ML20093D871
ML20093D871 | |
Person / Time | |
---|---|
Site: | Vermont Yankee File:NorthStar Vermont Yankee icon.png |
Issue date: | 07/13/1984 |
From: | Conway W VERMONT YANKEE NUCLEAR POWER CORP. |
To: | Deyoung R NRC OFFICE OF INSPECTION & ENFORCEMENT (IE) |
References | |
REF-PT21-84-321-000 FVY-84-86, IEIN-84-30, PT21-84-321, PT21-84-321-000, NUDOCS 8407170264 | |
Download: ML20093D871 (1) | |
Similar Documents at Vermont Yankee | |
---|---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARML20217N3901999-10-25025 October 1999
[Table view]Advises That Info Provided in & Affidavit Re Holtec Position Paper WS-115,rev 1,repts HI-87113, Rev 0,HI-87114,rev 0,HI-87102 Rev 0 & HI-87112,rev 0,marked Proprietary,Will Be Withheld from Public Disclosure ML20217L8591999-10-21021 October 1999 Discusses 990921 Request for Approval to Perform Alternative Testing as Part of Vermont Yankee Nuclear Power Station IST Program.Informs That Submittal Reviewed Against ASME Code Section XI Requirements & Forwards Safety Evaluation ML20217M1181999-10-19019 October 1999 Forwards NRC Rept Number 17, Requal Tracking Rept from Operator Licensing Tracking Sys.Rept Was Used by NRC to Schedule Requalification Exam for Operators & Record Requal Pass Dates ML20217D9711999-10-13013 October 1999 Responds to Request That Information Titled Addl Info Re Cycle Specific SLMCPR for Vermont Yankee Cycle 21 Be Withheld from Public Disclosure.Determined Info to Be Proprietary & Will Be Withheld from Public Disclosure ML20217F1261999-10-12012 October 1999 Forwards Update to Previously Submitted RELAP5 Analytical Assumptions for App R,Re RAI of 961104 BVY-99-130, Provides Clarification of Method for Determining MSIV Maximum & Minimum Pathway at Vermont Yankee Nuclear Power Station1999-10-0808 October 1999 Provides Clarification of Method for Determining MSIV Maximum & Minimum Pathway at Vermont Yankee Nuclear Power Station ML20217C1501999-10-0707 October 1999 Forwards Insp Rept 50-271/99-11 on 990809-27.No Violations Noted.Insp Focused on Effectiveness of Engineering Functions in Providing for Safe Operation of Plant BVY-99-128, Submits Listed Addl Info in Support of 990414 Request for Clarification to SER Confirming Adequacy of Space Cooling for HPCI & RCIC Sys,Re Item II.K.3.24 of NUREG-0737.Copy of NEDE-24955,encl1999-10-0606 October 1999 Submits Listed Addl Info in Support of 990414 Request for Clarification to SER Confirming Adequacy of Space Cooling for HPCI & RCIC Sys,Re Item II.K.3.24 of NUREG-0737.Copy of NEDE-24955,encl ML20212J7891999-10-0404 October 1999 Informs That Licensee 980804,0628,29 & 990921 Responses to GL 98-01, Y2K Readiness of Computer Sys at NPPs Acceptable.Nrc Consider Subj GL to Be Closed for Plant ML20212J6501999-09-30030 September 1999 Informs of Completion of mid-cycle PPR of VYNPS on 990913. No New Areas Identified in Which Licensee Performance Warranted Addl Insp Beyond Core Insp Program.Historical Listing of Plant Issues & Insp Plan Through Mar 2000 Encl ML20216J3531999-09-29029 September 1999 Responds to NRC Re Violations Noted in Insp Rept 50-271/99-12 on 990628-0811.Corrective Actions:Based on RFO 20 Maint Rule Outage Performance Review,Task Was Generated to Clarify & Enhance SD Monitoring Process BVY-99-122, Notifies of Intention to Reinstate Original Version of App F in FSAR & Correct Docket Re Assumption That Electrical Power Sys Are Designed IAW Requirements of GDC-171999-09-28028 September 1999 Notifies of Intention to Reinstate Original Version of App F in FSAR & Correct Docket Re Assumption That Electrical Power Sys Are Designed IAW Requirements of GDC-17 BVY-99-114, Provides Notification That Licensee Completed Y2K Remediation Efforts Described in Util 990608 Response to NRC GL 98-01,Suppl 11999-09-21021 September 1999 Provides Notification That Licensee Completed Y2K Remediation Efforts Described in Util 990608 Response to NRC GL 98-01,Suppl 1 BVY-99-113, Requests Approval to Perform Alternative Testing to That Specified by ASME Boiler & Pressure Vessel Code,Section XI & Asme/Ansi OM, Operation & Maint of Nuclear Power Plants. Attachment 1 Provides Justification for Alternative Testing1999-09-21021 September 1999 Requests Approval to Perform Alternative Testing to That Specified by ASME Boiler & Pressure Vessel Code,Section XI & Asme/Ansi OM, Operation & Maint of Nuclear Power Plants. Attachment 1 Provides Justification for Alternative Testing BVY-99-116, Informs of Determination That Wh Schulze,License SOP-10528-1,will No Longer Maintain License at Facility. Termination of License Requested1999-09-21021 September 1999 Informs of Determination That Wh Schulze,License SOP-10528-1,will No Longer Maintain License at Facility. Termination of License Requested BVY-99-121, Requests Extension Until 990929 to Respond to Violations Noted in Insp Rept 50-271/99-12,dtd 990819.Licensee Did Not Receive Rept Until 990830 & Addl Time Is Needed to Prepare & Allow for Adequate Review of Violation Response Submittal1999-09-20020 September 1999 Requests Extension Until 990929 to Respond to