ML20092B107

From kanterella
Jump to navigation Jump to search
Forwards Response to 840511 Proposed Civil Penalty Action EA 84-32 Re Improper Reactivity Control Noted in IE Insp Repts 50-259/84-02,50-260/84-02 & 50-296/84-02.Fees Being Wired to Nrc.Procedure Goi 100-12 Revised
ML20092B107
Person / Time
Site: Browns Ferry  Tennessee Valley Authority icon.png
Issue date: 06/11/1984
From: Mills L
TENNESSEE VALLEY AUTHORITY
To: Deyoung R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
References
EA-84-032, EA-84-32, NUDOCS 8406200059
Download: ML20092B107 (8)


Text

_ _ _ _ __ _

TENNESSEE VALLEY AUTHORITY b /E [

CH ATTANOOGA. TENNESSEE 374o1 3

400 Chestnut Street Tower II h[ [ _. 3 M Mr. R. C. DeYoung, Director bb Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission Washington, D.C. 20555

Dear Mr. DeYoung:

Enclosed is our response to J. P. O'Reilly's May 11, 1984 letter to H. G. Parris transmitting the Proposed Civil Penalty Action: EA 84-32, Improper Reactivity Control (IE Inspection Report Nos. 50-259/84-02,

-260/84-02, -296/84-02) for Browns Ferry Nuclear Plant which appeared to deviate from NRC commitments. We have enclosed our response to the Notice of Violations and Proposed Imposition of Civil Penalty. Fees in the response to the proposed civil penalty of $60,000 are being wired to the NRC, Attention:

Office of Inspection and Enforcement.

If you have any questions, please call Jim Domer at FTS 858-2725.

To the best of my knowledge, I declare the statements contained herein are complete and true. <

Very truly yours, TENNESSEE VALLEY AUTHORITY

. M. Mills, anager

'[

Nuclear Licensing Enclosure oc (Enclosure):

U.S. Nuclear Regulatory Commission Region II ATTN: James P. O'Reilly, Regional Administrator 101 Marietta Street, Suite 2900 Atlanta, Georgia 30323 Mr. R. J. Clark Browns Ferry Project Manager U.S. Nuclear Regulatory Commission 7920 Norfolk Avenue Bethesda, Maryland 20814 8406200059 840611 DR ADOCK 05000259 PDR

/6 ' / i t An Equal Opportunity Employer 9 '

. REVISED RESPONSE - PROPOSED PENALTY ACTION i IMPROPER REACTIVITY CONTROL (REFERENCE INSPECTION REPORT NOS.

50-259/ 84-02, 50-260/ 84-02, AND 50-296/ 84-02) l I

Enclosure 1 Item A i

Technical Specification 6.3.A requires that detailed written procedures be j prepared, approved and adhered to for the startup and shutdown of the i reactors.

I Contrary to the above, a memorandma was issued to shif t engineers on June i 9,1983, authorizing the use of the Rod Out Notch Override (RONOR) switch  !

during controlled shutdowns for all units. These instructions were used on  !

two occasions (September 6,1983 and January 6,1984) and were contrary to  !

approved procedures GOI 100-12 and 0I-85. The memorand.nu had not been '

approved by the Plant Operations Review Committee (PORC) or by the Plant Superintendent.

l .

This is applicable to all three units. '

l

1. Admission or Denial of the Violation TVA admits to.the violation. '

l 2. Reasons for the Vloistion if Admitted

( l At the time management issued the memorandum it was mistakenly f interpreted by management that the letter did not authorize any new i mode of operation of the ' emergency-in' switch. The letter was

, intended to clarify a question regarding existing procedures, not to 6 l authorize a new mode of operation other than allowed by GOI-100-12 and  :

l OI- 85. ,

v 3 Corrective Stens Which Have Been Taken and Results Achieved  !

