ML20092K367
ML20092K367 | |
Person / Time | |
---|---|
Site: | Waterford ![]() |
Issue date: | 06/22/1984 |
From: | Carus R USX CORP. (FORMERLY UNITED STATES STEEL) |
To: | Deyoung R NRC OFFICE OF INSPECTION & ENFORCEMENT (IE) |
References | |
REF-PT21-84-276-000 PT21-84-276, PT21-84-276-000, NUDOCS 8406280299 | |
Download: ML20092K367 (1) | |
Similar Documents at Waterford | |
---|---|
Category:DEFICIENCY REPORTS (PER 10CFR50.55E & PART 21)
MONTHYEARML20207M9231999-03-12012 March 1999
[Table view]Amended Part 21 Rept Re Cooper-Bessemer Ksv EDG Power Piston Failure.Total of 198 or More Pistons Have Been Measured at Seven Different Sites.All Potentially Defective Pistons Have Been Removed from Svc Based on Encl Results ML18066A2771998-08-13013 August 1998 Part 21 Rept Re Deficiency in CE Current Screening Methodology for Determining Limiting Fuel Assembly for Detailed PWR thermal-hydraulic Sa.Evaluations Were Performed for Affected Plants to Determine Effect of Deficiency ML18065B1351998-01-0606 January 1998 Part 21 Rept Re Use of Deltstrat Code for RCS Flow Rate Determination.Code Corrects for Temps to Determine Hot Leg Bulk Coolant Temp ML20203J2521997-12-0101 December 1997 Deficiency Rept Re Failed Mdr Relays at Entergy Operations Inc,Waterford 3 Nuclear Generation Station.Caused by Contaminated Grease.Housekeeping Procedures Formalized & Added Enclosed Booth Isolating Mdr Final Assembly LD-97-033, Part 21 Rept Re Defect in Potter & Brumfield Mdr Relays, Models 170-1 & 7032.Extended Problem to Include All Mdr Relay Models W/Date Codes 93XX-95XX.Root Cause Analysis, Written Rept & Recommended Corrective Actions Due by 9712011997-11-20020 November 1997 Part 21 Rept Re Defect in Potter & Brumfield Mdr Relays, Models 170-1 & 7032.Extended Problem to Include All Mdr Relay Models W/Date Codes 93XX-95XX.Root Cause Analysis, Written Rept & Recommended Corrective Actions Due by 971201 LD-97-028, Part 21 Rept Re Contamination of Lubricant Which Has Led to Hardening of Lubricant in Certain Potter & Brumfield Mdr Relay Models 170-1 & 7032.Will Distribute Copy of Rept to Utils Having ABB-CE Designed Nuclear Steam Supply Sys1997-10-13013 October 1997 Part 21 Rept Re Contamination of Lubricant Which Has Led to Hardening of Lubricant in Certain Potter & Brumfield Mdr Relay Models 170-1 & 7032.Will Distribute Copy of Rept to Utils Having ABB-CE Designed Nuclear Steam Supply Sys LD-97-024, Part 21 Rept Re Error in Energy Redistribution Factor Used in LOCA Analysis for Listed Plants for Which ABB-CE Performed Analysis.Issued Recommendations Info Bulletin 97-0041997-08-14014 August 1997 Part 21 Rept Re Error in Energy Redistribution Factor Used in LOCA Analysis for Listed Plants for Which ABB-CE Performed Analysis.Issued Recommendations Info Bulletin 97-004 ML20140A9661997-05-29029 May 1997 Part 21 Rept Re Ksv Emergency Diesel Generator Power Piston Failure.Caused by Jacket Water in Combustion Chamber. Recommends That Users Verify That Crown Thickness at Valve Cutout Be 100 Minimum ML18065B0111996-10-18018 October 1996 Part 21 Rept Re Application of Certain Aspects of ABB-CE Safety Analysis Methodology ML20117K9731996-09-10010 September 1996 Follow-up Part 21 Rept of Re Failures of Waterford 3 Dedication Testing Process of Seven Commercial Grade Barksdale Pressure Switches ML20116C7031996-07-29029 July 1996 Part 21 Rept Re Failures Identified by Waterford 3 Dedication Testing Process of 7 Commercial Grade Barksdale Pressure Switches ML20117G4641996-05-14014 May 1996 Part 21 Rept Re Cooper Bessemer Reciprocating Products,Div of Cooper Cameron Corp,Issued Ltr to Define Utils/Plants Containing Similar Equipment as Supplied on Cooper Bessemer Ksv & Enterprise Dsr EDGs LD-96-009, Part 21 Rept Re Potential Instrumentation Decalibr at Low Power.Affected Utils Should Ensure That Log Power Channels Properly Calibr & cross-correlated to Linear Power Channels at 100% Reactor Power1996-04-15015 April 1996 Part 21 Rept Re Potential Instrumentation Decalibr at Low Power.Affected Utils Should Ensure That Log Power Channels Properly Calibr & cross-correlated to Linear Power Channels at 100% Reactor Power ML20077D3431994-11-29029 November 1994 Part 21 Rept Re Suspect Master Connecting Rods & Contains Info Location in Engine for Rods ML20078G3051994-11-0909 November 1994 Rev to Part 21 Rept Re Potential Problem W/Master Power Connecting Rods.Vendor Recommends Listed Utils Perform Visual Insp of Master Rods to Determine Applicability of Rept LD-94-019, Suppl Part 21 Rept Re Notification of Potential Defect in motor-driven Relays