Violations Noted in Insp Rept 50-271/99-12,dtd 990819.Licensee Did Not Receive Rept Until 990830 & Addl Time Is Needed to Prepare & Allow for Adequate Review of Violation Response Submittal ML20212C1621999-09-17017 September 1999 Forwards Amend 175 to License DPR-28 & Safety Evaluation. Amend Revises TSs to Enhance Limiting Conditions for Operation & Surveillance Requirements Relating to Standby Liquid Control System BVY-99-118, Responds to RAI Concerning GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions1999-09-16016 September 1999 Responds to RAI Concerning GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions BVY-99-115, Forwards non-proprietary & Proprietary Responses to 990714 RAI Re Civil & Mechanical Engineering Considerations for Proposed Change to TS to Increase Spent Fuel Storage Capacity from 2,870 to 3,355.Proprietary Encls Withheld1999-09-16016 September 1999 Forwards non-proprietary & Proprietary Responses to 990714 RAI Re Civil & Mechanical Engineering Considerations for Proposed Change to TS to Increase Spent Fuel Storage Capacity from 2,870 to 3,355.Proprietary Encls Withheld ML20216F3171999-09-13013 September 1999 Forwards Insp Rept 50-271/99-06 on 990621-0801.One Violation Identified & Being Treated as Noncited Violation BVY-99-110, Informs of Util Intent to Replace Commitments Made in Licensee & Subsequently Ack in NRC with Containment Insp Criteria Defined in 10CFR50.55a(b)(2)(vi),per Drywell Coating Insp1999-08-31031 August 1999 Informs of Util Intent to Replace Commitments Made in Licensee & Subsequently Ack in NRC with Containment Insp Criteria Defined in 10CFR50.55a(b)(2)(vi),per Drywell Coating Insp BVY-99-111, Informs That Encl TS Bases Page 91 Has Been Revised to Allow Reactivity Anomaly BOC Steady State Core Reactivity to Be Normalized Between off-line Uncorrected Solution & on-line 3D-Monicore Exposure Corrected Solution1999-08-31031 August 1999 Informs That Encl TS Bases Page 91 Has Been Revised to Allow Reactivity Anomaly BOC Steady State Core Reactivity to Be Normalized Between off-line Uncorrected Solution & on-line 3D-Monicore Exposure Corrected Solution ML20211G4791999-08-27027 August 1999 Forwards Notice of Withdrawal of 990420 Amend Request Re TS on Reloading & Unloading Sequence of Fuel in Reactor Core When All Fuel Removed from Core BVY-99-107, Submits Response to NRC RAI Re Proposed Change to TS to Increase Spent Fuel Storage Capacity from 2,870 to 3,355 Fuel Assemblies1999-08-26026 August 1999 Submits Response to NRC RAI Re Proposed Change to TS to Increase Spent Fuel Storage Capacity from 2,870 to 3,355 Fuel Assemblies ML20211E8841999-08-25025 August 1999 Requests That Licensee Provide bldg-specific Justification for Use of Method A.1 at Locations Where Amplification Significantly Exceeds 1.5 Limit Above 8 Hz ML20211E1371999-08-20020 August 1999 Forwards from J Bean to H Miller & FEMA Final Exercise Rept for 990427-29 Plume Exposure & Ingestion Pathway Exercise for Vermont Yankee Nuclear Power Station.No Deficiencies Noted.Areas Requiring C/A Identified ML20211H0851999-08-19019 August 1999 Forwards Insp Rept 50-271/99-12 on 990628-0711 & Nov. Violation Re Failure to Monitor Unavailability of Specific Sys,Structures & Components During Refueling Outage Did Not Allow Adequate Assessment of Maint Effectiveness BVY-99-108, Requests That Gv Bogue,Bj Croke,Vs Ferrizzi,Me French, Bk Mcnutt,Jf Meyer & DM Navarro Take BWR Gfes of OL Exam Administered on 991006.DA Daigler & ST Brown Will Have Access to Exams Before Tests Administered1999-08-19019 August 1999 Requests That Gv Bogue,Bj Croke,Vs Ferrizzi,Me French, Bk Mcnutt,Jf Meyer & DM Navarro Take BWR Gfes of OL Exam Administered on 991006.DA Daigler & ST Brown Will Have Access to Exams Before Tests Administered BVY-99-103, Informs That Util Expects to Submit Approx Twenty Licensing Actions in FY00 & FY01,in Response to Administrative Ltr 99-021999-08-18018 August 1999 Informs That Util Expects to Submit Approx Twenty Licensing Actions in FY00 & FY01,in Response to Administrative Ltr 99-02 BVY-99-100, Forwards Revised Floor Response Spectra Diagrams,Originally Sent as Attachment 1 to Licensee to Nrc.Revised Diagrams Have More Legible Scale Markings1999-08-0202 August 1999 Forwards Revised Floor Response Spectra Diagrams,Originally Sent as Attachment 1 to Licensee to Nrc.Revised Diagrams Have More Legible Scale Markings ML20210M5791999-07-30030 July 1999 Responds to NRC 990726 Telcon Re Status of Resolution for USI A-46 Outliers.Written Summary,By Equipment Category, Listed ML20211E1701999-07-28028 July 1999 Forwards Copy of Final Exercise Rept for 990427-29,full- Participation Plume Exposure & Ingestion Pathway Exercise of Offsite Radiological Emergency Response Plans site-specific to VYNPS ML20210G5041999-07-27027 July 1999 Responds to NRC 990301 RAI Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design- Basis Accident Conditions. Licensee Will Submit Info Re Proposed Sys Mod by 990916 ML20210J3031999-07-27027 July 1999 Submits Proposed Changes to Eals.Attachment 1 Provides