The memorandum has been withdrawn and the procedure relating to the _

, RONOR switch has been revised. l l -

l 4. Corrective Stens Which Will Be Taken to Avoid Further Violations i

Other outstanding memorandums have been reviewed and there are none which authorize a different mode of operation than expressly permitted by the PORC-reviewed and Plant Superintendent-approved procedures.

i Discussions have been held with those managers involved in issuing the l 1etter to emphasize that procedures shall not be clarified by

  • memorandum, but shall be formally revised. I t

6 i

I T . _ . . _ _ _ . _ . _ _ _ _ _ _ _ _ _ _ _ , _ _ _ , _ _ _ _ 1___ Jb_ _ ._ _ _ _ L _. - T'i

- i I

5. Date When Full Como11ance Will Be Achieved Full compliance has been achieved. ,

Iten B 10 CFR 50.59(a)(1) permits the holder of a license for a reactor f acility l

to make changes in the procedures as described in the Safety Analysis

. Report without prior Commission approval ualess the change involves a  !

change in the Technical Specifications incorporated in the license or an i unreviewed safety question.

10 CFR 50.59(b) requires the licensee to maintain records of changes in (

procedures as described in the Final Safety Analysis Report (FSAR) and l Include a written safety evaluation which provides the basis for the dctermination that the change does not involve an unreviewed safety j que s tion.

Contrary to the above, the licensee issued a memorandum on June 9,1983, instituting use of the RONOR switch which rendered the Rod Sequence Control l System (RSCS) inoperable below 20 percent rated power contrary to Technical  !

Specification 3.3.B.3.a. Section 7.7 of the FSAR does not include in its  !

shutdown procedure description the use of the RONOR switch above 50 percent I rod density and below 20 percent. power. The modification to procedures by  :

lasuance of the June 9th memorandum was made without seeking prior Commission approval and without conducting an evaluation of the saf ety  ;

significance of the change in order to determine whether a change to ,

Technical Specifications or an unreviewed safety question was involved, i This is applicable to all three units.

1. Admission or Denial of the Allened Vloistion r TVA admits the violation.
2. Reasons for the Violations Since the memorandum was incorrect 1'y interpreted as not authorizing any  ;

new mode of operation a written safety evaluation was not performed nor was Commission approval sought.  ;

l 3. Corrective Stens Which Have Been Taken and Results Achieved OI-85 has been revised defining the use of the RONOR switch. The l

subject memorandum has been withdrawn.

l l .

l t 1

1 i

1 ,

4 l

4. Corrective Stens Which Will Be Taken to Avoid Further Violations Existing procedures require a written safety evaluation on issue of new procedures or revision to procedures authorizing a new mode of operation so no further corrective action is required.
5. Date When Full Como11ance Was Achieved Full compliance has been achieved.

Item C.1 Technical Specification 3.3.B.3.a requires that, whenever the reactor is in

  • the startup or run modes below 20 percent rated power, the RSCS shall be operable.
1. Contrary to the above, on January 6,1984, when Unit I reactor power l was being reduced from 12 percent power, the RSCS was rendered inoperable by moving control rods with the RONOR switch. The following improper rod moves were performed.
a. Control Rod 30-59 was moved out from notch 22 to 24 with the [

remaining group rods at notches 30, 24, 30, 26 and 26. l L

b. Control Rods 30-03, 06-27, 54-27, and 06-35 were individually and i continuously inserted from notch 24 to notch 0.

Admission or Denist of the Violation

1.  !

i TVA admits to the violation as stated.

2. Reasons for the Violation if Admitted ,

The unit 1 event on January 6,1984 was clearly outside the RSCS requiremests of Technical Specifications and the FSAR and outside the limitations of the administrative memorandum c6vering use of the  !

' emer gency-in' switch during controlled shutdowns.. At the time of the event, the unit had a half-scram an'd the reactor operator and the nuclear engineer were under the mistaken impression that an emergency existed. The reactor operator asked the nuclear engineer if the

' emergency-in' switch could be used; and the nuclear engineer erroneously agreed to rod moves that would not normally have been pe rforme d.

l l

o

.1

'J '

' -- - ~ '

- -- L. . . - _ . :_ _ _ _ - _

N.  !

3. Corrective Stens Which Have Been Taken and Results Achieved ,

i Af ter the half-scram was reset, the nuclear engineer reconsidered rod '

movements in light of experience reviews of other similar incidents.

