Provides Suppl Info for Pending License Amend Application Re Unit 1.Licensee Will Keep NRC Project Manager for Plant Informed of Further Developments
ML20094F884
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 10/30/1995
From: Stetz J
CENTERIOR ENERGY
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
2340, NUDOCS 9511090126
Download: ML20094F884 (2)


Text

.

C{

- GNTERDOR M

ENERGY 7

300 Mod 6 eon Avenue Jelut P. Slett loiedo, OH 43652-0001 Vice President - Nuclear l

419-249-2300 Dovis-Besse Docket Number 50-346 4

License Number NPF-3 Serial Number 2340 October 30, 1995 t

United States Nuclear Regulatory Commission Document Control Desk i

Washington, D. C.

20555

Subject:

License Amendment Application to Revise the Facility Opera-ting License to Reflect the Pending Merger of Operating Companies - Supplemental Information Ladies and Gentlemen:

The purpose of this letter is to provide supplemental information for a pending license amendment application regarding the Davis-Besse Nuclear Power Station (DBNPS) Unit Number 1 Operating License NPF-3.

The Toledo Edison (TE) Company submitted an application dated June 6, 1994 (TE Serial Number 2219), to the NRC for an amendment to the DBNPS Operating License Number NPF-3.

The proposed changes reflected the pending merger of the Toledo Edison Company into the Cleveland Electric Illuminating Company.

Toledo Edison submitted supplemental information to the initial submittal on July 20, 1994 (Serial No. 2239), November 11, 1994 (Serial No. 2259),

April 12, 1995 (Serial No. 2290), September 19, 1995 (Serial No. 2324), and on September 27, 1995 (Serial No. 2331).

The September 19, 1995 supplemental letter noted that although the merger requires approval of other regulatory agencies in addition to the NRC, receipt'of such approvals was believed to be imminent. Accordingly, the NRC was requested to grant consent to the license transfer pursuant to 10 CFR 50.80 on or before October 30, 1995. The letter also requested NRC consent to the associated license amendment on or before October 30, 1995, conditioning its effectiveness upon receipt of the other necessary regulatory agencies' approval and upon consummation of the merger.

nnn n, _

9511090126 951030

[ g0:

PDR ADOCK 05000346 l

PDR operating Companies:

Cleveland Electric muminating i O Toledo Edison l

~

Docket Number 50-346 License Nunter NPF-3 Serial Number 2340 Page 2 As discussed in recent conversations with the NRC Staff, acceptance of the merger by the Federal Energy Regulatory Commission is now not expected to occur within the previously anticipated timeframe.

Hence, the above-mentioned NRC actions are no longer needed on or before October 30, 1995.

A revised schedule is not available at this time. Toledo Edison will keep the NRC Project Manager for the DBNPS informed of further developments.

Toledo Edison is aware that the NRC Staff was prepared to complete the above-mentioned actions within the timeframe originally requested.

Please accept Toledo Edison's apologies for any inconvenience this subsequent delay may have caused.

Should you have any questions or require additional information, please contact Mr. William T. O'Connor, Manager - Regulatory Affairs, at (419) 249-2366.

Ve truly yours, kA %%f l

MK /laj cc:

L. L. Gundrum, DB-1 NRC/NRR Project Manager H. J. Miller, Regional Administrator, NRC Region III S. Stasek, DB-1 NRC Senior Resident Inspector J. R. Williams, Chief of Staff, Ohio Emergency Management Agency, State of Ohio (NRC Liaison)