Supplemental Response to IE Bulletin 83-06, Nonconforming Matls Supplied by Tube-Line Corp. Improved Receipt Insp Capabilities Will Be Provided by Including Addl Visual Insp Criteria,Training & Alloy Verification
ML20093D259
Person / Time
Site: Harris, Brunswick, Robinson, 05000000
Issue date: 06/01/1984
From: Cutter A
CAROLINA POWER & LIGHT CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
IEB-83-06, IEB-83-6, NLS-84-232, NUDOCS 8407160194
Download: ML20093D259 (2)


Text

+*

Carolina Power & Light Company SERIAL: NLS-84-232

'JU N 1 1984 5

Pl2 : 3 i Mr. James P. O'Reilly, Regional Administrator United States Nuclear Regulatory Commission Suite 2900 101 Marietta Street, NW Atlanta, GA 30303 H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2 DOCKET NO. 50-261/ LICENSE NO. DPR-23 SHEARON HARRIS NUCLEAR POWER PLANT UNIT NO. 1 - DOCKET NO. 50-400 BRUNSWICK STEAM ELECTRIC PLANT, UNIT NOS. 1 AND 2 DOCKET NOS. 50-325 & 50-324/ LICENSE NOS. DPR-71 & DPR-62 SUPPLEMENTAL RESPONSE TO IE BULLETIN No. 83-06

Dear Mr. O'Reilly:

SUMMARY

By letters dated November 18, 1983 (Serial No. LAP-83-531), November 15, 1983 (Serial No. LAP-83-525), and November 18, 1983 (Serial No. LAP-83-533),

Carolina Power & Light Company responded to IE Bulletin 83-06, " Nonconforming Materials Supplied by Tube-Line Corporation Facilities At Long Island City, New York; Houston, Texas; and Carol Stream, Illinois." Carolina Power & Light Company (CP&L) provides the following additional information concerning the status of actions taken in response to the hulletin.

DISCUSSION The general concerns expressed in the bulletin were reviewed for applicability to CP&L, as requested. As part of our review, CP&L investigated the possible use of additional inspection and testing during receipt inspection to strengthen quality assurance capabilities in detection of fraudulently supplied material. In the responses referenced above, CP&L stated it would report the results of the above referenced investigation. A program is scheduled to be implemented during the third quarter of 1984 at each of CP&L's nuclear power plants which will reduce the probability of accepting fraudulent or nonconforming materials (safety-related pipe, pipe fittings, and pipe components) during receipt inspections.

Improved receipt inspection capabilities will be provided by including additional visual inspection',,

criteria and training, alloy verification, and hardness testing.

8407160194 840601 h'

0 PDR ADOCK 05000261 G

PDR

~

r A-Mr. James P. O'Reilly JUtl 3g If you need any additional information regarding this response, please contact Mr. Sherwood R. Zimmerman at (919) 836-6242.

Yours very truly, bNf A h%

A. B. Cutter - Vice President Nuclear Engineering & Licensing WRM/pgp (l42WRM) cc:

Mr. B. C. Buckley (NRC)

Mr. Wells Eddleman Mr. Grotenhuis (NRC)

Dr. Phyllis Lotchin Mr. G. F. Maxwell (NRC-SHNPP)

Mr. G. Requa (NRC)

Mr. D. O. Myers (NRC-BSEP)

Mr. John D. Runkle Mr. Travis Payne (KUDZU)

Mr. S. Weise (NRC-HBR)

Mr. Daniel F. Read (CHANGE /ELP)

Dr. Richard D. Wilson Chapel Hill Public Library Mr. G. O. Bright (ASLB)

Wake County Public Library Dr. J. H. Carpenter (ASLB)

Mr. J. L. Kelley (ASLB)

A. B. Cutter, having been first duly sworn, did depose and say that the information contained herein is true and correct to the best of his information, knowledge and belief; and the sources of his information are officers, employees, contractors, and agents of Carolina Power & Light Company.

Y/A__e MA..

gg"p'8ef,',,

Notary (Seal) f OCT 041936 g