D. Harrington Senior Vice President-Nuclear Commonwealth of Massachusetts County of Suffolk Then personally appeared before me, William D. Harrington, who, being duly sworn, did state that he is Senior Vice President-Nuclear of Boston Edison Company and that he is duly authorized to execute and file the submittal contained herein in the name and on behalf of Boston Edison Company and that the statements in said submittal are true to the best of his knowledge and belief.

My commission expires: Oc2Mw R/.1988 fJa

/

DATE

[

NOTARYP[BLIC 1

JC: caw Registered Mail Return Receipt Requested cc:

Regional Administrator U.S. Nuclear Regulatory Commission Region I - 631 Park Avenue King of Prussia, PA 15406