Supplied by ABB-CE to Waterford Steam Electric Station Unit 3.Entergy Oparations Aware of Info1994-03-16016 March 1994 Suppl Part 21 Rept Re Notification of Potential Defect in motor-driven Relays Supplied by ABB-CE to Waterford Steam Electric Station Unit 3.Entergy Oparations Aware of Info LD-93-177, Part 21 Rept Re Potter & Brumfield motor-driven Relays Models 7032,7033 & 7034 Supplied by ABB/C-E to Entergy Operations Waterford Steam Electric Station,Unit 3.Eighty- Two Percent of Affected Relays Tested1993-12-23023 December 1993 Part 21 Rept Re Potter & Brumfield motor-driven Relays Models 7032,7033 & 7034 Supplied by ABB/C-E to Entergy Operations Waterford Steam Electric Station,Unit 3.Eighty- Two Percent of Affected Relays Tested LD-93-003, Part 21 Rept Re Defect in Potter & Brumfield Model 170-1 Relay.One of Two Rotor Return Springs Broke & Portion of Spring Lodged Between Rotor & Stator.Rotor Springs Supplied by Lewis Spring Co.Info Bulletin Being Prepared1993-01-13013 January 1993 Part 21 Rept Re Defect in Potter & Brumfield Model 170-1 Relay.One of Two Rotor Return Springs Broke & Portion of Spring Lodged Between Rotor & Stator.Rotor Springs Supplied by Lewis Spring Co.Info Bulletin Being Prepared ML20126J5961992-12-31031 December 1992 Part 21 Rept Re Potential Loss of RHR Cooling During Nozzle Dam Removal.Nozzle Dams May Create Trapped Air Column Behind Cold Leg Nozzle Dam.Mod to Nozzle Dams Currently Underway. Ltrs to Affected Utils Encl ML20125C7161992-12-0707 December 1992 Part 21 Rept Re Possibility for Malfunction of Declutching Mechanisms in SMB/SB-000 & SMB/SB/SBD-00 Actuators. Malfunction Only Occurs During Seismic Event.Balanced Levers May Be Purchased from Vendor.List of Affected Utils Encl ML20127M5201992-11-24024 November 1992 Final Part 21 Rept Re Reject Lot Serial Numbers of Defective Fuel Nozzle Tips,Consisting of Corrected Page 6 of 921102 Rept Re Reject Lots for Fuel Injector Assembly ML20127P5861992-11-23023 November 1992 Followup to 921005 Part 21 Rept Re Potential Defect in SB/SBD-1 Housing Cover Screws.Procedure Re Replacement of SBD-1 Spring Cover Bolts Encl.All Fasteners Should Be Loosened & Removed.List of Affected Utils Encl ML20115D6331992-10-15015 October 1992 Part 21 Rept Re Nuclear Logistics Inc 10CFR21 Notification for Gnb Industrial Battery Co Batteries.Util Will Obtain Replacement Batteries from C&D Power Sys,Inc & Alarm Features to Be Tested by End of Refuel 5 ML20118B4391992-09-11011 September 1992 Part 21 Rept Re Degradation in Abb Type 27N Undervoltage Relays Used in Electrical Switchgear.Recommends That Users Review Applications Requiring Exposures Greater than 1E03 Rads TID W/Time Delay Function Option ML20101Q9311992-07-0808 July 1992 Part 21 Rept Re Failure to Comply w/1 Minute Rating of NCX-17 Cells Mfg by Gnb Battery Co (Formally Gould).Addl Testing of Cell Sizes & End Voltages Scheduled to Begin on 920713 & Be Completed on 920815 L-91-002, Supplemental Part 21 Rept Re GE Reactor Trip Breakers Used in safety-grade Equipment.Initially Reported on 901228.List of Plants Supplied w/C-E Breakers Encl1991-01-0404 January 1991 Supplemental Part 21 Rept Re GE Reactor Trip Breakers Used in safety-grade Equipment.Initially Reported on 901228.List of Plants Supplied w/C-E Breakers Encl ML17223A7451990-01-26026 January 1990 Part 21 Rept Re Backup Rings Furnished in Spare Parts Seal Kits & in 25 Gpm 4 Way Valves as Part of Actuators Made of Incorrect Matl.Rings Should Be Viton & Have Been Identified as Buna N ML20246P7111989-07-17017 July 1989 Part 21 Rept Re Quench Cracks in Bar of A-SA-193 Grade B7 Component.Quench Cracks Found in One Bar of Matl.Listed Purchasers Informed of Potential Defect.Next Rept Will Be Submitted When Addl Info Becomes Available ML20247P7991989-04-0404 April 1989 Part 21 Rept Re Atmospheric Dump Valves.Cause of Failure Speculative But Result of Piston Ring That Failed to Seal. Resolution to Problem Requires Increasing Pilot Valve Capacity & Reworking of Plug to Enlarge Pilot Flow Area ML20234C7351987-06-23023 June 1987 Supplemental Part 21 Rept Re Silicone Foam Seal Anomolies at Wolf Creek Generating Station ML20211P7211987-02-23023 February 1987 Part 21 Rept Re Rockbestos Coaxial Cable Used in Sorrento Electronics Digital & Analog high-range Radiation Monitor. Insulation Resistance at High Temp Not High Enough for Ion Chamber & Associated Electronics to Operate Properly ML20215G6801986-10-10010 October 1986 Part 21 Rept Re Vendor Tests of air-operated Diaphragm Valves Revealing Natural Frequencies Less than Required Values of 33 Hz.Initially