ML20092F382

From kanterella
Jump to navigation Jump to search
Application for Amend to License NPF-2 & NPF-8,eliminating Periodic Pressure Sensor Response Time Testing Requirements
ML20092F382
Person / Time
Site: Farley  Southern Nuclear icon.png
Issue date: 09/15/1995
From: Dennis Morey
SOUTHERN NUCLEAR OPERATING CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20092F385 List:
References
NUDOCS 9509180162
Download: ML20092F382 (1)


Text

Southern Nuctxt Op; rating Company e, i. Post Oftes Box 1295 Birmingham. Alabima 35201 Telephone (205) 868 5131 .

, l

. L l o.ve uorey Southern Nudear Operating Company .

Vice President Farley Project the southern electnc system September 15, 1995 Docket Nos: 50-348 50-364 10 CFR 50.90 i

U. S. Nuclear Regulatory Commission ATrN: Document Control Desk i Washington, DC 20555 1 Joseph M. Farley Nuclear Plant Technical Specifications Change Request ,

Elimination of Periodic Pressure Sensor Response Time Testina Reauirements l l

I Ladies and Gentlemen:

Dy letter dated August 17,1994, Southern Nuciar Operating Company (SNC) proposed changes to the Farley Unit I and Unit 2 Technical Specifications to climinate periodic pressure sensor response time testing requirements. SNC letter dated June 15,1995 provided supplemental infomtation as requested by NRC letter dated April 17,1995. SNC letter dated August i1,1995 transmitted Westinghouse WCAP-13632, Revision 2, " Elimination of Pressure Sensor Response Time Testing Requirements," which included the Foxboro E13DH similarity analysis, priority information clarifications, and the text enhancements discussed in our supplemental response. This letter provides updated Technical Specifications Bases page B3/4 3-2 for Units 1 & 2 to reflect the new WCAP revision.

Respectfully submitted, b

  • Dave Morey MGE:maf RTITSS6. DOC Attachment oc: Mr. S. D. Ebneter Mr. B. L. Siegel Mr. T. M. Ross Dr. D. E. Williamson
  • C r ." A 1  ;

950918o162 950915 PDR ADOCK 05000348 P .PDR I