_ _ _
o o
CDCTON EDICON COMPANY e*
B00 BOVLaTON STREET BOSTON MASSACHUSETTS 02199 WILLIAM D. H ARRINGTON sineen viss passeoswt N3 FLEAS May 14, 1984 BECo. #84-070 Mr. Thomas T. Martin Division of Engineering and Technical Programs Region I U.S. Nuclear Regulatory Commission 631 Park Avenue King of Prussia, PA 19406 License No. DPR-35 Docket No. 50-293
Subject:
Combined Inspections 82-02/82-03
Reference:
(a) NRC letter of April 29, 1982 from T. T. Martin to W. D. Harrington (BECo. ltr. 1.82.126)~
(b) Boston Edison letter of May 19, l982 from W. D. Harrington to T. T. Martin (BECo. ltr. 2.82.151)
(c) NRC letter of -January 27, 1983 from T. T. Martin to W. D. Harrington (BECo. ltr. 1.82.013)
(d)BostonCJisonletterofFebruary 22, 1983 from W. D. Harririgton to T. T. Martin (BEco. ltr. 2.83.051)
(e) NRC letter of April 10, 1984 from T. T. Martin to W. D. Harrington (BECo. ltr. 1.84.092) 9
Dear Sir:
In response to Reference (e) dated April 10, 1984 and received by Boston Edison Company on April 14, 1984, the following is offered for your consideration in resolving the open Violation B of the subject combined inspections.
In your request to specifically define our mechanisms for de-termining when safety-related maintenance requires an approved procedure and when such procedure must be reviewed by the Operations Review Committee (0RC), please note that Procedure 1.5.3 (Mainten-ance Requests) contains a prerequisite that all Station maintenanca (with certain exceptions) shall be performed in accordance with l
8407060167 840626
~
PDR ADOCK 05000293
.G PDR
30 TD EECON COMPANY Mr. Thomas T. Martin May 14, 1984 Page Two approved procedures for unplanned maintenance. Procedure 1.5.7 is more explicit in that if an approved procebure does not exist for work activities detennined to be Q, the Chief Maintenance En-gineer, or his designated alternate, shall prepare a procedure and have it approved by the ORC prior to approving the Maintenance Request (MR).
To ensure that these requirements are understood, we will provide clarification to appropriate Station Maintenance personnel to ensure that plans for safety-related work perfonned under an MR which involves approved procedures shall be included (documented) on the' Maintenance Summary and Control Sheet (MSC) or future equivalent.
This will be completed by June 1,1984.
If you have further questions on this matter please contact me.
Very truly yours, William D. Harrington WDH/mg 1