Reported on 841227.No Adverse Effects Noted During Testing ML20215G5351986-10-10010 October 1986 Part 21 Rept Re Vendor Tests of air-operated Diaphragm Valves Revealing Natural Frequencies Less than Required Values of 33 Hz.Initially Reported on 841227.No Adverse Effects Noted During Testing ML20153D8861986-02-17017 February 1986 Part 21 Rept Re Failure of Penetration & Conduit Seal Configurations During Fire Tests.Initially Reported on 860214.Evaluation of Number & Location of Defective Seals in Progress.Nrc Assistance Requested ML20140A5281985-12-19019 December 1985 Part 21 Rept Forwarding Ltr Sent to Customers Re Check Valves Missing Lock Welds on Hinge Supports or Hinge Support Capscrews,Per 851121 Request.List of Customers Receiving Ltr Also Encl ML20135E1161985-09-0505 September 1985 Part 21 Rept Re Use of Connectron non-IEEE Qualified Matl in Spare Part Terminal Blocks Supplied to Facilities. Appropriate Customers Notified.Terminal Blocks Should Be Reviewed to Identify Defective Matl W3P85-1442, Final Potentially Reportable Deficiency Rept 180 Re Failure to Maintain Adequate Control of Vendor Manuals.Initially Reported on 840918.Preventive Maint Program Implemented.Item Not Reportable Per 10CFR50.55(e)1985-08-0101 August 1985 Final Potentially Reportable Deficiency Rept 180 Re Failure to Maintain Adequate Control of Vendor Manuals.Initially Reported on 840918.Preventive Maint Program Implemented.Item Not Reportable Per 10CFR50.55(e) ML20133G9741985-07-31031 July 1985 Part 21 Rept Re Anchor/Darling Valve Co Swing Check Valves W/Loose Set Screws &/Or Missing Lock Welds,Reported by Palo Verde Nuclear Generating Station.All Customers W/Similar Valves Notified.Ltr Re Waterford 3 Valves Encl W3P85-1420, Potentially Reportable Deficiency Rept PRD-180 Re Failure to Maintain Adequate Document Control of Vendor Manuals. Initially Reported on 840918.Submittal of Written Rept on Deficiency Rescheduled for 8508011985-06-27027 June 1985 Potentially Reportable Deficiency Rept PRD-180 Re Failure to Maintain Adequate Document Control of Vendor Manuals. Initially Reported on 840918.Submittal of Written Rept on Deficiency Rescheduled for 850801 W3P85-1400, Potentially Reportable Deficiency 180 Re Failure to Maintain Adequate Document Control of Vendor Manuals.Initially Reported on 840918.Addl Time Needed to Evaluate Deficiency. Next Rept Will Be Submitted by 8507011985-05-29029 May 1985 Potentially Reportable Deficiency 180 Re Failure to Maintain Adequate Document Control of Vendor Manuals.Initially Reported on 840918.Addl Time Needed to Evaluate Deficiency. Next Rept Will Be Submitted by 850701 ML20128G5101985-05-24024 May 1985 Part 21 Rept Re Heat Numbers to Be Added & Deleted from Sublist Sheet A,Based on Review of NRC W3P85-1240, Potentially Reportable Deficiency Rept PRD-180 Re Failure to Maintain Adequate Document Control of Vendor Manuals. Initially Reported on 840918.Written Rept Submittal Date Extended Until 8505311985-04-29029 April 1985 Potentially Reportable Deficiency Rept PRD-180 Re Failure to Maintain Adequate Document Control of Vendor Manuals. Initially Reported on 840918.Written Rept Submittal Date Extended Until 850531 W3P85-0785, Interim Deficiency Rept 180 Re Failure to Maintain Adequate Document Control of Vendor Manuals.Initially Reported on 840918.Addl Time to Evaluate Safety Significance Required. Submittal of Written Rept Rescheduled for 8504301985-03-25025 March 1985 Interim Deficiency Rept 180 Re Failure to Maintain Adequate Document Control of Vendor Manuals.Initially Reported on 840918.Addl Time to Evaluate Safety Significance Required. Submittal of Written Rept Rescheduled for 850430 W3P85-0551, Significant Const Deficiency Rept 93 Re Charging & Letdown Containment Isolation Valve.Potential Exists for Valve to Stick Open Due to Thermal Contraction.Testing Under Temp Conditions Being Performed1985-03-0606 March 1985 Significant Const Deficiency Rept 93 Re Charging & Letdown Containment Isolation Valve.Potential Exists for Valve to Stick Open Due to Thermal Contraction.Testing Under Temp Conditions Being Performed W3P85-0544, Supplemental Final Significant Const Deficiency 93 Re Failure of Containment Isolation Valve CVC-103 to Close After Plant Cooldown.Details Will Be Provided on Valve Failure When Info Obtained1985-02-27027 February 1985 Supplemental Final Significant Const Deficiency 93 Re Failure of Containment Isolation Valve CVC-103 to Close After Plant Cooldown.Details Will Be Provided on Valve Failure When Info Obtained W3P85-0509, Interim Rept of Potentially