He recognized that Technical Specifications had been violated without the existence of a true emergency and recommended a manual scram. i An administrative memorandum was issued January 12, 1984 that: (1) i restricted the use of the ' emerge ncy-in' switch to the correction of l RSCS notch logic errors only; (2) prohibited the bypassing of RWM if it j is operable, and (3) clearly identified reactor scrams as a possible and necessary action to rapidly reduce power. 01-85 was later revised [

to incorporate these restrictions. All of the reactor operators and j nuclear engineers were sent through supplemental training on February i 28, 1984 concerning this event and other problems and events at similar  ;

facilities.

4. Corrective Stens Which Will Be Taken to Avoid Further Violations 1

Specific use of the ' emergency-in' switch will be covered in the l I

operator requalification program and conjunction with 0I-85.

i

5. Date When Full Comn11ance Will Be Achieved I The Hot License Lesson Plan" revisions and operator requalification h training will be completed by December 14, 1984.

l Item C.2 [

2. Contrary to the above, on September 6,1983 during a Unit 3 controlled  ;

shutdown below 20 percent reactor power, the RSCS was rendered

! inoperable by moving control rods with the RONOR switch. The following

, improper rod moves were performed:

I

a. Control Rod 34-31 was moved out from notch 26 to 28 with the other '

group rods at notch 24.

l ,

-~ l l

i b. Control Rod 10-31 was moved in 'from notch 2 to 0 with group rod

  • 26-47 at notch 4, and then rod 10-31 was moved to notch 2.

l l c. Control Rod 02-31 was moved from notch 8 to 4 with the other group l rods at notch 8.

d. Control Rod 34-07 was moved from notch 6 to 2 with the other group [

rods at notch 6 and 4. l l t

!i h

I l .. ,. + , ,

a+n~w .-

,NN:'

w .- *

~~"

_ _ . - - - - . . - _ . . _ - - _ . - _ _ _ _ __ _ ,,__ - ,- -- ,__ _-- .. __ _ - . _ - _ , r

i

.? . Admission or Denial of the Violation

[ TVA admits to the violation.

I i

2. Reasons for the Violation if Admitted At the time of the Unit 3 shutdown on September 6,1983, the use of the

' emergency-in' switch to insert control rods had been evaluated and l mistakenly found to NOT render RSCS inoperable.

t l 3. Corrective Stens Which Have Been Taken and Results Achieved l

l The memorandum has been withdrawn and OI-85 has been revised to limit f the use of the ' emergency-in' switch in accordance with existing technical specifications.

i t 4. Corrective Stens Which Will Be Taken to Avoid Further Violations  ;

i TVA will seek approval of a more flexible definition of RSCS operability. Until Technical Specification changes are approved, TVA will continue using the existing technical specification operability definitions.

5. Date When Full Comellance Will Be Achieved i TVA is in full compliance with the present definition of RSCS  :

operability.

  • Item D +

Technical Specification 3.3.b.3.c requires that, when the reactor is in the startup or run modes below 20 percent rated power, the RWM shall be operable. When the RWM is inoperable, a second licensed operator shall be assigned the specific task of assuring adherence to the ccntrol rod program. -

7 Contrary to the above, on January 6,1984, when Unit 1 power was being reduced frem 12 percent power, the RWM was ' bypassed and rendered i Inoperable, and a second licensed operator did not assure adherence to the control rod program. Specifically, rod 30-59 was positioned at notch 22 versus required notch 24.

L I

l

  • , < ISh he a - 4M 4 = sr If 8 h

+

1. Admission or Denial of the Violation TVA admits the violation as stated.
2. Reasons for the Vloistion if Admitted i

The second licensed operator failed to verify the confonnance to the  !