Listing of Changes to EALs Along with Ref to Bases Documents Supporting Change ML20210G4271999-07-27027 July 1999 Forwards Testing Data & Associated Results for Fitness for Duty Program at Plant for 990101-0630 ML20216D7321999-07-26026 July 1999 Forwards Insp Rept 50-271/99-05 on 990510-0620.Two Viiolations Being Treated as Noncited Violations ML20209G2721999-07-14014 July 1999 Discusses Licensee Response to RAI Re GL 92-01,Rev 1,Suppl Suppl 1, Rv Structural Integrity, for Vermont Yankee Nuclear Power Station ML20209J0601999-07-14014 July 1999 Forwards Rev 11 to Vols 1-10 of State of Nh Radiological Emergency Response Plan & Vols 11-50 to Town Radiological Emergency Response Plans,In Support of Vermont Yankee & Seabrook Station.Vols 17-19 of Were Not Included ML20209G6931999-07-14014 July 1999 Forwards Request for Addl Info Re Spent Fuel Storage Capacity Expansion ML20209G1531999-07-12012 July 1999 Discusses Util Setpoint Control Program Implementation Schedule,As Committed to in Licensee 990514 Response to Notice of Violation,Insp Rept 50-271/97-10 ML20196J2321999-06-30030 June 1999 Submits Input from Util Technical Staff Re Soil Disposal on-site Under 10CFR20.2002 & Expresses Interest in Pursuing Approval to Use Same Methodology (Implemented Through Util ODCM & Reported as Noted) If Possible ML20196J7421999-06-29029 June 1999 Informs NRC That Vygs Has Implemented Severe Accident Management,As Committed to in Licensee to NRC ML20209B6111999-06-29029 June 1999 Resubmits Summary of Vynp Commitments Page to Replace Original Page Submitted with Responding to GL 98-01,Suppl 1, Y2K Readiness of Computer Sys at Nuclear Power Plants ML20196J2431999-06-29029 June 1999 Informs That Author Received Call from NRR on Dirt Spreading Ltr & Questions Re Cover Ltr Statement Where Util Asks to Be Allowed to Dispose of Future Soil in Same Manner Provided Same Acceptance Criteria Met ML20209C3751999-06-28028 June 1999 Forwards non-proprietary Rev 16 to EPIP OP 3524, Emergency Actions to Ensure Initial Accountability & Security Response & Proprietary Rev 12 to EPIP OP 3531, Emergency Call-In Method. Proprietary Encl Withheld ML20209B5861999-06-28028 June 1999 Provides Alternative Y2K Readiness Status Described in Supplement 1 to GL 98-01, Y2K Readiness of Computer Sys at Npps. Y2K Readiness Disclosure Rept Encl ML20196G5241999-06-22022 June 1999 Responds to Re Changes to Vermont Yankee Guard Training & Qualification Plan,Rev 8,Errata A.No NRC Approval Is Required.Encl Will Be Withheld from Public Disclosure Per 10CFR73.21 BVY-99-084, Forwards Proprietary Application & Medical Certificate for Mod of Listed SRO License,For Gj Leclair.Gj Leclair Will Be Trained & Evaluated in Accordance with Util Lsro Training Description.Proprietary Info Withheld,Per 10CFR2.7901999-06-18018 June 1999 Forwards Proprietary Application & Medical Certificate for Mod of Listed SRO License,For Gj Leclair.Gj Leclair Will Be Trained & Evaluated in Accordance with Util Lsro Training Description.Proprietary Info Withheld,Per 10CFR2.790 ML20212J0541999-06-17017 June 1999 Responds to Requesting That NRC Staff ...Allow BWR Plants Identified to Defer Weld Overlay Exams Until March 2001 or Until Completion of NRC Staff Review & Approval of Proposed Generic Rept,Whichever Comes First ML20195H1741999-06-15015 June 1999 Forwards Original & Copy of Request for Approval of Certain Indirect & Direct Transfer of License & Ownership Interests of Montaup Electric Co (Montaup) with Respect to Nuclear Facilities Described as Listed 1999-09-30 Category:DEFICIENCY REPORTS (PER 10CFR50.55E & PART 21) MONTHYEARML20211M6491997-10-0808 October 1997
[Table view]Addenda 1 to Part 21 Rept Re Weldments on Opposed Piston & Coltec-Pielstick Emergency stand-by Diesel gen-set lube-oil & Jacket Water Piping Sys.Revised List of Potentially Affected Utils to Include Asterisked Utils,Submitted ML20211H7911997-09-30030 September 1997 Part 21 Rept Re Failure of Weldment Associated w/lube-oil Piping Sys on 970804 at Millstone,Unit 2.Root Cause Is Not Yet Known.Quality of Weldment Is Being Considered.Listed Util Sites Affected ML18038A8971994-09-0707 September 1994 Part 21 Rept Re Defect in Latching Mechanism of Potter & Brumfield Relay on C&D High Voltage Shut Down Alarm Assembly Printed Circuit Boards.Pull Test on Relay Reset Button Incorporated Into Receiving Insp Procedures ML20059F2631994-01-0707 January 1994 Part 21 Rept Re Air Start Distributor Cam Mfg by Fairbanks Morse.Mfg Suggests That Site Referenced in Encl App I Inspect Air Start Distributor Cam as Soon as Practical ML20125C7161992-12-0707 December 1992 Part 21 Rept Re Possibility for Malfunction of Declutching Mechanisms in SMB/SB-000 & SMB/SB/SBD-00 Actuators. Malfunction Only Occurs During Seismic Event.Balanced Levers May Be Purchased from Vendor.List of Affected Utils Encl ML20127P5861992-11-23023 November 1992 Followup to 921005 Part 21 Rept Re Potential Defect in SB/SBD-1 Housing Cover Screws.Procedure Re Replacement of SBD-1 Spring Cover Bolts Encl.All Fasteners Should Be Loosened & Removed.List