Reportable Deficiency 180 Re Failure to Maintain Adequate Document Control of Vendor Manuals.Initially Reported on 840918.Addl Time to Evaluate Safety Significance Needed.Next Rept Delayed Until 8503291985-02-26026 February 1985 Interim Rept of Potentially Reportable Deficiency 180 Re Failure to Maintain Adequate Document Control of Vendor Manuals.Initially Reported on 840918.Addl Time to Evaluate Safety Significance Needed.Next Rept Delayed Until 850329 W3P85-0337, Final Significant Const Deficiency Rept SCD-80 Re Unsatisfactory Stroking of Emergency Feedwater Pump Turbine Steam Supply shut-off Valves.Pneumatic Operators for Valves 2MS-V611A & V612 Replaced w/D-C Motors1985-02-22022 February 1985 Final Significant Const Deficiency Rept SCD-80 Re Unsatisfactory Stroking of Emergency Feedwater Pump Turbine Steam Supply shut-off Valves.Pneumatic Operators for Valves 2MS-V611A & V612 Replaced w/D-C Motors W3P85-0339, Final Significant Const Deficiency Rept SCD-93 Re Charging & Letdown Containment Isolation Valve Deficiency.Vendor Repaired Valve W/New Seats Sized for Max Interference Fit1985-02-21021 February 1985 Final Significant Const Deficiency Rept SCD-93 Re Charging & Letdown Containment Isolation Valve Deficiency.Vendor Repaired Valve W/New Seats Sized for Max Interference Fit W3P85-0338, Final Part 21 & Const Deficiency Rept SCD-37 Re Unreliable Temp Signals from Resistance Temp Detectors (Rtd).Initially Reported on 810710.Safety-related RTDs Replaced or Environmentally Sealed.Design Change Notice Issued1985-02-21021 February 1985 Final Part 21 & Const Deficiency Rept SCD-37 Re Unreliable Temp Signals from Resistance Temp Detectors (Rtd).Initially Reported on 810710.Safety-related RTDs Replaced or Environmentally Sealed.Design Change Notice Issued W3P85-0083, Deficiency Rept PRD-180 Re Failure to Maintain Adequate Document Control of Vendor Manuals.Initially Reported on 840918.Safety-related & Environmentally Qualified Equipment Manuals to Be Reviewed.Next Rept Anticipated by 8502281985-01-14014 January 1985 Deficiency Rept PRD-180 Re Failure to Maintain Adequate Document Control of Vendor Manuals.Initially Reported on 840918.Safety-related & Environmentally Qualified Equipment Manuals to Be Reviewed.Next Rept Anticipated by 850228 1999-03-12 Category:INCOMING CORRESPONDENCE MONTHYEARML20217L0101999-10-18018 October 1999
[Table view]Provides Update of Waterford 3 Effort for Review of Ufsar. Info Listed Includes Background Mgt Expectations,Review Status & Results,Clarifications Re Review & Conclusions ML20217L0141999-10-18018 October 1999 Submits Update to NRC Staff Re Circumstances & Plans for Submitting Certification Rept on Waterford 3 Plant Specific Simulator ML20217G7051999-10-14014 October 1999 Forwards Comments on Four of NRC RO Examination Questions for Exam Administered During Week of 991004 05000382/LER-1999-014, Forwards LER 99-014-00,providing Details of Reactor Shutdown Due to Loss of RCP Controlled bleed-off Flow.Attached Commitment Identification/Voluntary Enhancement Form Identifies All Commitments Contained in Submittal1999-10-12012 October 1999 Forwards LER 99-014-00,providing Details of Reactor Shutdown Due to Loss of RCP Controlled bleed-off Flow.Attached Commitment Identification/Voluntary Enhancement Form Identifies All Commitments Contained in Submittal ML20217D5151999-10-0707 October 1999 Forwards Application for Renewal of SRO License for C Fugate License SOP-43039-3,IAW 10CFR55.57.Without Encls 05000382/LER-1999-013, Forwards LER 99-013-00,providing Details of Exceeding TS Limits for RCS Cooldown Rates.All Commitments Contained in Submittal Are Identified on Encl Commitment Identification/ Voluntary Enhancement Form1999-09-23023 September 1999 Forwards LER 99-013-00,providing Details of Exceeding TS Limits for RCS Cooldown Rates.All Commitments Contained in Submittal Are Identified on Encl Commitment Identification/ Voluntary Enhancement Form ML20212C2391999-09-16016 September 1999 Requests Cancellation of SRO Licenses for Bn Coble,License SOP-43835,due to Job Assignment Location & CA Rodgers, License SOP-43537-1,due to Resignation from Company, Effective 990901 ML20212C2471999-09-16016 September 1999 Forwards Five Final Applications for RO Licenses for G Esquival,Jm Hearn,Md Lawson,Re Simpson & PI Wood.Written Exam & Operating Test to Be Administered,Is Requested. Encls Withheld ML20211P4121999-09-0707 September 1999 Requests NRC Staff Review & Approval of Integrated Nuclear Security Plan (Insp) & Integrated Security Training & Qualification Plan (Ist&Q), for Use by All