JOSEPH M. FARLEY NUCLEAR PLANT UNIT 2 NARRATIVE

SUMMARY

OF OPERATIONS APRIL, 1984 During the month of April, there was one (1) automatic shutdown which occurred on April 9,1984.

The following safety-related maintenance was performed in the month of April:

1.

Performed miscellaneous maintenance on diesel generators.

2.

Replaced A RCP seal injection filter.

l i

L l

8406070199 840430 DRADOCK05000g i

1 i

469 L

DOCKET NO. 364 i'

UNIT 2

May 8, 1984 DATE COMPLETED BY W.G. Hairston. III TELEPHONE (9nsi non-sisr, April, 1984

.%t0tml DAY-AVERACE DA!LY POWER LEVEL DAY' AVERAGE DAILY POWER LEVEL (AlWe Net)

(MWe Net) 330 g7 828 g,

2 R2R 13 R77 822 3

g9 821 4

822 20 817 827 814

,3 21 6

827 n

809 819 7

A?O 23 g

823

4 823 9

363 25-821 396 818 10 26 33 826 n

826 12 A?'

23 ann 13 823 29 80 8 811 14 820 30 827 Is 3g 16 827 i

(?imL*CLONS l

On tiiis form:t. list the :ve sg: daiy umt power icvelin MWe Net fut e:ch cy in the reporting rnunth. Campute to

, the ne:re t whuie me;: watt.

(9/77) a

.._,___.....,..,.m______._

,____._,___r_

-...~...,

OPERATLNG DATA REPORT DOCKET NO.

50-364 DATE May 8.

1984 COMPLETED BY u _ r' uni rston III TELEPl!ONE (2051 899-5156 OPERATING STATUS

1. Unit Name:

Joseph M. Farley - Unit 2 Notes

2. Reporting Period:

April, 1984

1) Cumulative data since 2652 7-30-81, date of
3. Licensed Thermal Power (MWt):

860 commercial operation.

4. Nameplate Rating (Gross MWe):
5. Design Electrical Rating (Net MWe):

A?O

6. Maximurn Dependable Capacity (Gross MWe):

R57 5

7. Maximum Dependable Capacity (Net MWe):

809.1

8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report, Give Reasons:

N/A

9. Power Level To Which Restricted. If Any (Net MWe):

N/A

10. Reasons For Restrictions,if Any:

N/A This Month Yr.-to Date Curnulatne

11. Ilours in Reporting Period 719 2 901 24.144
12. Number Of liours Reactor Was Critical 708.3 2.856.0 21.398.8
13. Reactor Reserve Shutdown lloun 0.0 0.0 138.0
14. Ilours Generator On-Line 704.5 2,807.7 21,106.5
15. Unit Reserve Shutdown IIours nn 0.0 0.0
16. Gross Thermal Energy Generated (MWil) 1 R45.190 7.298.586 52.636.430
17. Gross Electrical Energy Generated (MWII) 597.574 2.384,342 17.371.218
18. Net Electrical Energy Generated (MWil) 569.044 2,268,744 16,468,770
19. Unit Service Factor 98.0 96.7 87.4
20. Unit Availability Factor 98.0 os y 87.4
21. Unit Capacity Factor (Using MDC Net) 97.8 96.6 84.3 95.5 94,3 82.3
22. Unit Capacity Factor (Using DER Net) 2.0
23. Unit Forced Outage Rate 3.3 5.1
24. Shutdowns Scheduled Oser Next 6 Months (Type. Date, and Duration of Each t:

N/A

25. If Shut Down At End Of Report Period. Estimated Date of Startup:

N/A

26. Units in Test Status (Prior to Commercial Operation):

Forecast Achiesed INITIA L CRITICALITY

A R1 5_g_n1 INIIIA L ELECTRICITY 5-24-81 5-25-81 COMMERCIAL OPERATION 8-1-81 7-30 to/77

1

\\

DOCKET NO.

~ 50-364 UNIT SilU1 DOWNS AND POWER REDUCTIONS UNII N AhlE J.M. Farlev - Unit 2 DATE May 8, 1954 COSIPLETED tlY L7 C-Unircenn IIIs REPORT Af 0NIII April, 1984 TELEPIIONE (205) 899-5156 E E

'h fE Lh.ensee E-r, Cause & Correceive No.

Date R

~g js5 Event g

gu3 Action to mU Psevent Recurrence f5 5

~ jj =?

Report a u

W g

o 6

l 005 840409

?

14.5 G

3 84-005-00 N/A N/A Reactor trip due to improper per-formance of surveillance test.

l l

I 1

I 1

2 3

4 1 I orted Renon:

hiethod:

Exhibit G - Inst ructions S: St heduled A l~quipment Failure (Explain) 1 hlanual for Picp:uation of Data ll.hlaintenance of Test 2 hfannal Scram.

Entiy Sheeis for I.itensee C Hefueling 3 Automatic Sesam.

Esent Repint (i.ER)IileiNtlHl:G-i l

l} Hegulainay Restsie lion 4 Other (Explain) 0161) l 1 -Oper stor Tsaining & IJcense Examination F Administiative 5

l G Opcutional Lnor (lixplain) lishibit I - Same Sousee i

l's/77)

II 01hei (Explain) l

E

.s

[

Malling Address Alabama Power Company 600 North 18th Street Post Office Box 2641 Birmingham, Alahama 35291 Telephone 205 783-G090 -

A e

"dsE$"x*Euannuun AlabamaPower nintndge Build.n9 Senior Vice President n:v -

~cs May 11, 1984 Docket No. 50-364 Director, Office of Management Information and Program Control U. S. Nuclear Regulatory Comission Washington, D.C.

20555

Dear Sir:

RE: Joseph M. Farley Nuclear Plant Unit 2 Monthly Operating Data Report Attached are two (2) copies of the April 1984 Monthly Operating Report for Joseph M. Farley Nuclear Plant, Unit 2, required by Section 6.9.1.10 of Appendix A of the Technical Specifications.

As requested by letter from Mr. John F. Stolz to Mr. Alan R. Barton, dated October 21, 1977, a

" Narrative Summary of Operating Experience" is included in the attached report.

If you have any questions, please advise.

Yours very

uty, R. P. Mcdonald RPM /KWM: sam Enclosures xc: Mr. Ted Cintula (1 copy)

Director, IE (10 copies)

Director, RII (1 copy) 9 9