of Affected Utils Encl ML20095J7981992-04-29029 April 1992 Part 21 Rept Re Failure of Anchor Darling Swing Check Valve to Move Freely Through Entire Range of Motion.Caused by Insufficient Clearance Between Swing Arm & Shaft Bushings. Valve Repaired Onsite by Vendor ML20090L8801992-03-18018 March 1992 Part 21 Re Cracked Piston Castings Received from Acme Foundry,Fairbanks Morse & General Casting.Magnetic Particle Insp of All Pistons Will Be Performed.List of Affected Plants Encl ML20247M5851989-07-27027 July 1989 Part 21 Rept Re Failed Globe Valve Stem on 890405.Caused by Improper Heat Treatment of 410 Stainless Steel Alloy Used in Stem Which Increased Susceptibility to Stress Corrosion Cracking.Larger Shaft Modified by Machining Radius ML20246H5331989-02-14014 February 1989 Part 21 Rept Re Defect in Motor Mounting Bolts on Limitorque Operators & Reliance Motors.Caused by Loosening of Motor End Bell Bolts.All Normally Inaccessible Operators W/Susceptible Bolting Will Be Inspected ML20204D1911987-03-20020 March 1987 Part 21 Rept Re Potential Existence of Design Defect in Bingham/Willamette RHR Pumps Flow Capacity.Ge Will Perform Evaluation of Conditions.Operators Will Be Alerted in Writing to Miminize Time in Min Flow Mode FVY-86-105, Part 21 Rept Re Design Defect Relating to Limitorque Motor Operators Mfg Prior to 1975.Mfg Contacted & Retrofit Kits Installed on safety-related & nonsafety-related Operators. Addl Info Encl1986-11-10010 November 1986 Part 21 Rept Re Design Defect Relating to Limitorque Motor Operators Mfg Prior to 1975.Mfg Contacted & Retrofit Kits Installed on safety-related & nonsafety-related Operators. Addl Info Encl ML20196E1171986-09-16016 September 1986 Part 21 Rept Re GE Solenoid Valve Rebuild Kits.Defect Found During Failure to Scram on 860613-28.Util Replaced All 178 Hydraulic Control Unit Scram Solenoid Internals,Plus Two Discharge Vol Solenoid Valve Internals NRC-86-3142, Part 21 Rept Re Increased Failure Probability of Coils Used in Class 1E Motor Starters & Contactors Supplied to Nuclear Power Plants by Westinghouse.Replacement Coils Mfg for All Starters & Contactors on Encl List1986-06-19019 June 1986 Part 21 Rept Re Increased Failure Probability of Coils Used in Class 1E Motor Starters & Contactors Supplied to Nuclear Power Plants by Westinghouse.Replacement Coils Mfg for All Starters & Contactors on Encl List ML20141A0881986-03-28028 March 1986 Part 21 Rept Re Potential Defect in Contact Block Kits Supplied by Namco Controls.Initially Reported on 860227. Defective Kits Replaced.Vendor QA Program Under Reevaluation ML20154N5141986-03-10010 March 1986 Part 21 Rept Re Failure of Standby Liquid Control Sys Squib Valve to Fire.Caused by Discrepancies Identified Between Conax Corp Drawings of Trigger Assemblies & Wiring Configuration of Trigger Assemblies in Stock ML20154K3611986-03-0505 March 1986 Part 21 Rept Re Possible Wiring Defect in Fabricated Primer Chamber Assemblies for Standby Liquid Control Valves. Initially Reported on 860214.Listed Corrective Actions Will Be Completed by 860328 ML20126C6901985-06-0505 June 1985 Part 21 Rept Re Generator Failure.Concurs W/Encl Louis Allis That Interpolar Connectors Be Removed ML20129G4401985-05-29029 May 1985 Part 21 Rept Re Failure of Inner Polar Connector Between Damper Bar Circuit on Generator Main Field.Cause of Failure Not Defined.Further Investigation Necessary ML20116K0891985-03-0505 March 1985 Followup Part 21 Rept Re Overcompression of Power Lead Gland Assembly Sealant During Factory Assembly.Procedures Revised to Specify That Only One Coat of Threaded Lubricant Will Be Applied.Proprietary Rept Encl.Rept Withheld ML20096C5761984-08-31031 August 1984 Part 21 Rept Re Potential Defect in Power Lead Gland Assemblies Qualified for Nuclear Svc.Parts 7D92-11000-01-04, 7D92-11001-01-05,N-11150-01 & N-11151-01 Showing Loss of Electrical Continuity.Customer Informed & Evaluation Begun ML20093D8711984-07-13013 July 1984 Part 21 Rept Responding to NRC Re IE Info Notice 84-30 on Bahnson Co HVAC Equipment.Units Not Supplied to Facility.Stringent QA Program Implementation Essential to Prevent & Detect Problems ML20093D1431984-06-29029 June 1984 Part 21 Rept Re Defective Uninterruptible Power Supply Batteries Supplies by Exide Corp.Util Replaced Batteries During Current 1984 Refueling Outage ML20082E7801983-11-21021 November 1983 Part 21 Rept Advising That Review of QA Program Initiated in Response to IE Bulletins 83-06 & 83-07 to Address Possible Fraudulent Actions by Suppliers ML19305F2001980-11-0303 November 1980 Part 21 Rept Re Failure of Fire Penetration Seals to Pass Fire Test.Cause Undetermined.Tested Matl Will Be Analyzed 1997-09-30 Category:TEXT-SAFETY REPORT MONTHYEARML20217L8831999-10-21021 October 1999