Entergy Operations,Inc.Encl Withheld,Per 10CFR2.790(d) ML20211M8391999-09-0303 September 1999 Forwards Revised Epips,Including Rev 25 to EP-001-020,rev 24 to EP-001-030,rev 25 to EP-001-040,rev 30 to EP-002-100,rev 22 to EP-001-010,rev 27 to EP-002-010,rev 26 to EP-002-102 & Rev 16 to EP-002-190.Listed Proprietary Revs to Epips,Encl ML20211L3681999-09-0202 September 1999 Forwards Five Preliminary Applications for Reactor Operator Licenses for Individuals Listed,Iaw 10CFR55.31.Encls Withheld 05000382/LER-1999-011, Forwards LER 99-011-00,providing Details of Reactor Shutdown Due to Loss of Controlled bleed-off Flow.All Commitments Contained in Submittal Identified on Attached Commitment Identification/Voluntary Enhancement Form1999-08-31031 August 1999 Forwards LER 99-011-00,providing Details of Reactor Shutdown Due to Loss of Controlled bleed-off Flow.All Commitments Contained in Submittal Identified on Attached Commitment Identification/Voluntary Enhancement Form ML20211M3641999-08-30030 August 1999 Forwards Written Examination,Operating Tests & Supporting Ref Matl Identified in Attachment 2 of ES-210,in Response to NRC .Encl Withheld ML20211E3281999-08-26026 August 1999 Forwards fitness-for-duty Performance Data for Period of 990101-0630,IAW 10CFR26.71(d).Ltr Does Not Contain Commitments 05000382/LER-1999-010, Forwards LER 99-010-00,providing Details of Inadequate Pumping Capacity in Dry Cooling Tower Area.All Commitments Contained in Submittal Are Identified on Attached Commitment Identification Voluntary Enhancement Form1999-08-26026 August 1999 Forwards LER 99-010-00,providing Details of Inadequate Pumping Capacity in Dry Cooling Tower Area.All Commitments Contained in Submittal Are Identified on Attached Commitment Identification Voluntary Enhancement Form 05000382/LER-1999-009, Forwards LER 99-009-00 Re Discovery of Condition of Noncompliance with App R Involving Inadequate Separation of Essential Cables Routed in Fire Area RAB-30 in Rab. Compensatory Measures Were Established Immediately1999-08-26026 August 1999 Forwards LER 99-009-00 Re Discovery of Condition of Noncompliance with App R Involving Inadequate Separation of Essential Cables Routed in Fire Area RAB-30 in Rab. Compensatory Measures Were Established Immediately ML20211F3561999-08-24024 August 1999 Forwards CTS Pages & TS Proposed marked-up Pages for Insertion Into TS Change Request NPF-38-207 Re Efas, Originally Submitted on 980702.Original NSHC Determination Continues to Be Applicable ML20211F5421999-08-24024 August 1999 Forwards Proposed marked-up TS Page Xviii, Index Administrative Controls, Correcting Page Number Re TS Change Request NPF-38-220.Editorial Changes for TS Change NPF-38-221 Discussed ML20211C5101999-08-19019 August 1999 Forwards Certified Copies of Liability Insurance Policy Endorsements Issued in First Half of 1999 for Each Entergy Operations,Inc Nuclear Unit,Per 10CFR140.15 ML20210Q6161999-08-12012 August 1999 Forwards Corrected Copy of Monthly Operating Rept for July 1999 for Waterford 3.Original Rept,Submitted with ,Contained Typos ML20210S0561999-08-12012 August 1999 Submits Voluntary Response to NRC AL 99-02, Operating Reactor Licensing Action Estimates, for NRC Fys 2000 & 2001 for Waterford 3 ML20217F2661999-08-12012 August 1999 Forwards Copy of 1999 Waterford 3 Biennial Exercise Package to Be Performed Using Waterford 3 CR Simulator 05000382/LER-1999-008, Forwards LER 99-008-00,re Failure to Perform Testing of ESF Filtration Units Per TS Srs.Commitments Made by Util Also Encl1999-07-29029 July 1999 Forwards LER 99-008-00,re Failure to Perform Testing of ESF Filtration Units Per TS Srs.Commitments Made by Util Also Encl ML20210H4291999-07-29029 July 1999 Forwards Response to NRC Rai,Associated with TS Change Request NPF-38-208,proposing to Replace Ref to Supplement 1 with Ref to Supplement 2 of Calculative Methods for CE Small Break LOCA Evaluation Model, in ACs Section of TSs ML20210F9451999-07-27027 July 1999 Forwards Proprietary & non-proprietary Version of Rev 29 to EPIP EP-002-100, Technical Support Ctr Activation,Operation & Deactivation. Proprietary Info Withheld,Per 10CFR2.790 ML20210D3171999-07-23023 July 1999 Submits Proposal for Final Resolution of Reracking Spent Fuel Pool at Plant,Per License Amend 144,issued by NRC in .No New Commitments Are Contained in Ltr 05000382/LER-1999-007, Forwards LER 99-007-00,providing Details of Operation Outside Tornado Missile Protection Licensing Basis for turbine-driven Emergency Feedwater Pump Exhaust Stack & Steam Supply Piping.All Commitments Identified on