4 RWM control rod program by allowing rods 30-59, 30-03, 06-27, 54-27, and 06-35, to be manipulated as described in item C.1. At the time of the event, the unit had a half-scram and the reactor operator and the nuclear engineer were under the mistaken impression that an emergency existed. The reactor operator asked the nuclear engineer if the

' emergency-in' switch could be used; and the nuclear engineer erroneously agreed to rod moves that wonid not normally have been perfonned.  ;

3. Corrective Stens Which Have Been Taken and Results Achieved After the half-scram was reset, the nuclear engineer reconsidered rod movements in light of experience reviews of other similar incidents.  ;

He recognized that Technical Specifications had been violated without ,

the existence of a true emergency and recommended a manual scram. The l shif t engineer directed the unit to be scrammed. ,

[

An administrative memorandna was issued January 12, 1984 that: (1) ,

restricted the use of the ' emergency-in' switch to the correction of RSCS notch logic errors only; (2) prohibited the bypassing of RWM if it i is operable, and (3) clearly identified reactor scrams as a possible l j and necessary action to rapidly reduce power. OI-85 was later revised ,

l to incorporate these restrictions. All of the reactor operators and j nuclear engineers were sent through supplemental training on February 28, 1984 concerning this event and other problems and events at similar facilities.  ;

4. Corrective Stees Which Will Be Taken to Avoid Further Violations , ,

Specific use of the emergency-in' '

switch will be covered in the l l operator requalification program in conjunction with OI-85.  !

l ,

l 5. Date When Full Comoliance Will Be Achieved The Hot License Lesson Plan revisions and operator requalification training will be completed by December 14, 1984.  ;

h l

1 i

4

,T ~s.h-

. .... .cw ,u 3[', ' $ '.

- . - . _ , . . . . , _ . _ . _ , , . _ _ , _, ___,.-__m - _ . - _ - . - . , - , _ . . . . . . . _ . _ - , _ - . , - . _ . _ , _ . , _ , _ _ - _ _ _ _ _ , . _ . _ , , - -

+

~ ,

{

Additional Information In the cover letter for these specific violations you requested that our response specifically address six areas of corrective action as follows:

i

1. Training of licensed operators includes adequate reviews of current  :

operational events and problems identified at other, sbailar i facilities.  !

i

2. Procedures required for the operation of the facility are adequate to achieve the intended result and that operators understand the need for i proper procedural adherence. i
3. The operator training program at Browns Ferry f acility instills the  !

i proper attitude toward reactor safety.

t

4. Proper administrative control is maintained for operating procedures. [

i

5. The flow of communication, i.e. , IE Notices and IE Bulletins, both from i

the plant and the corporate level, is prompt.  !

6. TVA, both at the corporate and plant management level, 'id'entifies root l causes for problems and takes comprehensive action to prevent their l

recurrence. t l t A number of these areas have already been addressed in the responses to the violations. In addition we are providing the following srpplemental '

information.

i Items 2 and 4, are addressed in response to items A and B. Our training  !

program now instills the proper attitude toward reactor safety and l procedural adherence. ' In our review of these events any attitude to the i l contrary was not exhibited. Upper management discussions with selected t j operators have confirmed that the proper attitude exists. I

! u The operating experience review is generally adequate, but as evidence by l l this event, improvement is warranted. Through our Regulatory Performance '

l l Improvement Program, we have provided for f aster dissemination of very  !

Important events through live-time training. We are also persuing, through  !

our present reorganization, providing for more timely review of operating ,

events. '

i We believe that the sua total of the tasks included in the Regulatory Performance Improvement Program and the proposed reorganizational changes will not only enhance identification of root causes and appropriate -

corrective action, but will allow TVA to head of f and prevent problems before they occur.

i i i I

4 e-

-.___--_--__.__'*___,_-----.,__-_.--._ . 6 4. se r4 m e. hpg -

Ci Q

_ _ _ _ _ _ - -