Responds to NRC Re Violations Noted in IE Insp Rept 50-412/84-04.Corrective Actions:Completion of Electrical Encl/Barrier Scheduled for Fourth Quarter 1985
ML20094C053
Person / Time
Site: Beaver Valley
Issue date: 06/25/1984
From: Woolever E
DUQUESNE LIGHT CO.
To: Starostecki R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
Shared Package
ML20094C046 List:
References
2NRC-4-090, 2NRC-4-90, NUDOCS 8408070355
Download: ML20094C053 (6)


Text

.

9 2NRC-4-090 (412)787 - 5141 Telecopy 8-6 Nuclear Construction Division June 25, 1984 Robinson Plara Building 2, Suite 210 Pittsburgh, PA 15205 United States Nuclear Regulatory Commission Regioa I 631 Park Avenue King of Prussia, PA 19406 ATTENTION:

Mr. Richard W. Starostecki Division of Project and Resident Programs

SUBJECT:

Beaver Valley Power Station - Unit No. 2 Docket No. 50-412 USNRC IE Inspection Report No. 50-412/84-04 Gentlemen:

The purpose of this letter is to clarify the following in regard to the above referenced Inspection Report.

1.

Paragraph 3.1.1.3 Table A.

2BVS-41 should read 2BVM-41 B.

The completion date for electrical enclosure / barrier should read.4th Quarter 1985 as documented in 2ASR-01096, dated May 7, 1984 and 2ASR-01097, dated May 8, 1984 (attached).

2.

Paragraph 3.1.2.2 FCP-413 should read.FCP-431 The Beaver Valley Power Station Unit No. 2 Project is proceeding on the basis of the above corrections.

Very truly yours, E. J. Woolever Vice President JFK/smb

- 9u.

~

c ;g t:

l

-8408070355'840801

~ ~

PDR ADOCK 05000412

.O-PDR

References:

'l.

NRC Leter to E. J. Woolever, dated May 31, 1984 2.

2ASR-01096, dated May 7,1984

.3.

2ASR-01097, dated May 8, 1984 EE/50-412-Attachment bec:

J. J. Carey (w/o att)

C. E. Ewing T. D. Jones T. P. Noonan H. M. Siegel R. J. ' Swiderski C. R. Bishop

'S.

D. Hall' D. H. Williams

T. J. Lex (W)(4)

L.'E. Arch -

(w/att)

~

P. RaySircar (6)

'J.

Sutton (SWEC)

MCE-NCD File Y

mm

.. _ _ + -

r l

.-.e.

...r..r.

DATE

.,...g....,

g 7_

ygg 314 01, 002,006 2

84 i 05,09 TiuE 10:1S AM PAGE ACTIVITY SuedR8ARY REPORT 015 N/A O.c.P.

ououtsNE LaoNT cowANY 102 N/A CAT.

2ASR-01096 2

T nuclear coNsTaucT ON OlVISION 103 N/A c.c.

sueJECT j

ELECTRICAL SEPARATION - R.G.

l.75 IEPE Z ENCE NO'S.

l 130 015 048 103 0.F.E.

10080 D.C.P.

P.O.

c.0.

6289 w

101 140 E.M.

E.C.N.

Other:

ACTiveTV l

] SITE / TRIP INSPECT.

SHOP / TRIP INSFECT.

OTHER X TEl.ECODI CONFERENCE PARTICIPANTS NAME/ TITLE COWANY/ ORGANIZATION LOCATION E. J. Woolever DLC/NCD R. J. Washabaugh R. Coupland DLC/VSG J. F. Konkus DLC/NCD C. Anderson NRC

'A. Finkel L. Tripp C'

ACTivery suasm8ARY l See Attached DISTRIBUTION:. Participants E. F. Ku u H. M. Siegel E. 14.,muuliscu S. D. Hall a. a...:..,

Q Q, f

E. J. Horvath y

f4L 1 !,I k f,. -, [

C MCS

' /

}

~

3 P. RaySircar 8

2 NCD File

(

  • i ' \\[i ~
  • ,,,)

W o

3 P

/

Ol5Tnl8UTIONI

b..

m DR-AY n

e i,..i....

o.

7

._s

~j

. ELECTRICAL SEPARATION - R.G. 1.75 MAY 7, 1984

-A telecon was initiated by Mr. A Finkel of the NRC to discuss the commitment dates for compliance with R.G.

1.75, Electrical Separation Criteria.

The following items to be published in an NRC confirmatory action letter were discussed.

Item 1 - Revised 2BVS-931 issued April 2, 19 84.