Attached1999-07-23023 July 1999 Forwards LER 99-007-00,providing Details of Operation Outside Tornado Missile Protection Licensing Basis for turbine-driven Emergency Feedwater Pump Exhaust Stack & Steam Supply Piping.All Commitments Identified on Attached ML20209G9771999-07-13013 July 1999 Forwards Objectives & Guidelines for Waterford 3 Emergency Preparedness Exercise Scheduled for 991013.List of Objectives cross-referenced Where Applicable to Relevant Sections of NUREG-0654 ML20209D4051999-07-0707 July 1999 Forwards Revised TS Pages to Replace Attachment C,Entirely in Original TS Change Request NPF-38-207,per 990519 Discussion with C Patel of Nrc.Changes to Action 20 Delete Word Requirement & Revise Word Modes to Mode ML20209B6081999-06-30030 June 1999 Submits Response to NRC GL 98-01,Suppl 1, Y2K Readiness of Computer Sys at Nuclear Power Plants. Disclosure Encl 05000382/LER-1999-005, Forwards LER 99-005-00,providing Details of Discovery of Untested Electrical Contacts in safety-related Logic Circuits1999-06-24024 June 1999 Forwards LER 99-005-00,providing Details of Discovery of Untested Electrical Contacts in safety-related Logic Circuits ML20196G5731999-06-24024 June 1999 Forwards Operator Licensing Exam Outlines Associated with Exam Scheduled for Wk of 991004.Exam Development Is Being Performed in Accordance with NUREG-1021,Rev 8 ML20212J4121999-06-23023 June 1999 Responds to NRC Re Reconsideration of EA 98-022. Details Provided on Actions Util Has Taken or Plans to Take to Address NRC Concerns with Ability to Demonstrate Adequate Flow Availability to Meet Design Requirements ML20196E9371999-06-22022 June 1999 Forwards Revs Made to EP Training Procedures.Procedures NTC-217 & NTC-217 Have Been Deleted.Procedure NTP-203 Was Revised to Combine Requirement Previously Included in Procedures NRC-216 & NTC-217 ML20196A1021999-06-17017 June 1999 Provides Supplemental Response to GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves, Per 990513 Request of NRC Project Manager ML20195F3671999-06-0909 June 1999 Forwards Rev 21,Change 0 to EP-001-010, Unusual Event. Rev Reviewed in Accordance with 10CFR50.54(q) Requirements & Determined Not to Decrease Effectiveness of Emergency Plan ML20195C7801999-06-0303 June 1999 Submits Response to Violations Noted in Insp Rept 50-382/99-08.Corrective Actions:All Licensee Access Authorization Personnel Were Retrained Prior to Completion of Insp ML20195C2951999-05-28028 May 1999 Forwards Annual Evaluation of Changes & Errors Identified in Abb CE ECCS Performance Evaluation Models Used for LOCA Analyses.Results of Annual Evaluation for CY98 Detailed in Attached Rept,Based Upon Suppl 10 to Abb CE Rept ML20195C0241999-05-28028 May 1999 Notifies NRC of Operator Medical Condition for Waterford 3 Opertaor Sp Wolfe,License SOP-43723.Attached NRC Form & Memo Contain Info Concerning Condition.Without Encls ML20196L3281999-05-24024 May 1999 Informs That Entergy Is Withdrawing TS Change Request NPF-38-205 Re TS 3.3.3.7.1, Chlorine Detection Sys & TS 3.3.3.7.3, Broad Range Gas Detection Submitted on 980629 ML20206S4691999-05-17017 May 1999 Requests Waiver of Exam for SRO Licenses for an Vest & Hj Lewis,Iaw 10CFR55.47.Both Individuals Have Held Licenses at Plant within Past Two Year Period,But Licenses Expired Upon Leaving Util Employment.Encl Withheld 05000382/LER-1999-004, Forwards LER 99-004-00 Re Discovery That Response Time Testing Had Not Been Performed for ESFAS Containment Cooling Function,As Required by TS SR 4.3.2.31999-05-14014 May 1999 Forwards LER 99-004-00 Re Discovery That Response Time Testing Had Not Been Performed for ESFAS Containment Cooling Function,As Required by TS SR 4.3.2.3 ML20206N1921999-05-10010 May 1999 Provides Revised Attachment 2 for Alternative Request IWE-02,originally Submitted 990429 Re Bolt Torque or Tension Testing of Class Mc pressure-retaining Bolting as Specified in Item 8.20 of Article IWE-2500,Table IWE-2500-1 ML20206J1471999-05-0606 May 1999 Requests That Implementation Date for TS Change Request NPF-38-211 Be within 90 Days of Approval to Allow for Installation of New Monitoring Sys for Broad Range Gas Detection Sys ML20206J1721999-05-0606 May 1999 Notifies That Proposed Schedule for Plant 1999 Annual Exercise Is Wk of 991013.Exercise Objective Meeting Scheduled for 990513 at St John Baptist Parish Emergency Operations Ctr ML20206G8021999-05-0404 May 1999 Provides Revised Response to NRC Re Violations Noted in Insp Rept 50-382/99-01.Licensee Denies Violation as Stated.Change Made Is Denoted by Rev Bar & Does Not Materially Impact