[Table view]Safety Evaluation Supporting Proposed Alternatives to Code Requirements Described in RR-V17 & RR-V18 ML20217G2041999-10-13013 October 1999 Safety Evaluation Supporting Amend 179 to License DPR-28 BVY-99-127, Monthly Operating Rept for Sept 1999 for Vermont Yankee Nuclear Power Station.With1999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Vermont Yankee Nuclear Power Station.With ML20212C2551999-09-17017 September 1999 Safety Evaluation Supporting Amend 175 to License DPR-28 BVY-99-112, Monthly Operating Rept for Aug 1999 for Vermont Yankee.With1999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Vermont Yankee.With BVY-99-109, Ro:On 990812,stack Ng Effluent Instrumentation for PAM Was Declared Oos.Caused by Instrument Drift Due to Electronic Components Based on Insps by Instrumentation & Controls Dept.Detector & Preamplifier Will Be Replaced on 9908311999-08-19019 August 1999 Ro:On 990812,stack Ng Effluent Instrumentation for PAM Was Declared Oos.Caused by Instrument Drift Due to Electronic Components Based on Insps by Instrumentation & Controls Dept.Detector & Preamplifier Will Be Replaced on 990831 BVY-99-102, Monthly Operating Rept for July 1999 for Vermont Yankee. with1999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Vermont Yankee. with ML20209J0081999-07-14014 July 1999 Special Rept:On 990615,diesel Driven Fire Pump Failed to Achieve Rated Flow of 2500 Gallons Per Minute.Pump Was Inoperable for Greater than 7 Days.Corrective Maint Was Performed to Reset Pump Lift Setting BVY-99-090, Monthly Operating Rept for June 1999 for Vermont Yankee Nuclear Power Station.With1999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Vermont Yankee Nuclear Power Station.With ML20196G5071999-06-23023 June 1999 Vynp Assessment of On-Site Disposal of Contaminated Soil by Land Spreading BVY-99-077, Monthly Operating Rept for May 1999 for Vermont Yankee Nuclear Power Station.With1999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Vermont Yankee Nuclear Power Station.With BVY-99-068, Monthly Operating Rept for Apr 1999 for Vynp.With1999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Vynp.With ML20206E8741999-04-29029 April 1999 SER Determined That Flaw Evaluation Meets Rules of ASME Code & Assumed Crack Growth Rate Adequate for Application ML20206D9301999-04-27027 April 1999 1999 Emergency Preparedness Exercise 990427 Exercise Manual (Plume Portion) ML20205S4211999-04-16016 April 1999 Non-proprietary Version of Revised Page 4-3 of HI-981932 Technical Rept for Vermont Yankee Spent Fuel Pool Storage Expansion ML20205K7581999-04-0707 April 1999 Safety Evaluation Supporting Alternative Proposal for Reexamination of Circumferential Welds with Detected Flaw Indications in Plant RPV BVY-99-046, Monthly Operating Rept for Mar 1999 for Vermont Yankee Nuclear Power Station.With1999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Vermont Yankee Nuclear Power Station.With ML20205F6631999-03-0404 March 1999 Jet Pump Riser Weld Leakage Evaluation BVY-99-035, Monthly Operating Rept for Feb 1999 for Vermont Yankee Nuclear Station.With1999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Vermont Yankee Nuclear Station.With ML20205P8241999-02-28028 February 1999 Rev 2 to Vermont Yankee Cycle 20 Colr ML20203H9881999-02-18018 February 1999 SER Accepting Alternative to 10CFR50.55a(g)(6)(ii)(A) Augmented Reactor Vessel Exam at Vermont Yankee Nuclear Power Station.Technical Ltr Rept Encl ML20203A6951999-02-0404 February 1999 Revised Rev 2,App B to Vermont Yankee Operational QA Manual (Voqam) ML20199K7151999-01-21021 January 1999 Corrected Safety Evaluation Supporting Amend 163 Issued to FOL DPR-28.Pages 2 & 3 Required Correction & Clarification ML20199K6991999-01-20020 January 1999 Safety Evaluation Concluding That Request to Use YAEC-1339, Yankee Atomic Electric Co Application of FIBWR2 Core Hydraulics Code to BWR Reload Analysis, at Vermont Yankee Acceptable ML20199L5951999-01-14014 January 1999 Safety Evaluation Accepting Licensee Proposed Alternative to Code Requirement,Described in Rev 2 to Pump Relief Request RR-P10 Pursuant to 10CFR50.55a(a)(3)(i) BVY-99-071, Corp 1998 Annual Rept. with1998-12-31031 December 1998 Corp 1998 Annual Rept. with BVY-99-001, Monthly Operating Rept for Dec 1998 for Vermont Yankee Nuclear Power Station1998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for Vermont Yankee Nuclear Power Station ML20198H5481998-12-23023 December 1998 Rev 2 to Vermont Operational QA Manual,Voqam ML20196H8641998-12-0101 December 1998 Cycle 19 Operating Rept BVY-98-163, Monthly Operating Rept for Nov 1998 for Vermont Yankee Nuclear Power Station.With1998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Vermont Yankee Nuclear Power Station.With ML20195C4161998-11-0909 November 1998 SER Accepting Request That NRC Approve ASME Code Case N-560, Alternative Exam Requirement for Class 1,Category B-J Piping Welds BVY-98-154, Monthly Operating Rept for Oct 1998 for Vermont Yankee Nuclear Power Station.With1998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Vermont Yankee Nuclear Power Station.With ML20155B6471998-10-26026 October 1998 Safety Evaluation Accepting Jet Pump Riser Insp Results & Flaw Evaluation,Conducted During 1998 Refueling Outage ML20154N0891998-10-16016 October 1998 Rev 1 to Vermont Operational QA Program Manual (Voqam) ML20154B6951998-10-0101 