ILLINOIB POWEl100MPANY jf]
O9B o
sur son. P o Bo* s'** CU"'*** *" *"
July 30, 1984 Docket No. 50-461 Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Washington, D. C.
20555
Subject:
Clinton Unit I Construction Schedule Update
Dear Mr. Denton:
The USNRC letter dated May 29, 1984 from H. R. Denton to-W._J. Kelley requested Illinois Power Company to provide a-quarterly update concerning the Clinton I construction schedule.
The critical path. schedule analysis shows that the limiting system schedulei Reactor Water Cleanup, is about 53 days behind.
The critical path analysis is performed each month tc f.dentify problem areas sufficiently in advance so-that timely corrective actions can be taken.
The target dates for Fuel Load and Commercial Operation remain at January 3 and November 1, 1986, respectively.
h--I We will' continue to submit quarterly updates of the Unit I construction schedule.
~
Sin rely yours, D.
P.
Hall Vice President REW/ psf-cc Mr.
B. Siegel, NRC Clinton Project Manager NRC Resident Office Illinois _ Dept. of Nuclear Safety Regional-Administrator, Region III, USNRC j'J"E8u'S8Eh
~