i; [,,Y CommonwealthEdison PRINCIPAL STAFF
'N A 960 North Route 47 RA 1DRP
~(' '")
Morris, Illinois 60450 D/RA DRS July 25, 1984 0
-Mr.-Jack Hind, Director Division of Emergency Preparedness and Operational Support U.S. Nuclear Regulatory Commission Region III 799 Roosevelt Road Glen Ellyn, IL 60137
SUBJECT:
LASALLE COUNTY STATION EMERGENCY EXERCISE OCTOBER 10, 1984 NRC DOCKET NUMBERS 50-373 & 50-374
Dear Mr. Hind:
Attached are the Objectives and the Scope of Participation proposed for the LaSalle County Exercise to be conducted on October 10, 1984.
These Scenario documents are submitted in accordance with the NRC and FEMA requirements.
Question regarding the LaSalle County Station Scope of Participation or Objectives should be directed to Tim Greene, (815)-942-8169.
Sincerely, A
f5 JAh&
T.R.
Greene Emergency Planner Technical Services Nuclear TRG:wjm Enclosures cc:
Mr. Wallace Weaver, RAC Chairman FEMA, Region V 300 South Wacker Drive Chicago, Illinois 60606 Mr.
E.
Erie Jones, Director, Illinois ESDA 110 East Adams Street Springfield, Illinois 62705 Mr. Steve Dunas Illinois Dept. of Nuclear Safety 1035 Outer Park Drive Springfield, Illinois 62704 CECO:
J.C. Golden, Technical Services Nuclear D.L.
Butterfield, Nuclear Station Division D.L. Farrar, Nuclear Licensing Administration EOF-84-165
_ 0565A/1 JUL 271984 8408060101 840801 PDR ADOCK 05000373 F
1 g, _h
~
\\
OBJECTIVES PRIMARY OBJECTIVE:
Demonstrate'the capability to implement the Commonwealth Edison Generating Station's Emergency Plan in cooperation with the Illinois Plan for Radiological Accidents to protect-the public in the event of a major accident at the La Salle County Station.
SUPPORTING OBJECTIVES 1)-
Incident Assessment and Classification a.
Demonstrate the capability to assess the accident conditions, to determine which Emergency Action Level (EAL) has been reached, and to classify the accident level correctly in accordance with
'GSEP.
2.
Notification and Communication a.
-Demonstrate the capability to notify the principal offsite organizations via NARS within 15 minutes of classification.
b.
Demonstrate the ability to notify the NRC within one hour of incident occurence.
c.
Demonstrate the capability to contact organizations that would normally assist in an emergency, but are not participating in this exercise (i.e.,
Sargent & Lundy, General Electric, INPO.)
d.
Demonstrate the Security Force's ability to communicate accurate and timely information to appropriate departments and/or organizations, both on-site and offsite (Note:
Any necessary offsite communications may be simulated.)
e.
Demonstrate the ability to provide accurate and timely information so reports may be made to the Joint Public Information Center (JPIC) for press releases.
(JPIC) f.
Demonstrate the ability of the News Information Center to control rumors that have been genc 'ated offsite.
(JPIC) 0530A/2 L
l I
f?...
I*
t V
c3)
Radiological Assessment' a.
Demonstrate the capability to calculate offsite dose projections.
Demonstrate the capability ~of Environmental Field
. Teams to conduct field radiation surveys, collect
. air, liquid,' vegetation and soil samples when needed.
(Environs Team.)
c.
Demonstrate the capability to' conduct in-plant radiation protection activities..
(OSC/ Health Physics Teams.)
d.
Demonstrate the ability to collect and conduct analy/ Rad. sis.of air or liquid sampit,s cw<3ite.
(OSC Chem.)
e.
Demonstrate the ability to perform calculations with radiological survey information, trend this information and make appropriate recommendations concerning protective actions.
4.
Emergency Facility Manning Demonstrate-the ability to activate the emergency a.
organization and' staff the nuclear station Emergency Response Facilities in accordance with procedures.
(Control Room, TSC, EOF, OSC/ General Plant and JPIC.)
b.
Demonstrate the ability to activate the TSC with appropriate staff in accordance with off-hours augmentation procedures.
Demonstrate the capability to provide timely and c.
accurate on-site personnel accountability in accordance with procedures.
5.
Emergency Direction and Control a.
-Demonstrate the ability of the Directors to manage the emergency organizations in the implementation of the CSEP.
Demonstrate the ability to interface with the NRC, through the use of CECO role players as NRC j_
individuals, in the Technical Support Center and j
the Emergency Operations Facility.
(TSC and EOF) i 0530A/3/wjm-i.
1 AT j
.,ga
. i i
5.
Emergency Direction and Control (cont'd) c.
Demonstrate the Security Force's capability tx) implement contingency responses during a threat to the Station.
d.
Demonstrate the Security Force's capability to limit and control access to affected areas of the Station during a contingency event.
6.
Recovery and Re-entry Demonstrate the capability of the emergency a.
response personnel to identify requirements, programs, policies governing damage assessments and implementation of procedures for recovery and re-entry.
r x i,. * :
~:*
. ): T i
SCOPE OF PARTICIPATION Commonwealth Edison will participate in the La Salle County Station exercise by activating the on-site' emergency response organization and the EOF as appropriate, subject to limitations that may become necessary to provide for safe efficient operation of the Station and other CECO nuclear generating stations.
Activation of the TSC and other on-site participants will be conducted on a real time basis during the evening hours.
The shift on duty will receive the initial scenario information and respond accordingly.
The Nuclear Duty Person and the balance of the Recovery Gourp will be prepositioned close to the La Salle Station to permit use of Recovery Group personnel from distant locations.
The Corporate Command' Center will not be' activated.
The La Salle County Station, October 10, 1984, Exercise is an off-hours event to test the integrated capability.of Commonwealth Edison, the State of Illinois and local governmental preparedness plans, and to assure adequate resources to verify their capability to respond to a simulated emergency.
Commonwealth Edison will demonstrate the capability to make contact with contractors, whose assistance would be required by the simulated accident situation, but will not actually incur the expense of using contractor services to simulate emergency response except as prearranged specifically for the exercise.
Commonwealth Edison will arrange to.p,rovide actual transportation and communication support in accordance with existing agreements to the extent specifically prearranged for the exercise.. Commonwealth Edison will provide unforeseen actual assistance only to the extent the resources are available and do not hinder normal operation of the Company.
l l
l 0530A/5/wjm m