The program documentation af feeted by revisions to 2BVS-931 will be identified, correct ed, and changed by the 4th Quarter 1984.

Item 2 - Elect:tical Separation Walkdown would be complete by July 31, 1984.

Item 3 - The Computer Tracking System would be implemeni:ed by April 9,1984.

Item 4 - The Design of Typical Barriers would be comple te by 4t h Qua rt er 1984.

Item 5 - The Ampacity Review would be complete by July 15, 1984.

Item 6 - The Review of the Hazard Analysis would be complete by 4th Quarter 1984.

Item 7 - Identify the Training Coordinator.

The Date for Implementation of Training to the Revised 2BVS-931 Criteria is May 14, 1984.

Item 8 - Provide the NRC with the Level 2 Schedule used to manage the program and the date of availability of the Senedule.

The above dates were presented by the NRC.

DI4 did not agree with all the agreed that DI4 would contact Mr. A. Finkel by May 8, l

dates stated.

It was 1984 with the corrected dates.

Exceptions to the following above listed items were either discussed during this telecon or will be clarified in a subsequent telecon.

Item 2 Walkdown Completion Date should read 8-31-84 Item 4 Design of Typical Barriers Completion Data should read 4th Quart er 1985 Item 6 Review fo the Hazard Analys is Completion Date should read 4th Quarter 1985 Item 7 Implementation of the " Construction Training" to the Revised 2BVS-931 Criteria will begin by May 14, 1984 C

r-

.___._..m_

j

, m m.

t i

4 1

.....--.....v.

DATE g

g gg3 314 01, 002, 006 2 84,05 1 09 Time 3:15 PM PAGE ACTIVtTV summeAny REPonT 015 N/A D.C.P.

2 oueussNs woNT conseANY 102 N/A CAT.

1 0F p

2ASR-01097 A,,

Nuctsen coNornucTioN oevisio" 103 N/A c.o.

sueJECT l

ELECTRICAL SEPARATION - R.G. l.75 l

Caps:ssect mo's.

l 130 015 048 103 C.F.E.

10080 D.C.P.

P.O.

C.O.

6289 101 140 E.M.

E.C.N.

Other: 2ASR-01096, dated May 7, 1984 ACTw Tv l

cowPtRENCE S4TE/ TRIP INSPECT.

SHOP / TRIP INSPECT.

OTHER

] Tai.sCom P:nviC:PAseTS

[

NAasE/ TITLE COeseANY/OnGANIZATION LOCATION R. Coupland DLC/ SOC E. J. Horvath DLC/NCD J. F. Konkus

(*.Finkel NRC ACTIVITY suRAMAsty l Ss2 Attached l

DISTRTRUTTON.

'7 m ve(e{nm re l

R. J. Washabaugh E. F. Kurtz H. M. Siegel K. M. Bendiksen

(-

S. D. Hall E. Meneberry R. Matherwiez

,k

  1. g%

~. 4

. i 2

H. J. Nickl 7

r

-1 P. RaySircar

'i'4 ' i i L i i, J

/

3 r-t

!?

./

k/

3 MCE

\\j 4

]

i]

NCD File I

3 l L-oisThieuTION:

}\\..

5-9-S Y

p --

, ~

5

~

ELECTRICAL SEPARATION - R.G. 1.75 MAY 8, 1984 This telecon was initiated by Mr. J. F. Konkus DLC/NCD for the purpose of estab lishing the correct commitment dates that will be published in an NRC Confirmatory Action Letter.

The corrected dates to the following items that were presented by Mr. Finkel in a-telecon with DLC on May 7,1984.

. Item 1 - Revised 2BVS-931 issued April 2,

1984.

The program document ation affacted by revisions to 2BVS-931 will be ideneified, corrected, and chatiged by the 4th Quarter 1984.

Item 2 - Electrical Separation Walkdown emple tion date was not confirmed.

PLC s tat ed this would be confirmed in a subsequent telecon to be held on May 9, 1984.

Item 3 - The Computer Tracking System would be implemented by April 9,1985.

Item 4 - The Design of Typical Barriers would be complete by 4th Quarter

-l 1985.

Item 5 - The Ampacity Review would be complete by July 15, 1984.

Item 6 - The. Review of the Hasard Analysis would be complete by 4th Quarter 1985.

Item 7 - Identify the Training Coordinator.

The date. for Implement ation of L

Training to the revised 2BVS-931 Criteria is May 14, 1984.

Item 8 - Provide the NRC with the Level 2 Schedule used to manage the program and the date of availability of the Schedule. The date for issuance of the Level 2 Schedule would be provided in the res ponse to the Confirmatory Action Letter.

h-