October 1998 SER Re Licensee Response to GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves, for Vermont Yankee Nuclear Power Station BVY-98-149, Monthly Operating Rept for Sept 1998 for Vermont Yankee Nuclear Power Station.With1998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for Vermont Yankee Nuclear Power Station.With ML20239A1361998-09-0202 September 1998 SER Re License Request for NRC Review & Concurrence W/Changes to NRC-approved Fire Protection Program BVY-98-135, Monthly Operating Rept for Aug 1998 for Vermont Yankee Nuclear Power Station.With1998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for Vermont Yankee Nuclear Power Station.With ML20151U0361998-08-28028 August 1998 Non-proprietary Rev 1 to Holtec Rept HI-981932, Vermont Yankee Nuclear Power Station Spent Storage Expansion Project ML20237E9221998-08-20020 August 1998 Vynp 1998 Form NIS-1 Owners Summary Rept for ISI, 961103-980603 BVY-98-122, Monthly Operating Rept for July 1998 for Vermont Yankee Nuclear Power Station1998-07-31031 July 1998 Monthly Operating Rept for July 1998 for Vermont Yankee Nuclear Power Station ML20205F6491998-07-31031 July 1998 Rev 1 to GE-NE-B13-01935-02, Jet Pump Assembly Welds Flaw Evaluation Handbook for Vermont Yankee ML20236G0011998-06-30030 June 1998 Individual Plant Exam External Events BVY-98-098, Monthly Operating Rept for June 1998 for Vermont Yankee Nuclear Power Station1998-06-30030 June 1998 Monthly Operating Rept for June 1998 for Vermont Yankee Nuclear Power Station ML20248C5081998-05-31031 May 1998 Rev 2 to 24A5416, Supplemental Reload Licensing Rept for Vermont Yankee Nuclear Power Station Reload 19 Cycle 20 ML20248C4951998-05-31031 May 1998 Rev 1 to Vermont Yankee Nuclear Power Station Cycle 20 Colr BVY-98-081, Monthly Operating Rept for May 1998 for Vermont Yankee Nuclear Power Station1998-05-31031 May 1998 Monthly Operating Rept for May 1998 for Vermont Yankee Nuclear Power Station ML20247J8341998-05-31031 May 1998 Peak Suppression Pool Temp Analyses for Large Break LOCA Scenarios, for May 1998 ML20247G4001998-05-12012 May 1998 Interview Rept of Ej Massey ML20247E6351998-04-30030 April 1998 Rev 1 to GE-NE-B13-01935-LTR, Jet Pump Riser Welds Allowable Flaw Sizes Ltr Rept for Vermont Yankee 1999-09-30 Category:UTILITY TO NRC MONTHYEARML20059J2831990-09-10010 September 1990
[Table view]Forwards Updated Operator Licensing Exam Schedule for FY91, FY92,FY93 & FY94,per Generic Ltrs 90-07 & 89-12 ML20059D9831990-08-28028 August 1990 Forwards fitness-for-duty Program Performance Data for 900103-0630,per 10CFR26.71.NRC Review of Data Will Provide Realization That Positive Testing Rate Extremely Low & Limited to pre-access Testing Population BVY-90-087, Forwards Addl Info on Use of RELAP5YA Program for LOCA Analyses.Proprietary Encl Withheld1990-08-28028 August 1990 Forwards Addl Info on Use of RELAP5YA Program for LOCA Analyses.Proprietary Encl Withheld BVY-90-086, Responds to NRC Re Violations Noted in Insp Rept 50-271/90-06.Corrective Actions:Incident Rept Initiated & All Required Locking Devices in Place by 9007061990-08-24024 August 1990 Responds to NRC Re Violations Noted in Insp Rept 50-271/90-06.Corrective Actions:Incident Rept Initiated & All Required Locking Devices in Place by 900706 ML20059F6681990-08-22022 August 1990 Comments on Review of Amend 115 to License DPR-28,including Safety Evaluation.Requests Explanation of Statement in NRC Re How NRC Considers Comments & What Resolution Could Be for Each Util Comment in BVY-90-085, Informs That Sys Testing & Operator Training Successfully Completed & SPDS Declared Operable on 900813.Util Intends to Operate SPDS in Parallel W/Original Honeywell Gepac Plant Computer Until mid-Nov 19901990-08-15015 August 1990 Informs That Sys Testing & Operator Training Successfully Completed & SPDS Declared Operable on 900813.Util Intends to Operate SPDS in Parallel W/Original Honeywell Gepac Plant Computer Until mid-Nov 1990 BVY-90-084, Notifies NRC of Intentions to Install Test Fuel Assemblies & Test Control Blades During Cycle 15 Refueling Outage in Sept 19901990-07-24024 July 1990 Notifies NRC of Intentions to Install Test Fuel Assemblies & Test Control Blades During Cycle 15 Refueling Outage in Sept 1990 BVY-90-082, Informs That Effective 900723 Facility Implemented Rev 4 of Procedure Generating Package & Corresponding Revs to Eops. Revs Developed Per Rev 4 of BWR Owners Group Emergency Procedure Guidelines1990-07-24024 July 1990 Informs That Effective 900723 Facility Implemented Rev 4 of Procedure Generating Package & Corresponding Revs to Eops. Revs Developed Per Rev 4 of BWR Owners Group Emergency Procedure Guidelines BVY-90-071, Forwards Rev 2 to Training & Qualification Plan.Rev Withheld (Ref 10CFR73.21)1990-07-20020 July 1990 Forwards Rev 2 to Training & Qualification Plan.Rev Withheld (Ref 10CFR73.21) BVY-90-078, Forwards List of Refs for Proposed Change 161 to Facility OL & Tech Specs1990-07-17017 July 1990 Forwards List of Refs for Proposed Change 161 to Facility OL & Tech Specs BVY-90-072, Forwards