Original Ltr ML20206E7811999-04-29029 April 1999 Proposes Alternatives to Requirements of ASME B&PV Code Section XI,1992 Edition,1992 Addenda,As Listed.Approval of Alternative Request on or Before 990915,requested ML20205T2531999-04-22022 April 1999 Forwards LER 99-S02-00,describing Occurrence of Contract Employee Inappropriately Being Granted Unescorted Access to Plant Protected Area ML20205R2611999-04-20020 April 1999 Forwards Rev 19 to Physical Security Plan,Submitted in Accordance with 10CFR50.54(p).Plan Rev Was Approved & Implemented on 990407.Rev Withheld,Per 10CFR73.21 ML20205Q3241999-04-16016 April 1999 Submits Addl Info Re TS Change Request NPF-38-215 for Administrative Controls TS Changes.Appropriate Pages from New Entergy Common QA Program Manual Provided as Attachment to Ltr 1999-09-07 Category:TEXT-SAFETY REPORT MONTHYEARML20217F2891999-10-13013 October 1999
[Table view]Drill 99-08 Emergency Preparedness Exercise on 991013 ML20217G7211999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Waterford 3 Ses. with ML20211Q2141999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Waterord 3 Ses.With ML20210Q6361999-07-31031 July 1999 Corrected Monthly Operating Rept for July 1999 for Waterford 3 ML20210S0581999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Waterford 3.With ML20210D8951999-07-23023 July 1999 Safety Evaluation Accepting First 10-yr Interval Inservice Insp Plan Requests for Relief ISI-018 - ISI-020 ML20209H3781999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Waterford 3 Ses. with ML20195J8951999-06-17017 June 1999 Safety Evaluation Granting Relief for Listed ISI Parts for Current Interval,Per 10CFR50.55a(g)(5)(iii) ML20207E8631999-06-0303 June 1999 Safety Evaluation Accepting Licensee 990114 Submittal of one-time Request for Relief from ASME B&PV Code IST Requirements for Pressure Safety Valves at Plant,Unit 3 ML20195K3391999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Waterford 3 Ses.With ML20195C3041999-05-28028 May 1999 Annual Rept on Abb CE ECCS Performance Evaluation Models ML20206S7401999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Waterford 3.With ML20205T2621999-04-22022 April 1999 LER 99-S02-00:on 990216,contract Employee Inappropriately Granted Unescorted Access to Plant Protected Area.Caused by Personnel Error.Security Personnel Performed Review of Work & Work Area That Individual Was Involved with ML20205N9671999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Waterford 3 Ses.With ML20205E8531999-03-30030 March 1999 Corrected Pages COLR 3/4 1-4 & COLR 3/4 2-6 to Rev 1, Cycle 10, Colr ML20205A6331999-03-25025 March 1999 SER Accepting Request to Use Mechanical Nozzle Seal Assemblies as an Alternative Repair Method,Per 10CFR50.55a(a)(3)(i) for Reactor Coolant Sys Applications at Plant,Unit 3 ML20204H1401999-03-23023 March 1999 Rev 1 to Engineering Rept C-NOME-ER-0120, Design Evaluation of Various Applications at Waterford Unit 3 ML20204H1231999-03-22022 March 1999 Rev 1 to Design Rept C-PENG-DR-006, Addendum to Cenc Rept 1444 Analytical Rept for Waterford Unit 3 Piping ML20204H2451999-03-22022 March 1999 Rev 2 to C-NOME-SP-0067, Design Specification for Mechanical Nozzle Seal Assembly (Mnsa) Waterford Unit 3 ML20204F0791999-03-17017 March 1999 Rev 1 to Waterford 3 COLR for Cycle 10 ML20207M9231999-03-12012 March 1999 Amended Part 21 Rept Re Cooper-Bessemer Ksv EDG Power Piston Failure.Total of 198 or More Pistons Have Been Measured at Seven Different Sites.All Potentially Defective Pistons Have Been Removed from Svc Based on Encl Results ML20207F3491999-03-0505 March 1999 LER 99-S01-00:on 990203,contraband Was Discovered in Plant Protected Area.Bottle Was Determined to Have Been There Since Original Plant Construction.Bottle Was Removed & Security Personnel Performed Search of Area.With ML20204B5141999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Waterford 3.With ML20203H8591999-02-17017 February 1999 Safety Evaluation Accepting Licensee Second Ten Year ISI Program & Associated Relief Requests for Plant,Unit 3 ML20199H6261999-01-21021 January 1999 Safety Evaluation Accepting Classification of Instrument Air Tubing & Components for Safety Related Valve Top Works.Staff Recommends That EOI Revise Licensing Basis to Permit Incorporation of Change ML20199C9101998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for Waterford 3.With ML20196F4911998-12-0101 December 1998 SER Accepting Request for Relief ISI2-09 for Waterford Steam Electric Station,Unit 3 & Arkansas Nuclear One,Unit 2 ML20206N4131998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Waterford 