c' Boston Edison 10 CFR 50.73 Pilgnm Nuclear Power Station Rocky Hill Road l
Plymouth. Massachusetts 02360 i
l E. T. Boulette, PhD Senior Vce President - Nuclear september 5,1995 BECo Ltr. #95- 092 t
U.S. Nuclear Regulatory Commission Attn: Document Control Desk
- Washington, D.C. 20555 Docket No. 50-293 License No. OPR-35 The enclosed Licensee Event Report (LER) 95-007-00, " Simulated Automatic Actuation Test not Performed for the Automauc Depressurization System Prior to Plant Restart from Refuel Outage-10", is submitted in accordance with 10 CFR Part 50.73.
Within this report, the following commitment is made.
The procedure governing the Master Surveillance Tracking Program will be revised to provide enhanced guidance to reviewers of changes / revisions to the Master Surveillance Tracking Program.
Please do not hesitate to contact me if there are any questions regarding this report.
f E.T. Boulette, PhD 4
RLC/laa/9500700 cc:
Mr. Thomas T. Martin Regional Administrator, Region i U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Sr. NRC Resident inspector - Pilgrim Station 4
Standard BECo LER Distribution I
<ne 9509120231 950905
-S..._. _ A D O C K 05000293 hs PDR
,.PDR i
_._