Supplemental Effluent & Waste Disposal Semiannual Rept for Third & Fourth Quarters 1989,Including Annual Radiological Impact on Man for 19891990-06-27027 June 1990 Forwards Supplemental Effluent & Waste Disposal Semiannual Rept for Third & Fourth Quarters 1989,Including Annual Radiological Impact on Man for 1989 ML20043G4351990-06-15015 June 1990 Requests Temporary Waiver of Compliance from Tech Spec Requirements for Limiting Conditions for Operation for Certain post-accident Monitoring Instrumentation Listed in Tech Spec Table 3.2.6.Parameters Listed ML20043E4011990-06-0808 June 1990 Responds to Second Request for Addl Info on Use of RELAP5YA. Explanation Re Why More Accurate View Factor Calculation Not Included in Huxy Code Addressed ML20043C6131990-06-0101 June 1990 Forwards YAEC-1659-A, Simulate-3 Validation & Verification. ML20043C5991990-06-0101 June 1990 Forwards Accepted Version of YAEC-1683-A, MICBURN-3/ CASMO-3/TABLES-3/SIMULATE-3 Benchmarking of Vermont Yankee Cycles 9 Through 13. ML20043C4821990-05-30030 May 1990 Informs of Three Organizational Changes That Will Become Effective on 900601.WP Murphy,Jp Pelletier & DA Reid Will Be Senior Vice President of Operations,Newly Created Vice President of Engineering & Plant Manager,Respectively ML20043B7561990-05-23023 May 1990 Informs That Util Intends to Utilize Relationship Between Frosstey & FROSSTEY-2 to Support Cycle 15 Calculations.Nrc Approval of FROSSTEY-2 Needed by Aug 1990 for LOCA Analysis Program ML20043B6481990-05-17017 May 1990 Forwards Rev 19 to Physical Security Plan.Rev Withheld (Ref 10CFR73.21) BVY-90-058, Forwards Public Version of Vermont Yankee Nuclear Power Station Emergency Response Preparedness Exercise 1990. Exercise Scenario Package Includes All Info Pertinent to Performance of Exercise Scheduled for 9007181990-05-17017 May 1990 Forwards Public Version of Vermont Yankee Nuclear Power Station Emergency Response Preparedness Exercise 1990. Exercise Scenario Package Includes All Info Pertinent to Performance of Exercise Scheduled for 900718 ML20042G9061990-05-10010 May 1990 Forwards Proprietary Supplemental Info to 900419 Response to NRC 900309 Ltr Re FROSSTEY-2 Fuel Performance Code.Info Withheld ML20042F6471990-05-0404 May 1990 Ack That NRC Will Issue Supplementary Info to NRC 900307 Request for Installation of Neutron Flux Monitoring Instrumentation That Conforms to Requirements of Reg Guide 1.97 & 10CFR50.49 at Plant ML20042E7291990-04-23023 April 1990 Forwards Pages Omitted from 900314 Revs 16-18 to Physical Security Plan.Revs Withheld ML20012F3511990-03-30030 March 1990 Provides Supplemental Response to Station Blackout Rule (10CFR50.63).Util Will Use Alternate Ac Power Source Available within 10 Minutes of Onset of Station Blackout to Meet Requirements of Station Blackout Rule ML20012D0301990-03-19019 March 1990 Forwards Response to Generic Ltr 89-19 Re Resolution of USI A-47.Feedwater Sys Trip Relays,Interfacing W/Feedwater Pump Control Circuitry,Powered from Supplies Originating from safety-related Dc Sources ML20012D0241990-03-16016 March 1990 Forwards Supplemental Info Re Feedwater Check Valve V28B Flaws Evaluation,Per NRC Request.Util Remains Committed to Replacement of Subj Valve During Upcoming 1990 Refueling Outage ML20012C6381990-03-15015 March 1990 Forwards Vermont Yankee Nuclear Power Corp Financial Statements 891231,1988 & 1987. ML20012C6071990-03-15015 March 1990 Forwards Method for Generation of One-Dimensional Kinetics Data for RETRAN-02, Per NUREG-0393 & 891211 Request ML20012B8311990-03-0909 March 1990 Forwards Proprietary Vermont Yankee Evaluation Model Sample Problem 0.7 Ft(2) Break in Recirculation Discharge Loop, in Response to 900208 Telcon.Rept Withheld (Ref 10CFR2.790) ML20012B6131990-03-0909 March 1990 Informs of Schedular Changes Made W/Regard to Plant Licensed Operator Requalification Training Program ML20006E8871990-02-15015 February 1990 Provides NRC W/Results of Licensee Review of Design Bases & Operability Status of torus-to-reactor Bldg Vacuum Breakers ML20011E6791990-02-0505 February 1990 Responds to Weaknesses Noted in SALP Rept 50-271/88-99 for Jul 1988 to Sept 1989.Implementation of Emergency Response Facility Info Sys Nearing Completion & Remaining Safety Class Vendor Manuals Will Be Completed During 1990 ML20006D1571990-02-0202 February 1990 Responds to 891226 Request for Addl Info Re YAEC-1683 on MICBURN-3/CASMO-3/TABLES-3/SIMULATE-3 Benchmarking.Hot Eigenvalue Std Deviation on Table 5.7 of YAEC-1683 Reduced to 0.00098 w/SIMULATE-3 ML20006B1351990-01-22022 January 1990 Forwards Responses to Generic Ltr 89-13 Re Svc Water Sys Problems Affecting safety-related Equipment.Establishment of Program Revs Prior to Startup from Next Refueling Outage, Scheduled for Fall 1990,planned ML20006A4441990-01-16016 January 1990 Forwards Revised Page 127 of Tech Specs to Clarify Proposed Change 134, Rev of Pressure Suppression - Reactor Bldg Vacuum Breaker Sys Operability Requirements. Change Involves Adoption of Language Consistent W/Bwr STS ML19354E8001990-01-16016 January 