JOSEPH M. FARLEY NUCLEAR PLANT UNIT 2 NARRATIVE
SUMMARY
OF OPERATIONS APRIL, 1984 During the month of April, there was one (1) automatic shutdown which occurred on April 9,1984.
The following safety-related maintenance was performed in the month of April:
1.
Performed miscellaneous maintenance on diesel generators.
2.
Replaced A RCP seal injection filter.
l i
L l
8406070199 840430 DRADOCK05000g i
1 i
469 L
DOCKET NO. 364 i'
UNIT 2
May 8, 1984 DATE COMPLETED BY W.G. Hairston. III TELEPHONE (9nsi non-sisr, April, 1984
.%t0tml DAY-AVERACE DA!LY POWER LEVEL DAY' AVERAGE DAILY POWER LEVEL (AlWe Net)
(MWe Net) 330 g7 828 g,
2 R2R 13 R77 822 3
g9 821 4
822 20 817 827 814
,3 21 6
827 n
809 819 7
A?O 23 g
823
- 4 823 9
363 25-821 396 818 10 26 33 826 n
826 12 A?'
23 ann 13 823 29 80 8 811 14 820 30 827 Is 3g 16 827 i
(?imL*CLONS l
On tiiis form:t. list the :ve sg: daiy umt power icvelin MWe Net fut e:ch cy in the reporting rnunth. Campute to
, the ne:re t whuie me;: watt.
(9/77) a
.._,___.....,..,.m______._
,____._,___r_
- -...~...,
OPERATLNG DATA REPORT DOCKET NO.
50-364 DATE May 8.
1984 COMPLETED BY u _ r' uni rston III TELEPl!ONE (2051 899-5156 OPERATING STATUS
- 1. Unit Name:
Joseph M. Farley - Unit 2 Notes
- 2. Reporting Period:
April, 1984
- 1) Cumulative data since 2652 7-30-81, date of
- 3. Licensed Thermal Power (MWt):
860 commercial operation.
- 4. Nameplate Rating (Gross MWe):
- 5. Design Electrical Rating (Net MWe):
A?O
- 6. Maximurn Dependable Capacity (Gross MWe):
R57 5
- 7. Maximum Dependable Capacity (Net MWe):
809.1
- 8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report, Give Reasons:
N/A
- 9. Power Level To Which Restricted. If Any (Net MWe):
N/A
- 10. Reasons For Restrictions,if Any:
N/A This Month Yr.-to Date Curnulatne
- 11. Ilours in Reporting Period 719 2 901 24.144
- 12. Number Of liours Reactor Was Critical 708.3 2.856.0 21.398.8
- 13. Reactor Reserve Shutdown lloun 0.0 0.0 138.0
- 14. Ilours Generator On-Line 704.5 2,807.7 21,106.5
- 15. Unit Reserve Shutdown IIours nn 0.0 0.0
- 16. Gross Thermal Energy Generated (MWil) 1 R45.190 7.298.586 52.636.430
- 17. Gross Electrical Energy Generated (MWII) 597.574 2.384,342 17.371.218
- 18. Net Electrical Energy Generated (MWil) 569.044 2,268,744 16,468,770
- 19. Unit Service Factor 98.0 96.7 87.4
- 20. Unit Availability Factor 98.0 os y 87.4
- 21. Unit Capacity Factor (Using MDC Net) 97.8 96.6 84.3 95.5 94,3 82.3
- 22. Unit Capacity Factor (Using DER Net) 2.0
- 23. Unit Forced Outage Rate 3.3 5.1
- 24. Shutdowns Scheduled Oser Next 6 Months (Type. Date, and Duration of Each t:
N/A
- 25. If Shut Down At End Of Report Period. Estimated Date of Startup:
N/A
- 26. Units in Test Status (Prior to Commercial Operation):
Forecast Achiesed INITIA L CRITICALITY
- A R1 5_g_n1 INIIIA L ELECTRICITY 5-24-81 5-25-81 COMMERCIAL OPERATION 8-1-81 7-30 to/77
1
\\
DOCKET NO.
~ 50-364 UNIT SilU1 DOWNS AND POWER REDUCTIONS UNII N AhlE J.M. Farlev - Unit 2 DATE May 8, 1954 COSIPLETED tlY L7 C-Unircenn IIIs REPORT Af 0NIII April, 1984 TELEPIIONE (205) 899-5156 E E
'h fE Lh.ensee E-r, Cause & Correceive No.
Date R
~g js5 Event g
gu3 Action to mU Psevent Recurrence f5 5
~ jj =?
Report a u
W g
o 6
l 005 840409
?
14.5 G
3 84-005-00 N/A N/A Reactor trip due to improper per-formance of surveillance test.
l l
I 1
I 1
2 3
4 1 I orted Renon:
hiethod:
Exhibit G - Inst ructions S: St heduled A l~quipment Failure (Explain) 1 hlanual for Picp:uation of Data ll.hlaintenance of Test 2 hfannal Scram.
Entiy Sheeis for I.itensee C Hefueling 3 Automatic Sesam.
Esent Repint (i.ER)IileiNtlHl:G-i l
l} Hegulainay Restsie lion 4 Other (Explain) 0161) l 1 -Oper stor Tsaining & IJcense Examination F Administiative 5
l G Opcutional Lnor (lixplain) lishibit I - Same Sousee i
l's/77)
II 01hei (Explain) l
E
.s
[
Malling Address Alabama Power Company 600 North 18th Street Post Office Box 2641 Birmingham, Alahama 35291 Telephone 205 783-G090 -
A e
"dsE$"x*Euannuun AlabamaPower nintndge Build.n9 Senior Vice President n:v -
~cs May 11, 1984 Docket No. 50-364 Director, Office of Management Information and Program Control U. S. Nuclear Regulatory Comission Washington, D.C.
20555
Dear Sir:
RE: Joseph M. Farley Nuclear Plant Unit 2 Monthly Operating Data Report Attached are two (2) copies of the April 1984 Monthly Operating Report for Joseph M. Farley Nuclear Plant, Unit 2, required by Section 6.9.1.10 of Appendix A of the Technical Specifications.
As requested by letter from Mr. John F. Stolz to Mr. Alan R. Barton, dated October 21, 1977, a
" Narrative Summary of Operating Experience" is included in the attached report.
If you have any questions, please advise.
Yours very
- uty, R. P. Mcdonald RPM /KWM: sam Enclosures xc: Mr. Ted Cintula (1 copy)
Director, IE (10 copies)
Director, RII (1 copy) 9 9