3.With ML20195C4841998-11-0606 November 1998 SER Accepting QA Program Change to Consolidate Four Existing QA Programs for Arkansas Nuclear One,Grand Gulf Nuclear Station,River Bend Station & Waterford 3 Steam Electric Station Into Single QA Program ML20195E5161998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Waterford 3.With ML20155C1351998-10-26026 October 1998 Rev B to Entergy QA Program Manual ML20154K0801998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for Waterford 3 Ses. with ML20151W8331998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for Waterford,Unit 3. with ML20237B6831998-08-17017 August 1998 LER 98-S01-00:on 980723,discovered That Waterford 3 Physical Security Plan,Safeguards Document Was Not Under Positive Control of Authorized Person at All Times.Caused by Human Error/Inappropriate Action.Counseled Employee Involved ML20237C5661998-08-17017 August 1998 Safety Evaluation Accepting Licensee Request for Exemption from Section Iii.O of Appendix R to 10CFR50 ML18066A2771998-08-13013 August 1998 Part 21 Rept Re Deficiency in CE Current Screening Methodology for Determining Limiting Fuel Assembly for Detailed PWR thermal-hydraulic Sa.Evaluations Were Performed for Affected Plants to Determine Effect of Deficiency ML20237B5261998-07-31031 July 1998 Monthly Operating Rept for July 1998 for Waterford 3 ML20236S9031998-07-22022 July 1998 SER Accepting Rev 19 to Quality Assurance Program for Waterford Steam Electric Station,Unit 3 ML20198H3911998-07-14014 July 1998 Non-proprietary Rev 5 to HI-961586, Thermal-Hydraulic Analysis of Waterford-3 Spent Fuel Pool ML20236N4181998-06-30030 June 1998 Monthly Operating Rept for June 1998 for Waterford,Unit 3 ML20248E7781998-06-0101 June 1998 Annual Rept on Abb CE ECCS Performance Evaluation Models ML20249A4711998-05-31031 May 1998 Monthly Operating Rept for May 1998 for Waterford 3 Ses ML20196A4051998-05-31031 May 1998 Rept of Facility Changes,Tests & Experiments,Per 10CFR50.59 for 970601-980531. with ML20198H4681998-05-20020 May 1998 Non-proprietary Rev 1 to HI-981942, Independent Review of Waterford Unit 3 Spent Fuel Pool Cfd Model ML20247A3891998-05-0101 May 1998 SG Eddy Current Examination (8th Refueling Outage) ML20247F6761998-04-30030 April 1998 Monthly Operating Rept for Apr 1998 for Waterford,Unit 3.W/ ML20217M8951998-04-30030 April 1998 QA Program Manual ML20217P8281998-04-0707 April 1998 Safety Evaluation Accepting Relief Authorization for Alternative to Requirements of ASME Section Xi,Subarticle IWA-5250 Bolting Exam for Plants,Per 10CFR50.55a(a)(3)(i) ML20216B1751998-03-31031 March 1998 Monthly Operating Rept for Mar 1998 for Waterford 3 Ses ML20217M1411998-03-0303 March 1998 Rev 2 of Waterford 3 Cycle 9 Colr 1999-09-30 |
Text
i-American uss Bn.dge Division of United States Steel Corporation AIRPORT OFFICE PARK - BUILDING 3 420 ROUSER RO AD COR AOPOLIS, PENNSYLV ANI A MAIL: POST OFFICE BOX 2039 PITTSBURGH, PENNSYLV ANI A 15230 TELEX 866425 US STEE L PGH.
June 22, 1984 ME. Ric,hard C. DeYoung, Director Office of Inspection and Enforcement United States Nuclear Regulatory Commission Washington, D.-C. 20555 Re: Nuclear Regulatory Commission Docket 50-382 Construction Appraisal Team Inspection 50-382/84-07 May 14, 1984
Dear Sir:
American Bridge Division, United States Steel Corporqtion has reviewed the above-referenced report concerning Waterford SES Unit 3 Nuclear Plant which contains certain allegations regarding deficient shopwelds purportedly fabricated by American Bridge's subcontractor, Peden Steel.
These allegations are totally without justification with respect to American Bridge. American Bridge had no contractual or subcontractual agreement whatsoever with Peden Steel which dealt- directly with Louisiana Power and Light and Ebasco. ~Those parties, and not American Bridge, are responsible for the quality of the structural steel shopwelds and any necessary corrective action.
In order to avoid further damage to American Bridge, we hereby request that any reference to Peden Steel as our subcontractor and any language suggesting that we are thereby responsible for their problems be deleted from Inspection 50-382/84-07 as soon a',possible. Problems asso-ciated with Pederi and shopwelds should be evaluated separately from any discussion of American Bridge's erection, field welding, and bolting activities as noted in such report.
Your prompt attention to this matter is appreciated.
Yours very truly, Richard V. Carus General Manager-Contracting RVC:mb B406280299 840622 PDR ADOCK 05000382 IIO