1990 Forwards Addl Info Re Testing of Cable Vault C02 Suppression Sys During 891031-1102,per NRC 890518 & 0821 Requests.Encl Final Test Rept Demonstrates That Carbon Dioxide Sys Will Satisfy Design Bases for Greater than 10 Minutes in Room ML20005G0841990-01-10010 January 1990 Responds to NRC Bulletin 89-002 Re Stress Corrosion Cracking of high-hardness Type 410 Stainless Steel Internal Preloaded Bolting in Anchor Darling Model S350W Swing Check Valves or Valves of Similar Design ML20005E8201990-01-0202 January 1990 Forwards Minutes of NRC 890907 Meeting W/Util in Rockville,Md Re Util LOCA Analysis Program.List of Attendees Also Encl ML20005F0551990-01-0202 January 1990 Informs That Util Has Implemented Fitness for Duty Program, in Compliance w/10CFR26 ML20005E3531989-12-28028 December 1989 Forwards Response to Generic Ltr 89-10 Re safety-related motor-operated Valve Testing & Surveillance.Util Intends to Extend Existing IE Bulletin 85-003 Program to Cover motor- Operated Valves within Scope of Ltr ML20005E3191989-12-28028 December 1989 Responds to Violations Noted in Insp Rept 50-271/89-17 on 890906-1016.Corrective Actions:Plant Procedures Revised & Addl Meetings Between Plant Manager,Dept Supervisors & Personnel to Take Place ML19332G1791989-12-12012 December 1989 Forwards Rev 0 to Vermont Yankee Nuclear Power Station Cycle 14 Core Operating Limits Rept. ML19332F2781989-11-30030 November 1989 Forwards Rev 1 to YAEC-1693, Application of One-Dimensional Kenetics to BWR Transient Analysis Methods, Per 891106 Ltr.Rept Presents Methodology,Verification & Justification for Application of RETRAN-02 One Dimensional Option ML19332E3511989-11-29029 November 1989 Forwards Annual Cashflow Statements for 1989 as Evidence of Util Maint of Approved Guarantee,Per Requirements of 10CFR140.21 Re Licensee Guarantees of Payment of Deferred Premiums ML19332E5281989-11-28028 November 1989 Requests Removal of Change B to Proposed Change 148 Re Rev to Pages 5b & 6a Correcting Administrative Error in Tech Spec 2.1 ML19332D3801989-11-22022 November 1989 Responds to NRC Generic Ltr 89-21 Re Request for Info Re Status of Implementation of USI Requirements.Encl Table Details Implementation Status for USIs for Which Final Technical Resolution Achieved ML19324C1501989-11-10010 November 1989 Responds to NRC Bulletin 88-010,Suppl 1 Re Molded Case Circuit Breakers.Program Initiated to Ensure That Breakers Can Perform Safety Functions ML19324C2201989-11-0606 November 1989 Requests Change in Review & Approval Basis from Facility Specific to Generic Because Methods Described in YAEC-1693 & YAEC-1694 Applicable to All BWRs ML19325F0261989-11-0606 November 1989 Responds to Generic Ltr 89-07, Power Reactor Safeguards Contingency Planning for Surface Vehicle Bombs. Util Has Evaluated Listed Considerations,Including Safe Standoff Distances for Vital Equipment ML19324B7431989-10-30030 October 1989 Responds to Generic Ltr 89-16 Re Installation of Hardened Wetwell Vent.Util Expects to Establish Specific Design Criteria to Install Enhanced Containment Overpressure Protection Capability by End of 1992 Refueling Outage ML19324B8481989-10-30030 October 1989 Provides NRC W/Test Acceptance Criteria for Alternate Test of CO2 Suppression Sys,Per 891025 Meeting.Ability to Contain CO2 at Appropriate Concentration for Required Duration,As Well as Ability to Withstand Dynamics of Discharge,Verified 1990-09-10 |
Text
VERMONT YANKEE NUCLEAR POWER CORPORATION
. RD 5, Box 169, Ferry Road, Brattleboro, VT 05301 V
FVY-E4-86 WLuAu F. CONWAY July 13,1984 ,
PRESIDENT AND CHIEF EyECUTIVE OFFICER (802) 257-5271 U.S. Nuclear Regulatory Commission Washington, D.C. 20555 Attention: Office of Inspection & Enforcement Mr. Richard C. DeYoung, Director
References:
a) License No. DPR-28 (Docket No. 50-271) b) Letter, Richard C. DeYoung to W.F. Conway, dated 5/29/84 c) IE Information Notice 84-30, HVAC Equipment Manufactured by Bahnson Company
Dear Mr. DeYoung:
Subject:
Procurement Quality Assurance and Receipt Inspection Vermont Yankee has addressed the specific concerns of your May 29, 1984 letter in conjunction with our review of Reference c). We have determined that none of the subject units have been supplied to our facility.
Regarding the generic implications of this type of vendor product quality problem, I concur that stringent QA program implementation, including judicious selection of suppliers and perfonnance of receipt inspections, is essential to the prevention and detection of such problems. Vermont Yankee employs a vendor evaluation and procurement document review process which is designed to assess a vendor's ability to provide a quality product and to establish the degree of quality assurance oversight to be applied to the purchase of safety-related items. Furthermore, we require receipt inspection of all safety-related materials and components to ensure that the procurement specifications have been met and that the quality of the items is adequate for the intended service.
8407170264 840713 PDR ADOCK 05000271 PDR Very truly yours, G